Hollyberry Props 4 (Pty) Ltd (In Liquidation) v Hisuper Trading CC and Others (43073/2014) [2015] ZAGPJHC 108 (29 May 2015)

80 Reportability
Commercial Law

Brief Summary

Eviction — Commercial lease — Termination of lease and eviction of occupants — Applicant sought eviction of first and second respondents from commercial premises following non-payment of rent and failure to comply with sale agreement — First respondent occupied premises under a lease that lapsed, while second respondent took occupation under a sale agreement that was subsequently cancelled due to breaches — Legal issue arose regarding the applicant's ownership of the property and the validity of the cancellation notice — Court held that the applicant was entitled to evict the respondents as they failed to remedy breaches of the lease and sale agreements, and the cancellation of the sale agreement was valid.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an application for the eviction (ejectment) of the first and second respondents, together with all persons occupying through them, from certain commercial/industrial premises described as Erf 132 Chamdor, Krugersdorp, more commonly known as 38 Van Eck Street, Chamdor.


The applicant was Hollyberry Props 4 (Pty) Ltd (in liquidation). The first respondent was Hisuper Trading CC and the second respondent was Africa Land Properties (Pty) Ltd. The third respondent was the Mogale City Local Municipality, cited due to its connection to municipal charges and services relevant to occupation, although the dispute in substance concerned the rights of occupation between the applicant and the first two respondents.


The matter was initially opposed on several grounds. By the time of hearing before Francis J, the opposition was narrowed to two defences. The first defence was that the applicant was allegedly not the registered owner and that the bondholder (Investec Bank) ought to have been joined. The second defence was that the sale agreement had allegedly not been validly cancelled because the contractual breach notice and cancellation did not comply with a requirement of dispatch by registered post under clause 11.


The general subject-matter of the dispute concerned the termination of contractual rights to occupy commercial premises, first under a fixed-term lease and later under an offer to purchase/sale agreement concluded with the applicant’s provisional liquidators, and whether the respondents’ continued occupation was unlawful following effluxion of time and cancellation.


2. Material Facts


On 8 March 2013 the applicant and the first respondent concluded a written lease agreement in terms of which the first respondent leased the commercial premises for furniture manufacturing. The lease ran for one year, commencing 1 May 2013 and terminating 30 April 2014, at a rental of R130 000 per month excluding VAT, payable monthly in advance.


It was common cause that the first respondent took occupation and remained in occupation up to and beyond the expiry date. The lease lapsed by effluxion of time on 30 April 2014 and was not extended. The court accepted the applicant’s case that the first respondent had ceased making payments for rental and related charges during the lease period and was materially in arrears, with the applicant alleging an indebtedness of R1 721 573.40 for the period July 2013 to April 2014. The respondents disputed indebtedness and asserted that rental compliance ceased after the death of one of the applicant’s directors, while also referring to defects at the premises and repairs allegedly undertaken by them; however, the judgment treated the decisive facts as the termination of the lease by time and the absence of any extant right to occupy thereafter.


While the first respondent was still in occupation, and after the applicant had been liquidated, the second respondent (represented by Mr JianLiang Li, who was also a member of the first respondent) signed an offer to purchase the premises, accepted on 14 January 2014 by the applicant’s provisional liquidators. The purchase price was R11 000 000.00, with a 10% deposit of R1 100 000.00 payable on the effective date, and the balance payable against registration of transfer, secured by bank guarantees deliverable within 30 days of the effective date.


The sale agreement contemplated that if the second respondent took occupation before transfer, it would pay interest/occupational amounts and assume responsibility from occupation for municipal charges and other outgoings associated with the premises. The second respondent took occupation on or about 1 May 2014, after the lease expired. The applicant alleged that the second respondent failed to pay occupational rent and related charges, being indebted in the sum of R572 050.11 as at August 2014. It was further undisputed that the second respondent did pay the deposit but failed to provide the required bank guarantees for the balance within the contractually stipulated time.


The applicant’s attorneys addressed letters dated 3 September 2014 and 26 September 2014 recording alleged arrears, demanding payment, and (as to the second respondent) giving notice of breach in terms of clause 11 requiring remedy within 10 days. After discussions failed, the applicant informed the second respondent that the sale agreement was cancelled and, in a letter dated 9 October 2014, stated that the agreement was cancelled and demanded that the premises be vacated within 48 hours.


The respondents admitted receiving the relevant letters, including the breach notice and the cancellation communication, but contended that cancellation was invalid because the notices were not shown to have been dispatched by registered post as clause 11 required. The respondents also contended that the applicant was not the owner because Investec Bank was the bondholder, and on that basis alleged a non-joinder.


The court treated the premises as commercial premises in an industrial area, and the respondents did not persist with reliance on the Prevention of Illegal Eviction from and Unlawful Occupation of Land Act 19 of 1998 (PIE) as a defence.


3. Legal Issues


The central legal questions the court was required to determine were whether, notwithstanding the respondents’ continued occupation, the applicant had established a right to evict the respondents based on the termination of contractual occupation rights, and whether either of the two remaining defences defeated that claim.


The first issue was a question of law applied to largely common cause facts, namely whether a bondholder has an interest amounting to ownership or such a direct and substantial interest as to require joinder, and whether the applicant, as owner (in liquidation), could seek eviction without joining the bondholder.


The second issue concerned the application of contractual principles to fact: whether the sale agreement was validly cancelled in light of clause 11 requiring a breach notice dispatched per registered post, where the respondents admitted actual receipt of the breach notice and cancellation letter, but proof of registered post dispatch was not produced and delivery appeared to have occurred by hand.


A further contextual issue, although ultimately not pursued by the respondents, was whether the dispute engaged PIE; this was treated by the court as falling outside PIE because the property was commercial rather than residential.


4. Court’s Reasoning


On the non-joinder point, the court rejected the proposition that Investec Bank, as bondholder, was the owner of the premises. The court characterised the bondholder’s interest as that of a secured creditor, not ownership, and held that the bond did not confer upon the bank the status of owner or a basis to insist on being joined merely because of the existence of a mortgage bond. In support of this conclusion the court referred to Gainsford and Others NNO v Tanzer Transport (Pty) Ltd 2014 (3) SA 468 (SCA), which the court treated as authority for the proposition that the bondholder’s interest is security for debt rather than ownership of the property. On this basis the court found no merit in the defence and held that the applicant was entitled to pursue eviction without joining Investec Bank.


On the cancellation point, the court focused on the content of clause 11 of the sale agreement, which entitled an aggrieved party to cancel if the defaulting party remained in breach for 10 days after dispatch per registered post of a written notice to remedy. The court then evaluated the undisputed admissions by Mr Li on behalf of the respondents: he admitted receipt of the letters placing the second respondent in mora and the subsequent cancellation letter, although disputing the accuracy of their contents and contesting the formal mode of dispatch.


The court accepted that there was no proof before it that the letters were dispatched by registered post, but found that the letters appeared to have been hand-delivered, and that receipt was acknowledged. The court treated the purpose of the notice requirement as being met because the respondents were informed of the breach, were afforded the contractually stipulated period to remedy, failed to do so, and then received written notice that the agreement was cancelled.


In addressing authorities relied on by the respondents, the court considered them either irrelevant to the issues it had to decide or supportive of the proposition that actual receipt may cure objections related to the mode of delivery. The court stated that Minister of Land Affairs and Agricultural and Others v D & F Wevell Trust and Others 2008 (2) SA 184 (SCA) was not relevant because it concerned reliance on uncanvassed material in annexures in motion proceedings rather than the validity of breach notices in a cancellation context. The court regarded reliance on First National Bank of SA Ltd v Ganyesa Bottle Store (Pty) Ltd and Others; First National Bank of SA Ltd v Schweizer Drankwinkel (Pty) Ltd and Another 1998 (4) SA 565 (NC) as misplaced because that matter dealt with knowledge of a summons that had not been served. The court referred to Kragga Kamma Estates and Another v Flanagan [1994] ZASCA 137; 1995 (2) SA 367 (A) as dealing with mora and cancellation requirements, and treated Sandton Square Finance (Pty) Ltd and Others v Biagi, Bertola and Vasco and Another 1997 (1) SA 258 (W) and SA Wimpy (Pty) Ltd v Tzouras 1977 (4) SA 244 (W) as illustrating that where notice is received, the method of delivery is not necessarily decisive for validity. The court articulated the conclusion (with reference to SA Wimpy) that, provided there is proof the notice was received, “it matters not how the notice was given”.


Applying these principles, the court concluded that there had been compliance with clause 11. The breach notice of 26 September 2014 (admittedly received) identified the breach and allowed 10 days to remedy. The cancellation letter of 9 October 2014 (also admittedly received) recorded failure to remedy and communicated cancellation. The court therefore found the sale agreement validly cancelled and held that the respondents had no remaining legal basis to occupy the premises.


Having found that the lease had ended by effluxion of time and that the sale agreement had been cancelled following breach, the court characterised the respondents’ continued occupation as unlawful, entitling the applicant to eviction. The court also recorded that PIE did not apply given the commercial/industrial nature of the premises and that this defence was abandoned.


On costs, the court distinguished between two phases. An earlier urgent application had been struck from the roll on 9 December 2014 for lack of urgency, with costs reserved. The court held the applicant had not made out urgency and should bear those reserved costs on the party-and-party scale. As to the costs of the present application, the court found the respondents’ opposition to be frivolous and doomed to fail, warranting costs against them on an attorney and own client scale (attorney-and-client type scale), excluding the reserved costs from the earlier urgent appearance.


5. Outcome and Relief


The court granted an eviction order directing the first and second respondents and all those occupying through them to vacate the premises by 14h00 on 5 June 2015. The court further authorised the sheriff, with assistance from the South African Police, to enter and evict the occupants if they failed or refused to vacate by that deadline.


As to costs, the court ordered that the first and second respondents pay the costs of the application jointly and severally on the scale of attorney and own client, excluding the costs reserved on 9 December 2014. The reserved costs relating to the striking from the urgent roll were ordered to be paid by the applicant to the first and second respondents on a party-and-party basis.


Cases Cited


Gainsford and Others NNO v Tanzer Transport (Pty) Ltd 2014 (3) SA 468 (SCA).


Minister of Land Affairs and Agricultural and Others v D & F Wevell Trust and Others 2008 (2) SA 184 (SCA).


First National Bank of SA Ltd v Ganyesa Bottle Store (Pty) Ltd and Others; First National Bank of SA Ltd v Schweizer Drankwinkel (Pty) Ltd and Another 1998 (4) SA 565 (NC).


Kragga Kamma Estates and Another v Flanagan [1994] ZASCA 137; 1995 (2) SA 367 (A).


Sandton Square Finance (Pty) Ltd and Others v Biagi, Bertola and Vasco and Another 1997 (1) SA 258 (W).


SA Wimpy (Pty) Ltd v Tzouras 1977 (4) SA 244 (W).


Legislation Cited


Land Reform (Labour Tenants) Act 3 of 1996.


Extension of Security of Tenure Act 62 of 1997.


Prevention of Illegal Eviction from and Unlawful Occupation of Land Act 19 of 1998.


Rules of Court Cited


No specific rules of court were cited in the judgment.


Held


The court held that the applicant was entitled to evict the first and second respondents because the first respondent’s lease had terminated by effluxion of time and the second respondent’s sale agreement had been validly cancelled after breach and failure to remedy within the stipulated period.


The court held that Investec Bank, as bondholder, was not the owner of the premises and had no interest requiring joinder in the eviction proceedings.


The court held that, despite the absence of proof that the breach notice was dispatched by registered post as described in clause 11, the admitted receipt of the breach notice and cancellation letter meant that the contractual notice purpose was satisfied and that there had been sufficient compliance to found a valid cancellation.


The court held that PIE did not apply because the premises were commercial premises in an industrial area and the defence based on PIE was not persisted with.


LEGAL PRINCIPLES


A mortgage bondholder’s interest is that of a secured creditor and does not, by virtue of the bond alone, make the bondholder the owner of the property; non-joinder will not succeed merely because a bondholder exists where no direct ownership interest is established.


Where a contract requires that a breach notice be dispatched in a particular manner (here, per registered post), the court approached the issue by emphasising the significance of actual receipt and the substantive function of the notice, namely to place the defaulting party in mora and afford an opportunity to remedy, followed by communication of cancellation upon non-remedy.


Upon termination of a fixed-term lease by effluxion of time, and upon valid cancellation of a subsequent agreement conferring occupational rights, continued occupation of commercial premises becomes unlawful, entitling the owner (or party with the right to vindicate possession) to ejectment/eviction.


Costs may be awarded on a punitive scale such as attorney and own client where the court considers opposition to have been frivolous or without merit, while costs consequences from prior interlocutory/urgent proceedings may be allocated separately according to the court’s assessment of urgency and conduct.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2015
>>
[2015] ZAGPJHC 108
|

|

Hollyberry Props 4 (Pty) Ltd (In Liquidation) v Hisuper Trading CC and Others (43073/2014) [2015] ZAGPJHC 108 (29 May 2015)

IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG
LOCAL DIVISION, JOHANNESBURG)
Case
No: 43073/2014
DATE:
29 MAY 2015
In
the matter between:
HOLLYBERRY
PROPS 4 (PTY) LTD (IN
LIQUIDATIO)
..................................................
Applicant
And
HISUPER
TRADING
CC
...............................................................................................
1st
Respondent
AFRICA
LAND PROPERTIES (PTY)
LTD
...............................................................
2nd
Respondent
MOGALE
CITY LOCAL
MUNICIPALITY
...............................................................
3rd
Respondent
JUDGMENT
FRANCIS
J
1.
This is an application for an order that the first and second
respondents and all those who occupy the premises known as Erf
132
Chamdor Krugersdorp, and more commonly known as 38 Van Eck Street,
Chamdor (the premises), which are commercial premises, under
and by
virtue of the first and second respondents’ occupancy be
evicted from the premises with immediate effect.
2.
The application was initially opposed on several grounds. However
when the matter came before me, the challenge was limited
only to two
grounds. The first is that the applicant is not the registered owner
of the property and the second is that the sale
agreement was not
lawfully terminated in that the applicant had not given notice by
registered post of the mora and cancellation
in
terms of clause 11 of the agreement of sale.
3.On
8 March 2013, the applicant and the first respondent entered into a
written agreement of lease (the lease agreement) in respect
of the
premises. The lease agreement provided that the premises was leased
by the first respondent from the applicant on terms
and conditions
set forth in the schedule A to the agreement for the purposes of
manufacturing of furniture. The terms of the lease
agreement were
inter alia that the first respondent leased from the applicant the
premises. The period of the lease agreement
was for a period of 1
year commencing from 1 May 2013 and terminating on 30 April 2014.
The monthly rental payable by the first
respondent to the applicant
for the premises was R130 000.00 excluding VAT per month for the
duration of the lease period. The
rental would be payable in advance
on or before the first day of each and every successive calendar
month into the applicant’s
bank account.
4.The
first respondent took occupation of the premises in term of the lease
agreement and continued to remain in occupation as at
30 April 2014,
at which time the lease agreement lapsed due to the effluxion of
time. The first respondent did not attempt to
extend the lease
agreement for a further period of 1 year. The first respondent had
ceased making payments in respect of rental,
electricity, water and
sewerage during the currency of the lease for the period July 2013 to
April 2014 and is currently indebted
to the applicant in the amount
of R1 721 573.40.
5.
Whilst the first respondent was still in occupation of the premises,
and on 14 January 2014 after the applicant had been liquidated,
the
second respondent also duly represented by JianLiang Li (Li) who is
also the director of the second respondent and a member
of the first
respondent signed an Offer to Purchase the premises (the sale
agreement), which offer was accepted by Juanito Martin
Damons, Lilly
Mampina Malatsi-Teffo, Mthebaleng Christina Morobane and the
applicant as the provisional liquidators of the applicant.
6.
The material express terms of the sale agreement were inter alia, the
following:
6.1
The purchase price of the premises is the sum of R11 000 000.00.
6.2
A cash deposit of 10%, being R1 100 000.00 was to be paid by the
second respondent on the effective date, being 14 January 2014.
6.3
The full balance of the purchase price was payable against
registration of transfer of the premises and was to be secured by

bank guarantees acceptable to the applicant, payable at Johannesburg
free of exchange upon registration of transfer of the premises
and
would be delivered to
the
transferring attorneys or its nominee within 30 days of the effective
date.
6.4
In the event that the second respondent took occupation before
registration of transfer:
6.4.1
The second respondent would pay interest on the full purchase price
from date of occupation to date of registration of transfer,

calculated at 12% per annum, both days inclusive. The interest would
be payable in advance in the sum of R110 000.00 before or
on the
first of the month following occupation to thetransferring attorneys.
6.4.2
From the date of occupation, all benefits and risks in respect of the
premises would pass to the second respondent and the
second
respondent would be liable for any rates and taxes, and water and
electricity and any other municipal charges and imposts
levied
against the premises. The second respondent would also be liable for
all insurance premiums and any and all charges and
imposts with
regards to the premises.
6.5
Should any party fail to comply with any of the terms and conditions
of the sale agreement and remain in default for a period
of 10 (ten)
days after dispatch per registered post of written notice requiring
any default to be remedied, the aggrieved party
would be entitled, in
addition to and without prejudice to any other rights available at
law, to cancel the sale agreement forthwith
and retain all moneys
paid by the second respondent as “Rouwkoop” by way of
liquidated damages or enforce performance
of the terms of the sale
agreement.
7.
Prior to the registration of transfer, and on or about 1 May 2014,
and after the expiry of the lease agreement with the first

respondent, the second respondent took occupation of the premises.
The second respondent as a result of the sale agreement became
liable
from that date for payment of occupational rent and all rates and
taxes, water and electricity and any other municipal charges
and
imposts levied against the premises. The second respondent also
became liable for all insurance premiums with regards to the

premises.
8.
The applicant through its attorneys addressed a letter to Li on or
about 3 September 2014, attaching a schedule setting out the
various
amounts owed by the first respondent in respect of rental,
electricity, water and sewerage under the lease agreement, and
which
had not been paid during the currency of the lease for the period
July 2013 to April 2014 in the sum of R1 721 573.40.
9.
On or about 26 September 2014 the applicant through its attorneys
addressed a further letter to the first respondent demanding
the sum
of R1 721 573.40 within seven days, failing which the applicant would
proceed to take such steps as may be necessary to
protect its rights,
the costs of which would be for the first respondent’s account.
There was no response to the letter
and the amount remains
outstanding. Similarly in relation to the second respondent,
notwithstanding the fact that it took occupation
of the premises on
or about 1 May 2014, the second respondent has failed to make any
payment to the applicant for occupational
rental, water, electricity,
sewerage, and rates and as at August 2014 was indebted to the
applicant in the sum of R572 050.11.
10.The
applicant, through its attorneys, addressed a letter to the second
respondent, represented by Li on 3 September 2014, attaching
a
schedule which sets out the various amounts owed by the second
respondent for the period May 2014 to August 2014 to the applicant
in
respect of occupational rental, water and electricity, sewerage, and
rates, which were not paid during the currency of sale
agreement,
prior to its cancellation, the total being R572 050.11.
11.
In addition to the above breach of the sale agreement, the second
respondent also failed to procure and make available to the
applicant
the bank guarantees in terms of clause 4.2 of the sale of agreement,
which were to be procured within 30 days of the
effective date.
Although the deposit of R1 100 000.00 was paid by the second
respondent, it did not make available the required
guarantees for the
balance of the purchase price for the premises.
12.
On or about 26 September 2014, the applicant through its attorneys
addressed a letter to the second respondent wherein the applicant

gave notice to the second respondent in terms of clause 11 of the
sale agreement that the second respondent was in breach of the
sale
agreement and that the second respondent was required to remedy its
defaults within a period of 10 days of the date of dispatch
of the
letter in terms of which the second respondent was called upon to
make payment to the applicant in the sum of R572 050.11
in respect of
occupational rental and various consumables and the second respondent
was called upon to provide the applicant with
the bank guarantees
required to be obtained by it, to secure the balance of the purchase
price in terms of clause 4.2 of the sale
agreement.
13.
Following the letters of demand dated 3 and 26 September 2014 to the
first and second respondents, the applicant and second
respondent
engaged in without prejudice discussion and no agreement could be
reached on the resolution of the issues. These discussions

culminated in the second respondent being verbally informed by Len
Vorster of the applicant’s attorney on 9 October 2014
that the
sale agreement was cancelled and that the second respondent had 48
hours to vacate the property.
14.On
or about 9 October 2014 the applicant’s attorneys addressed a
letter to the second respondent stating that the second
respondent
had failed to meet any of the demands set out in the applicant’s
letter dated 26 September 2014 within the time
period afforded to it
therein. The letter further stated that settlement discussions held
on that same day between the applicant
and the second respondent had
been unsuccessful and that accordingly the sale agreement signed on
14 January 2014 was thereby cancelled
in accordance with clause 11 of
the sale agreement and that the second respondent had 48 hours within
which to vacate the premises.
15.
On or about 11 October 2014 the applicant’s attorney received a
letter from the second respondent’s than attorney
indicating
that to meaningfully advise the second respondent, and taking into
account the applicant’s demand to
vacate
the premises in its letter dated 9 October 2014, it requested that
the applicant’s attorneys furnish it with a copies
of the sale
agreement and all copies of documents pertaining to the matter which
bears any impact in the second respondent. They
requested that the
demand that the second respondent vacate the property be held over
until the attorneys had received the requested
documentation and was
able to advise its clients of its rights.
16.
On or about 13 October 2014 the applicant’s attorneys responded
to the second respondent’s attorneys letter and
provided a copy
of the sale agreement; the letter of demand dated 26 September 2014
and the letter to vacate the premises dated
9 October 2014. It
advised that any further documentation or correspondence would be in
the second respondent’s possession
and that they did not agree
to hold over the demand for the second respondent to vacate the
premises.
17.
The parties failed to reach an agreement on the resolution of the
issues. The first and second respondents have failed to vacate
the
premises or to make payment to the applicant of any amounts which are
currently due and owing to it.
18.
The application was opposed by the first and second respondents and
Li stated that he is the owner of both respondents. He
manages a
furniture manufacturing company, producing lounge suites for a number
of South African furniture retail companies. He
is presently
employing a number of 50
employees
earning between R400 and R1 000.00 per week, which averages at least
R700 per week. Most of the employees working for
him have commenced
employment in 2006 and are depended on their jobs to sustain a
reasonable livelihood. He took possession of
the premises initially
in a rental arrangement in July 2013, but later opted to enter into a
sales agreement. Li entered on 8
March 2013 into a rental/lease
agreement with the applicant. The lease agreement was to commence on
1 May 2013 and was to operate
for a period of one year and was to
terminate on 30 April 2014. He took possession of the premises in
June 2013 and in terms of
the agreement was to effect rental in the
amount of R130 000 per month excluding VAT. When he took occupation
of the premises
there were already concerns related to electricity
supply, water leaks, broken windows and a leaking proof. These were
to have
been attended to by the lessor but he attended to fixing the
water leaks, the plumbing and some of the broken windows. He
affected
a deposit in the sum of R148 200.00 and one month’s
rental in the sum of R130 000.00 and the total paid is R278 200.00.

He has complied with his obligations in terms of the lease agreement.
He did not make any further payments after one of the directors
of
the applicant’s, Jeffrey Mark Wiggil had passed away.
19.In
August 2013 Li was approached and told that the premises was
available for sale. He was interested in purchasing it and in
terms
of the sale agreement he was to purchase the property for R11 million
and had to effect a deposit of R1.1 million as a deposit.
That
payment was effected in October 2013. In September 2013 he
approached Michael Pillay from Business Partners who
advised
him that they were desirous to fund the balance of the purchase price
and take up equity within the second respondent.
The only
requirement for the finalisation of financing raised by Business
Partners was the fact that the electrical supply from
the adjacent
building was not acceptable. After he had given them an explanation
Business Partners required a new electrical supply
point be installed
before it could continue with the financing. He met with the seller
who he believed was KPMG at their offices
on 25 August 2014 but had
subsequently discovered that the building is owned by Investec Bank,
the original bond holder. The meeting
was attended by various people
and the issue regarding the electrical repairs was central to the
discussion. It was decided that
an investigation would be undertaken
to gauge the extent of the electrical problems. It was decided that
Mr Weber would undertake
an investigation for purposes of preparing a
quotation to effect a single supply electrical point. The lease
agreement fell away
upon conclusion of the sale agreement.
20.
In October 2014 Li attended a meeting at KPMG and was informed that
it would cost R2.8 million to install a single supply electrical

point and attend the relay of the electrical supply throughout the
premises. The negotiations broke down when he requested whether
the
amount for the repairs of the
electrical
issues could be offset from the remainder of the purchase price. The
prospective financing of the remainder of the outstanding
purchase
price was discussed. He had expressly advised that the duty of the
restoration of a single electrical supply point was
the duty of the
seller and not the purchaser and that the extent of the problem was
never disclosed to him. Had he known about
the extent of the cost
involved, he would not have agreed to accepting the responsibility
for the electrical repairs. The agreement
in that regard was
unreasonable and unconstitutional as it unfairly and unreasonably
favours one party only namely the applicant.
He has attempted to
draw to the attention to the seller the urgency of the electrical
problems but same fell on deaf ears. He
has been informed that the
purchaser of a property generally is not required to attend to the
electrical repairs, but that there
is a duty on the seller to ensure
that the premises are fit for usage and that the requisite electrical
compliance certificates
are prepared.
21.
It was contended by the applicant that the first and second
respondents who remain in unlawful occupation have no basis in law

upon which they are entitled to occupy the premises at all and are
unlawful occupiers. The lease period under the lease agreement
has
come to its end and the sale agreement has been cancelled and a
notice to vacate was premises delivered to the second
respondent,
which notice was acknowledged by the second respondent’s
attorneys. In terms of the notice to vacate, the second
respondent
was informed that the premises must be vacated by 11 October 2014.
The first and second respondents are both represented
by Li who
received the notice to
vacate
the premises, and they were both aware that they were required to
vacate the premises on that specified date which they had
refused to
do.
22.It
was further contended by the applicant that by virtue of the
termination of the lease agreement and the cancellation of the
sale
agreement, the unlawful occupiers’ and/or tenants’
continued occupation and possession of the property is unlawful.

Their unlawful occupation of the premises is not subject to the
provisions of the Land Reform (Labour Tenants) Act 3 of 1996,
the
Extension of Security of Tenure Act 62 of 1997
or the Prevention of
Illegal Eviction from and Unlawful Occupation of Land Act 19 of 1998
in that they are not occupiers as defined
in section 1 of the
aforesaid pieces of legislation and they are conducting manufacturing
business on the premises and do not occupy
it for residential
purposes since it is situated in an industrial area. The applicant
is entitled to claim for immediate ejectment
of the unlawful
occupiers from the premises and the unlawful occupiers has no defence
in law to this claim by the applicant.
23.Li
denied that the first and second respondents are in unlawful or
illegal occupation of the premises since his conduct demonstrates
a
willingness to finalise the conclusion of the sale agreement, which
has been and continues to be delayed by the conduct of the
seller.
It was contended that a party cannot frustrate the process and claim
relief for non-compliance where that party itself
was the cause of
the non-compliance. The electrical report is in the process of being
finalised and same will be made available
to the court and the
premises are safe. For the aforesaid reasons there is neither
unlawful nor illegal occupation of the premises.
24.Li
has admitted having received the various letters but denied the
accuracy of the contents of the letter namely the one of 26
September
2014. He denied that he was indebted to the applicant. The one
letter deals with clause 11 of the agreement and he
admitted having
received that. He further admitted having received the letter dated
9 October 2014 that states that he has failed
to meet the demands
contained in the letter dated 26 September 2014 within the period
mentioned in it and that it was cancelled.
However it was contended
that the applicant cannot cancel the agreement verbally and that no
notice of cancellation has been filed
and it cannot vary the terms of
the agreement unilaterally. The first and second respondents’
admitted that it received
notice to vacate the property by 11 October
2014 but denied the notice constitutes a valid notice in terms in the
PIE Act.
25.
PIE finds no application in this matter since these are commercial
premises situated in an industrial area. This defence was
for
obvious reasons not persisted with.
26.
I have earlier indicated that the first and second respondents are
persisting only with two defences. The first was the non-joinder
of
the bondholder on the property, Investec Bank who it was contended
was the owner of the property and not Hollyberry Props 4
(Pty) Ltd.
The second ground is that
there
was no compliance with clause 11 of the sale agreement in that the
said notices were not sent by registered post. This court
was
referred to various judgments by the first and second respondents in
an attempt to bolster their defence.
27.
I now propose to deal with the first issue whether the applicant
could seek the relief that they are seeking and whether Investec
Bank
should have been joined as a party to the application. Investec Bank
as the bondholder is not the owner of the business premises
by virtue
of the bond. It has no interest other than that it is a secured
creditor. In this regard see Gainsford and Others NNO
v Tanzer
Transport (Pty) Ltd
2014 (3) SA 468
SCA. There is there no merit in
the above defence.
28.
This brings me to the second defence raised by the first and second
respondent around the issue of non compliance with clause
11 of the
sale agreement. Section 11 of the sale agreement deals with breach
and provides as follows:

Should
any party fail to comply with any of the terms and conditions of this
agreement and remain in default for a period of 10
(TEN) days after
dispatch per registered post of written notice requiring any default
to be remedied, the aggrieved party shall
be entitled, in addition to
and without prejudice to any other rights available at law, to cancel
this agreement forthwith and
retain all monies paid by the purchaser
as ‘ROUWKOOP” by way of liquidated damages or enforce
performance of the terms
of this agreement.”
29.Before
I refer to the judgements that the first and second respondents
counsel had referred me to, Li who is the owner of the
first and
second respondent’s had admitted that he had received the
letters that had placed him in mora and the cancellation
letter but
had disputed the contents of the letters. Whilst it is so that there
is no proof that the letters were sent by registered
post, it appears
that the letters were hand delivered. The first letter dated 26
September 2014 marked for the attention of Li
appears to have been
hand delivered and sent by registered mail and was received by one
Malcolm Pillay on 26 September 2014. The
letter at page 3 deals with
the breach and informs Li that in terms
of
clause 11 he is in breach and is given 10 days to remedy his breach
failing which further steps would be taken. Li admitted
having
received the said letter.
30.
The next letter of import is the letter dated 9 October 2014 which
was hand delivered on the same day which was also acknowledged
to
have been received by Li informs him that as a result of their breach
the sale agreement has been cancelled.
31.The
respondents counsel referred me to the following cases in support of
his contentions. The first was that of Minister of
Land Affairs and
Agricultural and Others v D & F Wevell Trust and Others
2008 (2)
SA 184
SCA. This case is simply not relevant to the issues that I am
required to determine. It deals with that it was not proper for
a
party in application proceedings to base an argument on passages in
documents where these have been annexed to the papers where
the
conclusions sought to be drawn from such passages had not been
canvassed in the affidavits. In motion proceedings the affidavits

contain both the pleadings and the evidence and the issues and
averments should appeal clearly therefrom. A party could not be

expected to trawl through lengthy annexures to their opponents’
affidavits and to speculate on the possible relevance of
the facts
therein contained. Trial by ambush should not be permitted. The
reliance on the matter of First National Bank of SA
Ltd v Ganyesa
Bottle Store (Pty) Ltd and Others; First National Bank of SA Ltd v
Schweizer Drankwinkel (Pty) Ltd and Another
1998 (4) SA 565
(NC) is
simply misplaced. That case dealt with the issue of knowledge of the
summons that was issued but was not a served. The
matter of Kragga
Kamma Estates and Another v Flanagan
[1994] ZASCA 137
;
1995 (2) SA 367
(A). This deals
with the requirements of placing a party in mora and cancellation.
The reliance of Sandton Square Finance (Pty)
Ltd and Others v Biagi,
Bertola and Vasco and Another
1997 (1) SA 258
(W) is misplaced since
this matter dealt with the question where service took place at
another address other than a domicilium
citandi et executandi it was
held that service at another address would be sound. The last case
that reliance was placed on is
that of SA Wimpy (Pty) Ltd v Tzouras
1977 (4) SA 244
(W) which also dealt with the issue whether a notice
was validly given. As long as there is prove that the notice was
received,
it matters not how the notice was given.
32.
Save for what I have referred to above, I am satisfied that the first
and second respondents are in breach of the sale agreement.
In a
letter dated 26 September 2014 which as stated earlier Li admitted to
having received it, they were informed about the nature
of the breach
and given ten days to remedy the breach. After they failed to do so,
they were given another letter dated 9 October
2014 that they had
failed to remedy the breach and that the applicant was now cancelling
the sale agreement. There was therefore
compliance with clause 11 of
the sale agreement. It was mindboggling that despite these
admissions that counsel for the first
and second respondents had
persisted with the defence which was stillbirth. This is a defence
that was manufactured in chambers
and was simply an afterthought.
33.
Following the second respondent’s failure to meet the terms of
the sale agreement, notwithstanding notice to remedy its
defaults and
the subsequent settlement discussions between the applicant and the
second respondent, the latter failed to remedy
its defaults and the
applicant accordingly, cancelled the sale agreement, which it is
entitled to do. The first and second respondents
do not have any
defence to this application. They have clearly breached the sale
agreement and are in unlawful occupation of
the premises. The
application stands to be granted.
34.
This brings me to the question of costs. The applicant had in its
notice of motion indicated that it was seeking costs on an
attorney
and client scale. It had brought an urgent application which was
heard on 9 December 2014. The matter was struck from
the urgent roll
to allow the first and second respondents’ to file an answering
affidavit and costs were reserved. The court
found that the matter
was not urgent and this appears to have been the reason why it was
struck of the roll. The applicant clearly
did not make out a case
for urgency. The applicant should bear the costs of the striking off
of the urgent application on a party
and party scale. The costs of
this application should be borne by the first and second respondents.
Their opposition to this
application was frivolous and was doomed to
fail from the onset. Such costs will have to be on an attorney and
client scale.
35.
In the circumstances I make the following order:
35.1
The first and second respondents and all those who occupy the
premises known as, Erf 132 Chamdor, Krugersdorp and more commonly

known as 38 Van Eck Street, Chamdor (the premises), under and by
virtue of the first and second respondents’ occupancy of
the
premises, be and are hereby evicted from the premises by not later
than 14h00 on 5 June 2015.
35.2
In the event of the first and second respondents and all those who
occupy the premises under and by virtue of the first and
second
respondents’ occupancy of the premises, failing and/or refusing
to vacate the premises by not later than 14h00 on
5 June 2015, that
the sheriff of this Court be and is hereby authorised to forthwith
enter upon the premises and evict the first
and second respondents
and all those who occupy the premises under and by virtue of the
first and second respondents’ occupancy
of the premises, with
the assistance of the South African Police.
35.3
The first and second respondents are to jointly and severally, the
one paying the other to be absolved, to pay the costs of
this
application on the scale of attorney and own client, excluding the
costs reserved by the court of the hearing on 9 December
2014, which
are to be paid by the applicant to the first and second respondents
on a party and party scale.
FRANCIS
J
JUDGE
OF THE HIGH COURT
FOR
APPLICANT : D J JOUBERT INSTRUCTED BY EDWARD NATHAN SONNENBERGS INC
FOR
RESPONDENTS : C E THOMPSON INSTRUCTED BY DAVID
KOTZEN
ATTORNEYS
DATE
OF HEARING : 12 & 14 MAY 2015
DATE
OF JUDGMENT: 29 MAY 2015