Body Corporate of the Sorronto Sectional Title Scheme, Parow v Koordom and Another (5439/2021) [2022] ZAWCHC 99; 2022 (6) SA 499 (WCC) (26 May 2022)

80 Reportability
Land and Property Law

Brief Summary

Body Corporate — Access to common property — Application for access to conduct leak detection test — Body corporate seeking access to unit for inspection due to ongoing damp issues — Second respondent initially refusing access but later permitting inspection — Legal standing of body corporate to institute application questioned — Court finds that resolutions authorizing application were valid and properly ratified — Application granted, with costs awarded to the applicant.

Comprehensive Summary

Summary of Judgment


1. Introduction


The proceedings were an application brought in the High Court by a body corporate of a sectional title scheme seeking coercive relief in the form of a mandamus to compel access to a unit within the scheme for purposes of leak detection and inspection. The matter was initially enrolled and pursued as an urgent application, but ultimately only the question of costs remained for determination after the substantive relief became moot.


The applicant was The Body Corporate of the Sorronto Sectional Title Scheme, Parow (Scheme No: 377/1997). The respondents were Leozette Koordom (first respondent) and Wilfred Booysen (second respondent), who were associated with Unit 101 in the scheme. The dispute arose in the context of the body corporate’s management of scheme property and maintenance concerns connected to water ingress.


Procedurally, the applicant launched the application on 29 March 2021 on an urgent basis, seeking an order compelling the respondents to give access to Unit 101 within a short period so that a further leak detection inspection could be conducted. The matter was enrolled for hearing on 20 April 2021, but it was only heard on 30 April 2021, when the urgent application was struck off the urgent roll. Thereafter, the respondents permitted access and the inspection occurred, with the result that the substantive relief sought was no longer live. The court was therefore required to decide (i) an authority/locus standi challenge raised by the respondents and (ii) the appropriate costs order, in circumstances where the merits had become moot.


The general subject-matter of the dispute concerned water ingress/damp affecting one unit in the sectional title scheme, the body corporate’s efforts to obtain access to another unit to investigate a suspected source of leakage, and the appropriate forum and cost consequences where such disputes could have been pursued under the Community Schemes Ombud Service framework.


2. Material Facts


During October 2020, damp marks appeared on the ceiling of Unit 100 within the Sorronto sectional title scheme. The body corporate took steps to investigate, including seeking access to Unit 101 (associated with the second respondent) as part of efforts to identify the source of the damp. Access was eventually obtained and an inspection occurred on 11 November 2020, but no leaks were found in Unit 101 at that stage.


On 25 January 2021, the owner of Unit 100 reported to the body corporate that the damp problem remained unresolved. What followed was a period of repeated efforts by the body corporate (through its managing agents, loss adjusters, leak detection agents, and attorneys) to obtain further access to Unit 101 to conduct additional inspection and testing. The court treated it as significant that these attempts were unsuccessful for an extended period and that access was refused or delayed.


The respondents’ position, as reflected in the answering affidavit, was that a leak detection inspection had already been conducted in late November 2020 with a negative finding, and that there was therefore no basis for another inspection. However, the record ultimately reflected that the respondents later accepted that the body corporate was entitled to conduct reasonable inspections from time to time for proper management of the scheme’s common property, and they permitted access, whereafter a second leak detection test was performed. This rendered the primary access-related prayer in the notice of motion academic.


Two sets of trustee resolutions featured prominently in the authority dispute. A resolution dated 19 March 2021 was signed by two trustees on a round-robin basis, and a further resolution dated 20 April 2021 was signed by all five trustees. The respondents contended that the initial resolution was defective and that the application had been launched without proper authority.


By the time the matter was before Carter AJ, the only outstanding issue was costs, together with the preliminary question whether the applicant was properly authorised to have instituted the application.


3. Legal Issues


The central questions the court was required to determine were, first, whether the applicant had the requisite authority (locus standi) to institute the urgent application given the form and execution of the trustee resolutions relied upon. This was predominantly an issue of application of legal principles to largely common-cause facts, namely the content, timing, and signature of the resolutions and the manner in which trustee authority may be validly conferred or ratified.


Second, the court had to determine the appropriate costs order where the substantive relief had become moot, including whether and how the availability of dispute resolution through the Community Schemes Ombud Service (CSOS) should influence the exercise of the High Court’s discretion on costs. This involved a mix of legal principle (the relationship between the High Court and statutory dispute-resolution mechanisms, and the approach in prior authorities) and an evaluative discretion (what costs order would be just in light of the parties’ conduct and the appropriateness of the chosen forum).


4. Court’s Reasoning


On authority, the court rejected the respondents’ argument that the initial resolution was null and void because it was signed on a round-robin basis and not signed by the majority of trustees. The court reasoned that modern practice—particularly in light of the effects of COVID-19—recognises that trustees and similar governing bodies frequently meet virtually and execute documents through round-robin processes. The court did not accept that the absence of express mention of round-robin execution in the scheme’s management rules rendered such resolutions fatally defective.


The court placed weight on the scheme’s management rule framework, referring in particular to Regulation (5) of the management rules, which contemplates trustee meetings by “any other method”. The court considered that this language was broad enough to accommodate the method by which the trustees’ decision was taken and recorded.


In addition, the court considered Regulation 10(1)(b) of the statutory management rules, which addresses when documents signed on behalf of a body corporate are valid and binding, including signature requirements tied to trustee resolution authority. The court held that, in practice, a trustee resolution may take the form of a general or special resolution, and that it would not be invalid merely because it was labelled “special” or because of semantic disputes about wording. The court treated the first resolution as clear in intent and purpose: it authorised the launching of legal proceedings to obtain access for inspection, and the litigation was instituted through the managing agent who had been duly involved in the process.


The court further found that the second resolution signed by all five trustees on 20 April 2021 did not materially change the authority position, but instead confirmed and underscored the original authorisation. The court rejected the proposition that the later resolution showed that the first was defective, or that the second was merely “installed” to cure invalidity. The court approached the later resolution as a ratification/confirmation of steps taken, and relied on authority indicating that acts done without authority are not necessarily nullities and can be ratified.


In this regard, the court referred to Marais v City of Cape Town 1997 (3) SA 1097 (CPD) for the proposition that unauthorised action instituted on behalf of a litigant can be capable of ratification, and to Smith v Kwanonqubela Town Council 1999 (4) SA 947 (SCA) for the principle that valid ratification generally requires an intention by the principal to confirm and adopt the unauthorised acts of an agent, expressed with knowledge of material circumstances or with the object of confirming the act in all events. On the papers, the court considered the evidence sufficient to show that trustees were aware of the decision to litigate and that the subsequent resolution confirmed the authority underpinning the proceedings. The authority challenge was therefore rejected and the applicant was held to have been duly authorised to bring the application.


On costs, the court first located the dispute within the broader context of community scheme dispute resolution. It noted that neither party appeared to have seriously pursued the possibility of approaching the Community Schemes Ombud for relief. The court accepted that the High Court retains jurisdiction, but it emphasised that there is an established body of authority recognising that certain disputes falling within the scope of the CSOS Act should, in the first instance, be brought before the Ombud through the statutory conciliation and adjudication framework.


The court relied particularly on Heathrow Property Holdings No 33 Close Corporation and Others v Manhattan Place Body Corporate and Others [2021] 3 ALL SA 527 (WCC), which held (as summarised in the judgment) that where disputes fall within the ambit of the CSOS Act, they should generally be referred to the Ombud first, and the High Court may be entitled or obliged to decline to entertain such matters as a forum of first instance absent exceptional circumstances. The court also referred to Prag N O v the trustees for the time being of the Mitchell’s Plain Industrial Enterprises Sectional Title Scheme Body Corporate 2021 (5) SA 623 (WCC) as part of the developing jurisprudence addressing the interaction between the Ombud’s jurisdiction and that of the High Court.


The court considered that the present dispute (access for inspection relating to water ingress and scheme management) was of a kind that fell within the dispute-resolution mechanisms available under the CSOS Act, and that there were no exceptional circumstances justifying resort to the High Court as a first instance. The court regarded it as significant that the earlier urgent enrolment had failed, because the matter was struck off the urgent roll, which reinforced the conclusion that the matter did not warrant extraordinary High Court intervention on an urgent basis.


The court also invoked Coral Island Body Corporate v Hoge 2019 (5) SA 158 (WCC), where it was stated (as summarised in the judgment) that while courts may not have the power to refuse to hear matters that could be brought under the CSOS dispute-resolution system, they should use their discretion in respect of costs to discourage inappropriate resort to the courts in matters that could more appropriately have been taken to CSOS. The court aligned itself with that policy concern, emphasising the social utility of a cheaper and more informal dispute-resolution mechanism and the risk that such a statutory scheme could be undermined if courts indiscriminately entertained matters better suited for CSOS processes.


At the same time, the court took account of the litigation history and party conduct. It noted that on 20 April 2021, the day before the matter was set down, the respondents made an unconditional settlement offer conceding the relief sought (save for costs and for the costs of the water ingress inspection), and that the applicant rejected that offer on the basis that the defence was frivolous and vexatious. The court also recorded that the respondents had pointed out to the applicant that the matter could be lodged with CSOS and criticised the use of body corporate funds for attorney-driven litigation in circumstances where the Ombud mechanism existed.


Against that background, the court treated the High Court litigation as having been manifestly inappropriately brought as a forum of first instance, and it expressed concern about the scale of the record and the costs consequences of opposed High Court proceedings for what was, in substance, a relatively narrow community scheme dispute. It referred to the policy warning against irresponsible litigation articulated in Limpopo Legal Solutions v Eskom Holdings SOC Limited [2017] ZACC 34, in the context of emphasising that litigants should respect court processes and avoid ill-considered litigation, even where the broader costs landscape may have changed in certain categories of cases.


The court’s ultimate approach to costs reflected an evaluative compromise driven by two considerations that it treated as simultaneously relevant: the applicant’s entitlement to pursue inspection access (which had been resisted and then conceded), and the impropriety of choosing the High Court rather than CSOS as the primary forum. Instead of awarding conventional High Court costs, the court limited the applicant’s costs to the tariff applicable to proceedings under the ambit of the Ombud, thereby discouraging resort to the High Court while still making an adverse costs order against the respondents.


5. Outcome and Relief


The court made no substantive order compelling access, because the respondents had by then permitted access and the further leak detection inspection had already taken place, rendering that relief moot.


On the preliminary point, the court found that the applicant was duly authorised to institute the proceedings, including on the basis that any initial defect alleged by the respondents was not established and, in any event, the later resolution signed by all trustees operated to confirm the authority underpinning the litigation.


On costs, the court ordered that the applicant was awarded costs limited to the tariff applicable to proceedings under the ambit of the Ombud. In addition, the respondents were ordered, jointly and severally, to pay the costs of KLS Consulting Engineers (Pty) Limited, with the one paying the other to be absolved.


Cases Cited


Marais v City of Cape Town 1997 (3) SA 1097 (CPD). Smith v Kwanonqubela Town Council 1999 (4) SA 947 (SCA). Heathrow Property Holdings No 33 Close Corporation and Others v Manhattan Place Body Corporate and Others [2021] 3 ALL SA 527 (WCC). Prag N O v the trustees for the time being of the Mitchell’s Plain Industrial Enterprises Sectional Title Scheme Body Corporate 2021 (5) SA 623 (WCC). Coral Island Body Corporate v Hoge 2019 (5) SA 158 (WCC). Limpopo Legal Solutions v Eskom Holdings SOC Limited [2017] ZACC 34. S S v V V-S [2018] ZACC 5.


Legislation Cited


Community Schemes Ombud Service Act 9 of 2011. Promotion of Administrative Justice Act 3 of 2000.


Rules of Court Cited


No Uniform Rules of Court were cited in the judgment. The court referred instead to statutory and scheme governance instruments described as the Management Rules, including Regulation (5), Regulation 10(1)(b), and rule 11(1)(a).


Held


The court held that the applicant body corporate had been properly authorised to institute the application, rejecting the contention that the initial trustee resolution was invalid merely because it was executed on a round-robin basis or not signed by a majority. The later resolution signed by all trustees was treated as confirming and adopting the decision to litigate, consistent with principles of ratification in the litigation context.


The court further held that the dispute should not have been brought in the High Court as a forum of first instance because it fell within the scope of CSOS dispute resolution and no exceptional circumstances were shown. As a consequence, while the applicant was awarded costs against the respondents, those costs were limited to the scale applicable to Ombud-related proceedings, and the respondents were ordered to pay the costs of the leak detection consultants.


LEGAL PRINCIPLES


The judgment applied the principle that decisions by sectional title trustees may validly be taken and recorded through methods consistent with the applicable management rule framework, and that contemporary decision-making practices (including round-robin execution) are not, without more, inherently invalid where the rules contemplate meetings or decisions by broader methods such as “any other method”.


It applied and relied upon the principle that proceedings instituted without proper authority are not necessarily nullities and may be capable of ratification, provided there is a clear intention by the principal to confirm and adopt the act of the agent, either with knowledge of material circumstances or with an intention to confirm in all events. The court treated subsequent trustee confirmation as sufficient, on the papers, to demonstrate adoption of the litigation decision.


On costs and forum selection, the judgment applied the principle that where disputes fall within the statutory remit of the Community Schemes Ombud Service, such processes function analogously to internal remedies that should generally be pursued before approaching the High Court, absent exceptional circumstances. Even where the High Court has jurisdiction and may not refuse to hear the matter, it may exercise a costs discretion to discourage inappropriate resort to litigation and to promote the use of specialised, lower-cost statutory dispute-resolution mechanisms designed for community scheme disputes.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Western Cape High Court, Cape Town
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2022
>>
[2022] ZAWCHC 99
|

|

Body Corporate of the Sorronto Sectional Title Scheme, Parow v Koordom and Another (5439/2021) [2022] ZAWCHC 99; 2022 (6) SA 499 (WCC) (26 May 2022)

IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
REPORTABLE
CASE
NO: 5439/2021
In
the matter between:
THE
BODY CORPORATE OF THE SORRONTO
SECTIONAL
TITLE SCHEME, PAROW
(SCHEME
N0:
377/1997)
Applicant
and
LEOZETTE
KOORDOM
First
Respondent
WILFRED
BOOYSEN
Second Respondent
Date
of hearing: 19 May 2022
Judgment
delivered: 26 May 2022
JUDGMENT
CARTER,
AJ
INTRODUCTION
[1]
This matter was initially brought before this court on an urgent
basis. It has its
origins and goes back to 29 March 2021, when the
applicant filed its notice of motion. This ostensibly, for one
specific reason,
to compel the first and second respondents to grant
access to Unit 101 of the applicant, more commonly known as Sorrento,
for the
purposes of conducting a leak detection test and inspection.
The facts in this matter are in my view fairly crisp and relatively

simple. In order not to overemphasize all the issues I accordingly
summarise the facts as follows.
[2]
During October of 2020, damp marks appeared on the ceiling of Unit
100
[1]
.
Various
attempts were undertaken to seek access to the second respondent’s
unit which was eventually inspected on 11 November
2020. No leaks
were found in unit 101 belonging to the second respondent. However,
on 25 January 2021, the owner of unit 100 Mr
Gavin Oddy informed the
applicant that the damp problem had not been resolved. What then
transpired
[2]
was an ongoing
effort to gain further access to the second respondent’s unit
but with little success. Various requests to
gain access through the
Managing agents,
[3]
loss
adjusters, leaked detective agents
[4]
and the applicant’s attorneys all fell on deaf ears and the
second respondent thwarted any possible requests for access to
unit
101 without any justifiable reason in my view.
[3]
Whilst n
othing had materialized, and in my
view as a direct result of the recalcitrant actions by the second
respondent who delayed and
refused access to unit 101, the applicant
then resorted to bringing an urgent application. The application
inter alia
requested an order that access be granted to unit 101 within 48 hours
of an order being granted. The matter was set down for Tuesday
20
April 2021, but was eventually only heard by Acting Judge Pangarker
on 30 April 2021, when the matter was struck off the urgent
roll.
[4]
In his answering affidavit the second respondent maintained that
a
leak detection inspection was conducted on his unit in late November
2020, and no leaks were found. There was therefore, in the
second
respondent’s opinion no reason why another inspection should be
conducted.
[5]
Evidently the
second respondent had a change of mind and he accepted that the
applicant is entitled to conduct reasonable inspections
from time to
time in order to properly manage the common property of Sorrento.
[6]
Accordingly the respondents, subsequently permitted access to their
unit and a second leak detection test was conducted. Prayer
two of
the applicant’s notice of motion thus became a nullity and all
that was left to be decided was the issue of costs,
which I shall now
turn my attention to.
LOCUS
STANDI
[5]
As a precursor the issue of authority to institute the urgent
application by the applicant,
was a fundamental argument raised by
Counsel for the respondents. The basis for the aforementioned
emanates from the two resolutions
that were signed by the trustees of
the applicant, the first one dated 19 March 2021, which was signed by
two trustees and the
second one dated 20 April 2021, signed by all
five trustees. Counsel for the respondents argued that the first
resolution is null
and void as it was signed on a round robin basis
and not signed by the majority of the trustees.
[6]
I do not agree with the contention that the first resolution is
defective because
it does not record the date, place and time, nor
that it was signed on a round robin basis. It is common practise what
with the
onslaught and the lagging effects of CV19 that trustees,
shareholders, governing bodies and directors meet virtually and sign
documents
via round robin. To suggest (as Counsel for the respondents
did and a rather cheap shot at that) that because same is not catered

for in the Management Rules of the applicant, any resolution would be
fatally defective is unplausible and unreasonable.
[7]
Regulation (5) of the Management Rules specifically caters for a
trustee meeting by “
any
other method”
which
in my view would encompass and encapsulate the extension of the
method of signing resolutions. It would be absurd to consider
or
apply anything to the contrary.
[7]
Further, the first resolution is in my view clear in its content as
to what the intended
purpose thereof was. There can be no doubt
thereon, as the urgent application was brought, and ensuing
litigation commenced through
the duly appointed management agent of
the applicant.
Regulation 10(1)(b) of the
statutory Management Rules states:

No
document signed on behalf of the body corporate is valid and binding
unless it is signed on the authority of a trustee resolution
by –
(a)
two trustees or the managing agent,
in the case of a clearance certificate... ; and
(b)
two trustees or one trustee and the
managing agent in the case of any other document
.”
Notwithstanding
that the above, a “
trustee resolution
” in practise
can take the format of either being a general or special resolution.
Because this is not specifically stated
for in the Management Rules,
a resolution is a resolution if signed in the manner dictated to
above. The content would surely not
be considered null and void
simply because the word “special” is recorded thereon.
The resolution was special in nature
and specific in intent.
[8]
In my view the second resolution having been signed by all five
trustees of the applicant,
was simply an extension and underscored
the content and purpose of the first resolution. To infer that the
second resolution was
“installed” for the purposes of
remedying a purported shortcoming of the first resolution, is in my
view incorrect
and rejected. The signing of the second resolution did
not provide the applicant with any additional material or substantial
advantage.
By not signing same, it would have at further costs merely
postponed the inevitable day of reckoning, irrespective of the
virtual
impasse that the parties were confronting. On a similar vein,
Fitzgerald AJ in
Marais
v City of Cape Town
[8]
had
the following to say:

In
the contractual field an agreement concluded by an agent on behalf of
his principal is not a nullity for want of authority at
the time of
contracting. For that reason it is capable of ratification. The same
in my view applies to an action instituted on
behalf of a litigant.

[9]
The trustees of the applicant complied with rule 11(1)(a) of the
Management Rules
in order to give effect to or ratify the first
resolution which should be seen as commendable corporate governance
compliance by
a board of trustees. Trustees typically do not meet
daily or weekly but normally once a quarter. It is therefore, not
uncommon
for them to manage the affairs of the body corporate as they
deem fit and in the best interests of the owners.
Ad hoc
and
informal meetings are often held in order to deal with incidents
without having to call or convene a formal meeting of the
trustees.
To thus infer and consider the actions of the applicant to have held
a trustees meeting in terms of section 11(1) (a)
of the Management
Rules, as being untoward, or for sinister reasons and/or ulterior
motives, is not sustainable and inconclusive
on the papers and is
therefore rejected.
[10]
The definition of ratification is as follows:

the
action of signing or giving formal consent to a treaty, contract or
agreement, making it officially valid.”
[9]
This
is precisely what all the trustees implemented by signing the second
resolution, thereby approving and confirming the acceptance
of the
cause and intent of the first resolution. This is further confirmed
and underscored by the applicant in his replying affidavit
whereby he
states as follows:

in
so far as it is necessary to mention, all five of the trustees were
aware of the original resolution as attached to the founding

affidavit and in agreement with its content authorizing these legal
proceedings, despite the fact that only two signed it. As the

portfolio manager, I was the person that obtained the instructions to
proceed.

[10]
[11]
What can clearly be garnered/gleaned from Mr Cloete’s remarks
is that throughout the entire
process all the trustees were aware of
and informed of what was transpiring. Nothing new was raised in the
second resolution save
for the mentioning of the second respondent’s
name. Trustees that serve on body corporates are simply
representatives (duly
elected by the owners) usually not qualified in
the managing and functioning of their respective body corporates.
They are lay
people that rely upon qualified and knowledgeable
managing agents as is the case with Trafalgar Property Management
(Pty) Limited
duly represented by Mr Cloete who deposed of the
founding affidavit. To argue as Counsel for the respondent’s
did, that certain
words being “
is
” and “
to

in the second resolution must be understood and attributed
prospective in interpretation, is with respect splitting hairs
and a
matter of semantics. The same argument applies to the contention that
the word “
ratification
” is not recorded in the
second resolution. The intent and purpose of the contents of the
second resolution did not change
anything and was in my view an
affirmation of that which was stated in the first resolution.
[12]
Counsel for applicant made reference to the view held by Harms JA in
Smith
v Kwanonqubela Town Council
[11]
which
I consider to be as applicable to the current matter, where the
learned Judge stated the following:

it
is in general essential for a valid ratification that there must have
been an intention on the part of the principal to confirm
and adopt
the unauthorized acts of the agent done on his behalf, and that the
intention must be expressed either with full knowledge
of all the
material circumstances, or with the object of confirming the agent’s
action in all events, whatever the circumstances
may be….. the
decision to proceed with the case evinces a clear intention to ratify
whatever action was taken, irrespective
of the legal niceties
involved

The
managing agent ensured that all the trustees were “kept in the
loop” as to what had transpired over several months
with little
cooperation from the second respondent and was then authorised to
take such legal action as per the wording on both
resolutions.
[13]
I am of the view therefore, that the applicant was duly authorised
through its managing agent
to bring the urgent application in the
form of a
mandamus
and the meeting was therefore properly
constituted for purposes of this matter. The two trustees that signed
the first resolution
were not in my view at any stretch of the
imagination, on a frolic of their own and were not at any time not
acting in the best
interests of the applicant in fulfilling their
fiduciary duties as trustees.
COSTS
[14]
I needed to traverse the entire background to this matter in order
for me to finally address
the issue of costs, which I as stated above
I have been called upon to do.
[15]
I
t
is noteworthy, that it is a law of long standing that when a High
Court has a matter before it that could have been brought in
a
Magistrates Court, it has no power to refuse to hear the matter.
Similar considerations apply here. Notwithstanding the
aforementioned,
I got the distinct impression that neither Counsel
had considered the avenue of approaching and engaging with the
Community Schemes
Ombud (hereafter the “Ombud”) whose
powers and dutiful significant purpose
[12]
falls under the
Community Schemes Ombud Service Act
(“the
Act”).
[13]
[16]
Further the courts concurrent jurisdiction with the Ombud is
well-established, albeit the Ombud
has wider jurisdiction on certain
issues and less on others. Both the
Heathrow
Property Holdings N0 33 Close Corporation and Others v Manhattan
Place Body Corporate and Others
[14]
and
Prag
N O v the trustees for the time being of the Mitchell’s Plain
Industrial Enterprises Sectional Title Scheme Body Corporate
[15]
grappled with the question when the Ombud enjoys jurisdiction in
matters pertaining to sectional title schemes and when, on the
other
hand, the appropriate forum is the High Court.
[17]
I
n the Heathrow matter Justice Sher held
that:

In
the result, I am of the view that where disputes pertaining to
community schemes such as sectional title schemes fall within
the
ambit …. of the CSOS Act, they are in the first instance to be
referred to the Ombud for resolution in accordance with
the
conciliative and adjudicatory process established by the Act, and the
court is not only entitled to decline to entertain such
matters as a
forum of first instance, but may in fact be obliged to do so, save in
exceptional circumstances. Such matters will
not be matters which are
properly before the High Court and on the strength of principle which
was endorsed in Standard Credit
(and a number of courts thereafter
including the Constitutional Court in Agriwire), it is accordingly
entitled to decline to hear
them, even if no abuse of process is
involved. In this, as far as the High Court is concerned the
processes which have been provided
for the resolution of disputes in
terms of the CSOS Act are in my view tantamount to “internal
remedies” (to borrow
a term from the Promotion of
Administrative Justice Act) which must ordinarily first be exhausted
before the High Court may be
approached for relief
.”

What
will constitute exceptional circumstances entitling a litigant to
approach the High Court directly will have to be determined
on a
case-by-case basis
.”
[18]
The Act provides broad micro requirements for the Ombud to enjoy
jurisdiction, by way of Prayers
for Relief of which in my view a
number would have relevance to this matter.
[16]
None of these options were considered nor applied by any of the
parties to this litigation. In
Coral
Island v Hoge
[17]
Bins-Ward
J succinctly summarises the situation as follows:

A
nother
was the social utility to be achieved by the provision of a
relatively cheap and informal dispute resolution mechanism for
the
disposal of community scheme related issues. It requires little
insight to appreciate that those commendable policy considerations

would be liable to be undermined if the courts were indiscriminately
to entertain and dispose of matters that should rather have
been
brought under the Ombud Act. Whilst judges and magistrates may not
have the power to refuse to hear such cases, they should
in my view,
nonetheless use their judicial discretion in respect of costs to
discourage the inappropriate resort to the courts
in respect of
matters that could, and more appropriately should, have been taken to
the Community Schemes Ombud Service.

[19]
In applying the above legal guidance to the present case, I am of the
view that this matter should
never have been brought before this
court as first instance. This is underscored by the fact that the
urgency in the matter was
rejected by Pangarker AJ referred above.
There are no exceptional circumstances pertaining to this matter, but
rather issues that
fall squarely within the ambit of the Ombud that
can and would have been expeditiously dealt with at no cost as the
employ of legal
representatives is not permitted.
[20]
However on 20 April 2021, the day before the matter was set down for
hearing, the respondent’s
made an unconditional offer of
settlement in which he conceded the relief sought in the application
(after taking legal advice
[18]
),
save for costs of this application and for the applicant having to
carry the costs of the water ingress inspection.
[19]
These terms were rejected by the applicant based on the rationale
that the respondents conduct in defending this application was

frivolous and vexatious.
[20]
To compound matters further for the applicant, the respondent
conveyed to the agent of the applicant that the body corporate:
“…
should
refrain from
misusing
body corporate funds by wanting to appoint an attorney, if the
Community Scheme Ombud’s Service is available for
such matter.
They are welcome to lodge the matter with CSOS.
[21]

In
so doing the respondents were expressing their view as to the
possible inappropriateness of the applicant resorting to litigating

this minor dispute in the High Court. Such action cannot in my view
be condoned especially as further detailed and evidenced in
paragraph
7 of the applicant’s letter from their attorney’s pga
Incorporated dated 17 March 2021.
[22]
[21]
Some 198 pages forms the record in this matter much of which could
have been circumvented, if
the applicant had approached the Ombud in
the first place. It is therefore regrettable that the parties could
not reach agreement
to settle this matter before such lengthy and
unnecessary litigation ensued in the High Court. There is a moral and
ethical duty
upon legal practitioners to act in the best interests of
their clients and this also includes curtailing any legal costs which
will be incurred, when litigation of this nature is embarked upon. In
this regard Bins-Ward J had the following to say:

I
think that I am able to take judicial notice that the attorney and
own client costs of any applicant in opposed litigation in
the High
Court, even in a relatively straightforward matter not involving
voluminous papers nor meriting the engagement of counsel
of more than
junior or middle ranking stuff gown status, would easily exceed
R25,000. And such estimate leaves out of account altogether
the
contingency of the postulated applicant having to pay the other
side’s costs on a party and party basis should there
be an
adverse judgment.

[23]
Litigants
and their respective legal advisors must take heed of the
availability of the Ombud in matters that are uncomplicated,
require
a more conciliatory approach at vastly less costs with a considerably
more expedient manner of processing. I am finally
of the view that
this litigation was frivolous or vexatious (depending upon which
parties you are viewing from) and manifestly
inappropriately brought
in the High Court forum. I am considerably swayed by what the Court
aptly stated in
Limpopo
Legal Solutions v Eskom Holdings SOC Limited
[24]
:

Although
Biowatch changed the costs landscape for constitutional litigants, it
gives no free pass to cost-free, ill-considered,
irresponsible
litigation and applicants seeking to vindicate constitutional rights
must respect court processes.
[22]
Accordingly, the following order is therefore made:
1.
The applicant is granted costs on the
tariff applicable in respect of proceedings under the ambit of the
Ombud.
2.
The respondents are to pay the costs of KLS
Consulting Engineers (Pty) Limited jointly and severally, the one
paying the other to
be absolved.
G
L CARTER
ACTING
JUDGE OF THE HIGH COURT
For
applicant:
Adv. G Viljoen
Instructed
by:
Preshnee Govender Inc.
For
Respondents:     Adv. A Walters
Instructed
by:
Hickman Van Eeden Phillips Inc.
[1]
Unit
100 and 101 are members of the body corporate comprising of 102
units of the applicant
[2]
For
the period 25 January 2021 to 21 April 2021
[3]
Trafalgar
Property Management (Pty) Limited
[4]
KLS
Consulting Engineers (Pty) Limited – record page 107
[5]
Record
page 63
[6]
Record
page 64
[7]

This
round-robin procedure may be profitably used if urgent decisions
need to be taken or where there are
only
a limited number of trivial maters to be determined and it is not
considered worth convening a
meeting.”
Van der Merwe Sectional Titles in Van
der Merwe and Sonnekus Sectional Titles, Share Blocks and
Time-sharing Vol 1. This form
of signing resolutions has to some
extent become a norm what with the onslaught and unprecedented VC19
pandemic in modern times
[8]
1997
(3) SA 1097 (CPD)
[9]
Oxford
English Dictionary
[10]
Record
page 89 para 15
[11]
199
(4) SA 947
(SCA)
[12]
To
provide for the Community Scheme Ombuds Service; to provide for its
mandate and functions; and to provide for a dispute resolution

mechanism in schemes; and to provide for matters connected therewith
[13]
No
9 of 2011
[14]
[2021]
3 ALL SA 527
(WCC)
[15]
2021
(5) SA 623 (WCC)
[16]
Section
39(4)(b) and (c) and/or Section 39(6)(a), (c) and (e)
[17]
2019
(5) SA 158 (WCC)
[18]
Record
page 64 para 9
[19]
Record
page 64 para 10
[20]
Record
page 88 para 12
[21]
Record
page 25
[22]
Record
page 52
[23]
Ibid
fn 13
[24]
[
2017]
ZACC 34
– Kollapen AJ (as he then was) made reference hereto
in S S v V V -S
[2018] ZACC 5