About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2014
>>
[2014] ZAGPJHC 182
|
|
Cirano Investments 307 (Pty) Ltd v Execujet Aviation (Pty) Ltd (10831/12) [2014] ZAGPJHC 182 (22 March 2014)
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG
LOCAL DIVISION, JOHANNESBURG
CASE
NUMBER: 10831/12
NOT
REPORTABLE
NOT
OF INTEREST TO OTHER JUDGES
In
the matter between:
CIRANO
INVESTMENTS 307 (PTY)
LTD
...............................................................................
Plaintiff
and
EXECUJET
AVIATION (PTY)
LTD
.......................................................................................
Defendant
Coram:
WEPENER J
Heard:
19 MARCH 2014
Delivered:
22 MARCH 2014
Summary:
Breach of contract – damages claim
-
general damages – rule on
mitigation of loss not to be confused with calculation of claim for
loss of profit
JUDGMENT
WEPENER
J:
[1]
The plaintiff seeks damages from the defendant as a result of the
defendant’s breach or repudiation of a written agreement
in
terms whereof the defendant leased an aircraft from the plaintiff.
[2]
The parties agreed, and I ordered, a separation of issues in this
matter in that the following question only is to be determined
in
limine: whether the provisions of clause 11.4 of the written
agreement concluded by the parties, precludes the kind of claim
pursued by the plaintiff.
[3]
The relevant clause provides:
‘
The
Parties shall be exempt from, and no Party shall be liable under any
circumstances for, any indirect, special or consequential
damages of
any nature, or any loss of profit, loss of ability to make use of the
Aircraft or other special damages of any nature
which any other Party
may suffer, as a result of, relating to, or arising directly or
indirectly in any manner whatsoever out of
the terms of this
Agreement, or grossly negligent or wilful acts or omission of any
Party.’
[4]
It is not in dispute that the clause excludes claims for special
damages but not general damages. However, the defendant submits
that
the claim of the plaintiff is couched as a loss of profit, the latter
which is prohibited from being recovered from the defendant.
[6]
Counsel for the defendant did not counter the submission presented on
behalf of the plaintiff in relation to the exposition
of the law
regarding general damages, but submitted that it is not applicable in
this matter, as the plaintiff has instituted a
claim for loss of
profits, which is excluded .
[7]
The legal position which is not in dispute, but submitted by the
defendant not be applicable, is the following:
‘
The
loss which the innocent party suffers as a result of breach of
contract may be either primary or secondary (consequential).
The
innocent party’s primary loss is the value (that is, monetary
value) of the performance which he or she was promised
less the value
of the performance he or she has been excused from rendering (on
account of his or her having rescinded the contract).
The innocent
party’s secondary loss is the loss he or she suffered over and
above the value of performance not received,
for example, interest or
profit that he or she failed to earn because the guilty party did not
perform as promised. In what follows,
damages for secondary or
consequential loss are referred to as “additional”
damages.’
[1]
[8]
The difference between general damages and special damages has been
described by Trollip JA in
Shatz
Investments (Pty) Ltd v Kalovyrnas
[2]
as follows:
‘
According
to these particulars plaintiff's claim was not for (a) “general
damages”, but was for (b) “special damages”.
Sometimes the corresponding terms “intrinsic” and
“extrinsic” damages are used (see Pothier, Obligations,
(Evans' translation, paras. 161 and 162), and
Whitfield
v. Phillips and Another
,
1957 (3) SA
318
(AD) at p. 329D - E). I use the former terms here as well known,
convenient labels to respectively differentiate, broadly and without
any pretence at precision, between (a) those damages that flow
naturally and generally from the kind of breach of contract
in
question and which the law presumes that the parties contemplated
would result from such a breach, and (b) those damages that,
although
caused by the breach of contract, are ordinarily regarded in law as
being too remote to be recoverable, unless, in the
special
circumstances attending the conclusion of the contract, the parties
actually or presumptively contemplated that they would
probably
result from its breach (see
Lavery and
Co. Ltd. v Jungheinrich
,
1931 AD 156).
’
[9]
The plaintiff claims the rental for the period during which the
defendant was in breach. Such a claim has been said to be a
claim for
general damages
[3]
.The plaintiff
is entitled to institute such a claim for damages
[4]
.
The plaintiff seeks such damages but deducts from its claim:
‘
Maintenance
costs and all replacement of repairs or of components, and insurance
costs, averaging US $48 100.00 per month over
the duration of
the term (11.25 month) totalling US $541 126.00.’
[10]
Because of the manner in which the claim is formulated the defendant
submitted that the plaintiff is really seeking its loss
of profit.
[11]
Upon the cancellation of an agreement,
‘
.
. . The authorities are ad idem that the plaintiff is entitled to his
full
id
quod
interest
but no more. He must not by cancellation be in any better position
than he would have been had the contract been performed.
. . .’
[5]
Had
the plaintiff not deducted the amount which it would have saved had
the contract been properly performed, its claim would have
been
objectionable by virtue of the inclusion of the costs which it
otherwise would have incurred and which would have reduced
the income
earned pursuant to the agreement.
[12]
‘
The
fundamental rule in regard to the award of damages for breach of
contract is that is that the sufferer should be put in the
position
he would have occupied had the contract been properly performed, so
far as this can be done by the payment of money and
without undue
hardship to the defaulting party (see Victoria Falls & Transvaal
Power Co. Ltd. v Consolidated Langlaagte Mines
Ltd.,
1915 AD 1
at p.
22; Novick v Benjamin,
1972 (2) SA 842
(AD) at p. 860). To ensure
that undue hardship is not imposed on the defaulting party the
sufferer is obliged to take reasonable
steps to mitigate his loss or
damage (ibid.)’
[6]
[13]
It is incumbent upon an innocent party to mitigate its loss. Kerr,
The
Principles of the Law of Contract (Sixth Ed)
[7]
,
gives an example of a claim for general damages where the learned
author says
[8]
that:
‘
It
is suggested that when mitigation is in question the formula for
calculating damages is:
(1)
Such loss flowing from the original breach
as is agreed upon or is provided for in the residual rules, plus
(2)
(a) expenses which were incurred, and / or
charges for work done, in taking reasonable steps, whether successful
or unsuccessful,
to mitigate loss flowing from the original breach or
which would have been incurred or charged for a reasonable method of
mitigating
loss been taken, and
(b)
additional loss, if any, which has caused, or which would have been
caused, by taking such steps, if the agreed figure under
(1) above,
if any, does not cover these amounts,
minus
(3)
whatever, benefit is obtained or would have been obtained had
reasonable steps been taken to mitigate the loss.’ (own
emphasis).
[14]
The claim wherein a plaintiff concedes the mitigation is, in my view,
not objectionable. Ordinarily the defendant would have
to plead and
prove a non-mitigation of damages
[9]
.
In this case the plaintiff made this task of the defendant easier by
conceding the duty to mitigate and setting out the amount
of the
mitigation.
[15]
The defendant’s case is that the manner in which the plaintiff
alleges it damages, ie the rental value less the expenses,
results in
the plaintiff claiming a loss of profit which it cannot do by virtue
of the provisions of clause 11.4 of the written
agreement.
[16]
I do not agree with this submission. The fact that the amount claimed
as general damages (less the mitigation portion) does
not transform
the claim into a claim for loss of profit. Although the amount of the
damages may coincide with an amount which would
have been claimable
for a loss of profit, if claimable, that fact does not support the
submission that the claim is one for a loss
of profit. Indeed,
without evidence or facts to show how a loss of profit could be
arrived at, I am of the view that the submission
that, because of the
manner of the calculation of the damages, it constitutes a loss of
profit, has no merit.
[17]
Counsel for the defendant relied on the definition of the word profit
in the
Oxford Advanced Learner’s Dictionary of Current
English
which reads as follows:
‘
Money
gained in business, especially the difference between the amount
earned and the amount spent’.
[18]
The difficulty with the submission is that without evidence as to the
nature of the amount spent, it cannot be determined whether
there was
a profit at all. There is no basis before me upon which it can be
accepted that the amount which the plaintiff deducts
as mitigation of
damages is the only amount spent by the plaintiff, and even if it
were, the plaintiffs’ claim falls squarely
within the
boundaries of a claim for general damages whilst applying the rule
that it is obliged to mitigate its loss.
[19]
In the circumstances I issue the following order:
1.
It is declared that the plaintiff’s
claim for damages is not precluded by the provisions of clause 11.4
of the written lease
agreement.
2.
The defendant is ordered to pay the costs
of this hearing.
__________
Wepener
J
Counsel
for Plaintiff: M.P. Van der Merwe
Attorneys
for Plaintiff: Saunders Venter Van der Watt
Counsel
for Defendant: L. Hollander
Attorneys
for Defendant: Darryl Furman & Associates
[1]
LAWSA
Vol 5 Part 1 (Second Edition) para 493.
[2]
1976
(2) SA 545
(A) at 550B-E.
[3]
See
Shatz
at 550E-G.
[4]
Tos
v Angelo Outfitting Stores
1915 TPD 22
at 25.
[5]
Bonne
Fortune Belegging Bpk v Kalahari Salt Works (Pty) Ltd and Others
1973 (3) SA 739 (NC) at 818D
[6]
See
Holmdene
Brickworks (Pty) Ltd v Roberts Construction Co. Ltd
1977 (3) SA 670
(A) at 687C-E
[7]
At
758-768
[8]
At
762.
[9]
See
Soar
h/a Rebuilds for Africa v J.C. Motors en ‘n Ander
1992
(4) SA 127
(A) at 135C