Engen Petroleum Ltd v Business Zone 10 CC and Another (A0319/12) [2012] ZAGPJHC 246 (17 October 2012)

78 Reportability
Arbitration Law

Brief Summary

Arbitration — Review of arbitrator's ruling — Applicant sought to review and set aside an arbitrator's ruling granting leave to amend a statement of claim in arbitration proceedings under the Petroleum Products Act — Applicant contended that the amendment introduced issues beyond the arbitrator's jurisdiction — Court held that while an arbitrator cannot enlarge his jurisdiction by allowing amendments, the legal uncertainty surrounding the issue did not warrant intervention at this stage — Application dismissed with costs, including costs of two counsel.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an application in the High Court to review and set aside a ruling made by an arbitrator in ongoing arbitration proceedings. The applicant was Engen Petroleum Limited, and the first respondent was Business Zone 10 CC. The second respondent was Mr Michael Kuper SC, cited in his capacity as the arbitrator who delivered the impugned ruling.


The matter arose in the context of arbitration proceedings conducted under section 12B of the Petroleum Products Act 120 of 1977. Those arbitration proceedings were at an embryonic stage when the review application was launched. The immediate trigger was a procedural ruling made on 13 February 2012, in which the arbitrator granted the first respondent leave to amend its statement of claim. Engen launched the present review application on 22 March 2012.


The general subject-matter of the dispute concerned the scope of the arbitrator’s jurisdiction in a section 12B arbitration, specifically whether a proposed amendment would introduce issues beyond what had been referred through the statutory process. Although the ruling attacked was, in form, a procedural decision granting leave to amend, Engen framed the review as implicating a fundamental jurisdictional question.


2. Material Facts


It was common cause that arbitration proceedings between Engen and Business Zone 10 CC were being conducted pursuant to section 12B of the Petroleum Products Act 120 of 1977, and that the arbitration was still in its early stages.


Business Zone 10 CC applied in the arbitration for leave to amend its statement of claim. Engen raised eight objections to the proposed amendment. Of these objections, four were relevant to the High Court application, in that they concerned jurisdiction.


On 13 February 2012, the arbitrator, Mr Michael Kuper SC, issued a ruling granting Business Zone 10 CC leave to amend its statement of claim. Engen then launched the present review application on 22 March 2012, seeking to have that ruling reviewed and set aside.


The court recorded as a matter of agreement between the parties that an arbitrator cannot enlarge his jurisdiction by permitting an amendment that introduces alleged unfair or unreasonable contractual practices not referred to the arbitrator through the section 12B process. The dispute before the High Court concerned whether, on the facts and at that stage of the arbitration, it could be determined that the arbitrator had in fact permitted such an impermissible enlargement of jurisdiction.


3. Legal Issues


The central legal question was whether the High Court should, in the circumstances, intervene mid-arbitration to review and set aside a procedural ruling granting leave to amend, where the applicant contended that the ruling effectively involved a determination (and potential enlargement) of the arbitrator’s jurisdiction.


A related question was whether this matter fell within the category of exceptional circumstances in which judicial intervention is justified before the conclusion of proceedings in another forum. This required an evaluative assessment by the court as to the appropriateness and timing of review intervention, given the incomplete state of the arbitration.


The dispute principally concerned the application of legal principles to the procedural posture and facts of an ongoing arbitration, coupled with a discretionary or value-based judgment about whether intervention at that stage was warranted, rather than a final determination on the substantive merits of the alleged jurisdictional overreach.


4. Court’s Reasoning


The court approached the matter by recognising, first, the general character of the impugned decision. Engen’s counsel conceded that a ruling granting leave to amend is generally regarded as procedural. The applicant nevertheless argued that the ruling was reviewable because it was said to be “fundamental”, in that it implicated the arbitrator’s competence to entertain the amended claim.


The court accepted the legal proposition—treated as common cause—that an arbitrator may not allow an amendment if doing so would introduce issues that fall beyond the arbitrator’s jurisdiction, and specifically beyond what was referred through the statutory mechanism. The court therefore did not reject the applicant’s contention as a matter of principle; instead, it focused on whether it was appropriate to determine, at that stage, that the arbitrator had indeed acted outside his jurisdiction.


In addressing whether intervention was justified, the court emphasised the practical and jurisprudential undesirability of calling upon courts to intervene in proceedings still in progress before other tribunals. The court relied on the principle expressed in Wahlhaus v Additional Magistrate, Johannesburg 1959 (3) SA 113 (A), which discourages premature judicial interruption of incomplete proceedings except in rare and exceptional cases. The court’s reasoning was that intervention midstream is generally inappropriate because the developing course of the proceedings may affect the ultimate position and because premature review risks fragmenting the process.


Applying that approach, the court considered the jurisdictional contention to be legally uncertain and complex on the papers and at that point in time. The court expressly declined to make any definitive finding on whether the arbitrator had impermissibly enlarged his jurisdiction, stating that it was possible that such a conclusion could ultimately be reached, but that it would be wrong to reach it at that stage. The court therefore held that the case did not meet the threshold of clarity or exceptional circumstance required to justify intervention while the arbitration was ongoing.


On costs, the court undertook an evaluative balancing exercise. It was concerned that a costs award at that stage might later appear unfair if the applicant ultimately succeeded in the broader dispute. However, it weighed this against the established principle that costs follow the result, and the policy concern that declining to award costs could encourage litigants to seek premature court intervention in ongoing tribunal proceedings with little downside risk. On that basis, the court concluded—narrowly—that costs should follow the dismissal of the application. The court also accepted that the matter warranted the costs of two counsel for the first respondent.


5. Outcome and Relief


The court dismissed the application to review and set aside the arbitrator’s ruling.


The court ordered the applicant to pay the first respondent’s costs, and directed that such costs were to include the costs of two counsel.


No appearance was recorded for the second respondent.


Cases Cited


Wahlhaus v Additional Magistrate, Johannesburg 1959 (3) SA 113 (A)


Legislation Cited


Petroleum Products Act 120 of 1977 (section 12B)


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The High Court held that, although it was accepted in principle that an arbitrator cannot extend his jurisdiction by allowing amendments introducing issues not properly referred under the statutory scheme, the circumstances did not justify premature judicial intervention in an arbitration that was still in progress.


The court held that the jurisdictional point raised was not sufficiently clear, and was surrounded by legal uncertainty and complexity, such that this did not constitute the exceptional case warranting review of a procedural ruling midstream. The review application was therefore dismissed, with costs (including costs of two counsel) awarded against the applicant.


LEGAL PRINCIPLES


The judgment applied the principle that it is generally undesirable for courts to intervene in proceedings that are still ongoing before another tribunal, and that such intervention should occur only in rare or exceptional circumstances, consistent with the approach in Wahlhaus v Additional Magistrate, Johannesburg 1959 (3) SA 113 (A).


The judgment proceeded from the accepted principle that an arbitrator cannot enlarge his jurisdiction by permitting an amendment that introduces new issues beyond the scope of what was properly referred to arbitration under the governing statutory framework, while recognising that whether such enlargement occurred may require determination at an appropriate stage in the proceedings.


The judgment affirmed the conventional approach to costs that costs follow the result, and treated the awarding of costs (including the costs of two counsel) as serving both the outcome-based rationale and the policy objective of discouraging unwarranted midstream interruptions of tribunal proceedings.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: South Gauteng High Court, Johannesburg
SAFLII
>>
Databases
>>
South Africa: South Gauteng High Court, Johannesburg
>>
2012
>>
[2012] ZAGPJHC 246
|

|

Engen Petroleum Ltd v Business Zone 10 CC and Another (A0319/12) [2012] ZAGPJHC 246 (17 October 2012)

IN THE HIGH COURT OF
SOUTH AFRICA
(SOUTH GAUTENG HIGH
COURT, JOHANNESBURG)
CASE NO
:
A0319/12
DATE
:
2012/10/17
In
the matter between
ENGEN
PETROLEUM LIMITED
Applicant
and
BUSINESS
ZONE 10 CC
1
st
Respondent
MICHAEL
KUPER SC
2
nd
Respondent
J U D G M E N T
WILLIS  J
:
[1] The applicant seeks
an order which will review and set aside a ruling made by the 2
nd
respondent, Mr Michael Kuper SC, on 13 February 2012 in arbitration
proceedings that are taking place between the applicant and
the 1
st
respondent.
[2] The arbitration
proceedings arise between the parties in terms of
section 12B
of the
Petroleum Products Act No. 120 of 1977
.  The arbitration is in a
very embryonic stage.  The 1
st
respondent applied for
leave to amend its statement of claim. The applicant raised eight
objections to the proposed amendment,
four of which are relevant in
this particular matter before me today, and relate to the question of
jurisdiction.
[3] On 13 February 2012,
Mr Kuper SC gave his ruling in the matter and granted the 1
st
respondent leave to amend its statement of claim.  On 22 March
2012 the applicant launched the present application to review
and set
aside Mr Kuper’s ruling.  Counsel for the applicant, Mr
Thompson
, has fairly conceded that the ruling as one granting
leave to amend is generally regarded as procedural only. Despite
this, although
the ruling is one granting leave to amend, he has
nevertheless submitted that the ruling is fundamental, as it relates
to the arbitrator’s
determination of his own jurisdiction.
[3] Mr
Thompson
has submitted that, in exceptional circumstances, the court may
intervene and review a procedural ruling, while the arbitration
is
still in progress.  Mr
Thompson
has also submitted that
an arbitrator cannot allow an amendment which would introduce issues
that fall beyond his jurisdiction.
That, according to Mr
Thompson
,
is the point of the review.  I am in agreement with the
submission that an arbitrator cannot allow an amendment which would

introduce new issues that fall beyond his jurisdiction.
[4] Mr
Thompson
has submitted:

- the arbitrator
cannot enlarge his jurisdiction by allowing an applicant to amend so
as to introduce an alleged unfair or unreasonable
contractual
practice that was not referred to the controller.”
This much is common
cause. We all agree.  The difficult question in this particular
matter, is whether it can be found that
Mr Cooper did in fact so
enlarge his jurisdiction by allowing the applicant to amend so as to
introduce an alleged or unreasonable
contractual practice that was
not referred to him by the controller in terms of the
Petroleum
Products Act.
[5
] I wish to emphasise
that I make no definitive finding on that point whatsoever.  In
other words, I accept that it may ultimately
turn out that Mr Cooper
impermissibly allowed the amendment so as to enlarge his
jurisdiction.  Nevertheless, the point is
so shrouded in legal
uncertainty and is such a complex point of law that it would be
entirely wrong for me to making a finding
to this effect at this
stage. I do not think this is one of those exceptional and rare
circumstances where one is justified in
intervening while the parties
are midstream, crossing the river.
[6] It is far from
certain who will get to the other side of the river first and that
may well have a bearing on the matter ultimately.
I have
referred in other cases to the case of
Wahlhus v Additional
Magistrate, Johannesburg
1959 (3) SA 113
(A) at 115. It is a case
that is particularly topical today in view of certain expected
announcements by the Judicial Service Commission.
This case of
Wahlhus v Additional Magistrate, Johannesburg
makes clear that
it is an utterly undesirable practice to call upon courts to
intervene in proceedings that are on progress before
other tribunals
prior to those proceedings having been completed.  This is not
one of those cases where it can be said with
confidence so clearly
that Mr Kuper was wrong that intervention would be justified.
[7] I have agonised over
the question of costs. I am troubled by the fact that if I award
costs today, it may ultimately seem that
it was wrong not to put
these “in the pot”, in the event that the applicant,
(that is Engen Petroleum Limited) is successful.
On the other
hand, one must be careful to depart from what established rules of
law, such as the one that costs should follow the
result.  If
costs do not follow the result in this matter, one is in danger of
sending out a signal to parties that there
is nothing to lose by
approaching the court to intervene in proceedings before another
tribunal while these proceedings are in
progress.  That is a
practice to be deprecated, and on this basis alone, I am persuaded,
narrowly, that this is an appropriate
matter in which to award costs
at this stage.
[9] Mr
Suttner
,
who together with Mr
Redman
, has appeared for the 1
st
respondent, has submitted that the cost of two counsel should be
allowed.  I agree, this is a weighty matter and much is,

op
die spel
” to use a classic, a very expressive Afrikaans
idiom.
[10] Accordingly, the
following is the order of the court:
The application is
dismissed with costs, which costs are to include the costs of two
counsel.
- - - - - - - - - - - -
Counsel for the
Applicant:
Adv.
A.C Thompson
S.C
Counsel for the 1st
Respondent:
Adv.
J.M Suttner
S.C. (with him, Adv.
N.P.G
.
Redman)
No appearance for the
2
nd
Respondent