Viljoen N.O and Others v Du Preez (13082/2020) [2021] ZAWCHC 235 (16 November 2021)

80 Reportability
Administrative Law

Brief Summary

Contempt of Court — Breach of court orders — Application to compel compliance with prior court orders and declare respondent in contempt — Respondent failed to comply with 2016 order prohibiting diversion of water — Respondent's actions constituted clear contravention of court order despite claims of compliance — Court found respondent in contempt and granted final interdict.

Comprehensive Summary

Summary of Judgment


Introduction


The proceedings were brought as an application in the High Court (Western Cape Division, Cape Town) seeking to compel compliance with two prior orders of the same court, to obtain contempt-related relief arising from alleged non-compliance, and to secure interdictory protection against alleged assault and threats. Although the notice of motion initially contemplated a rule nisi and interim relief, the matter ultimately proceeded on the basis that final relief was sought.


The applicants were Philippus Jakobus Viljoen (Snr) NO, Philippus Jakobus Viljoen (Jnr) NO, and Arnoldus Jacobus Stofberg NO, in their capacities as co-trustees of the PJ Viljoen Boerderytrust (the “Viljoentrust”), together with Philippus Jakobus Viljoen (Jnr) in a further cited capacity. The respondent was Hennie du Preez. The parties were farming neighbours with a history of prolonged litigation.


The procedural history centred on two earlier interim orders pending the finalisation of action proceedings under case number 15076/14. The first was an order of 25 June 2014 (Gamble J, case number 9833/14) regulating a stone deflection wall at a point in the stream where water was historically divided. The second was an order of 13 December 2016 (Davis J, case number 8067/2016) directing closure of a man-made channel (“the furrow”) and associated works used to divert water; that 2016 order had been appealed and the appeal was dismissed on 11 October 2017 by a full bench of the division.


The general subject-matter of the dispute concerned water abstraction and diversion works affecting the parties’ farms, specifically the flow from a stream system involving the Watervalstroom and its upper source, the Donkerkloofstroom, as well as conflict about inspection and maintenance of the watercourse and related confrontations between the parties.


Material Facts


The farms were situated along a watercourse system in which water flowed from a mountainous area down over Bergplaas towards Kanonkop and Dennelaan and then to De Liefde. The Viljoentrust owned De Liefde, while the respondent occupied (and was in the process of buying) Kanonkop, Dennelaan and Bergplaas. A central factual feature was the existence of a water source (Watervalstroom, flowing from Donkerkloofstroom) serving the farms, and a history of conflict about how water was diverted and shared.


In relation to the 2016 order, it was undisputed that in 2015 the respondent had opened an old, unused man-made channel referred to as “the furrow” and used it to extract water from the Donkerkloofstroom into installed works (including a manhole and an underground pipe) to convey water directly to Kanonkop. The 2016 order required the respondent (and other respondents in that matter) to close the furrow together with all pipes and relevant works installed in terms of which water had been diverted from the Watervalstroom or its sources to Kanonkop. The appeal against that order was dismissed on 11 October 2017.


It was common cause that, while the appeal was still pending, the respondent installed a new 110 mm PVC pipe leading from the entrance of the furrow to a manhole. The respondent accepted that his attorney told him on 11 October 2017 to close the furrow immediately in compliance with the 2016 order. The respondent contended that he removed an upper section of the pipe and moved it away from the furrow, and he relied on photographs taken on 13 October 2017. The applicants disputed that account, asserting that on 17 October 2017 a new pipe was positioned in the Donkerkloofstroom and used to convey water via the furrow to the manhole, with the manhole not being closed and water continuing via pipeline to Kanonkop.


What was not disputed was that on 23 October 2017 the Sheriff attended the site and issued a return recording that the furrow and associated works were closed as per the order, supported by photographs. The respondent did not dispute the Sheriff’s attendance and return. It was also not disputed that some water flowed through an asbestos pipe serving as an intake into the manhole, though the respondent contended this was attributable to a small fountain upstream and unrelated to earlier litigation.


In relation to events in August 2020, it was not denied that after heavy winter rains the applicants found the manhole reopened and water again flowing from the Donkerkloofstroom via the furrow to the manhole, and from there via a 110 mm pipe to Kanonkop. The applicants recorded what they found (including by drone footage) and demanded compliance by letter on 24 August 2020, which received no response. The respondent denied reopening the furrow personally and advanced explanations including reliance on the small fountain, an interpretation of the 2016 order as not requiring closure of the large pipe if used for a different source, and an assertion that flooding had washed the furrow open.


The small fountain issue was materially disputed, with opposing expert opinions: the applicants’ expert, Professor du Plessis, considered the small fountain water to form part of the Watervalstroom, while the respondent’s expert, Mr Theron, asserted it did not. It was common cause that, although the respondent alleged discovery of the small fountain in 2016, it had not been raised in prior litigation as an existing lawful use and had not been judicially determined in that context.


In relation to the 2014 order, the undisputed background was that the order concerned a point lower downstream in the Watervalstroom, described as the first division point, where a temporary stacked rock deflection wall (a “klipkeerwal”) was historically erected to divert water to De Liefde until De Liefde’s dams were full, after which it would be taken down to allow flow to Kanonkop. The 2014 order granted the applicants the right annually to erect such a deflection wall, with removal by the respondent after De Liefde’s dams were full.


It was common cause that on 5 June 2019 the respondent demolished the deflection wall and reconstructed it. The respondent claimed he did so because the wall was not operating as intended due to sand and debris and that he repacked it to conform with the 2014 order. The applicants contended that the rebuilt wall now allowed substantially more water through to Kanonkop (about a third), resulting in De Liefde receiving only about two-thirds of the flow at that division point, contrary to the arrangement protected by the 2014 order. The respondent attempted to attribute later repairs to the second applicant and his workers after an alleged flash flood in July 2019, but the applicants relied on correspondence from the respondent dated 31 July 2019 indicating that the respondent had recently reconstructed the wall, and on diary material suggesting the respondent’s recollection may have conflated events from June 2018.


In relation to personal violence, the applicants alleged an assault on 20 June 2017 at the Donkerkloofstroom area. On the respondent’s own version, he admitted slapping the applicant and holding him down while striking him further, though he asserted provocation. A further factual element was a WhatsApp message sent by the respondent on 24 August 2020 stating, in Afrikaans, that it appeared to be time again for “a lesson in manners” (“alweer”), which the applicants relied upon as a threat linked to the prior assault.


Legal Issues


The central legal questions concerned whether the applicants were entitled to final interdictory and enforcement relief compelling compliance with the 2014 and 2016 orders, and whether the respondent’s conduct justified contempt-related proceedings and protective interdicts restraining assault, threats, and interference with inspection and maintenance of the water sources.


A substantial component of the dispute involved the application of law to fact in motion proceedings, particularly whether the alleged contraventions of the existing court orders were established on the papers and whether any disputes of fact were genuine and material such that they could not be resolved without oral evidence.


A further legal issue arose from the respondent’s reliance on the small fountain: whether abstraction from that fountain fell within the ambit of the 2016 order (as a “source of the Watervalstroom”) or constituted a different source potentially supporting a distinct entitlement. This raised a factual dispute (including expert disagreement) with direct legal consequences for the scope of compliance and the appropriateness of contempt relief.


The claim for protection against assault and threats engaged the legal requirements for a final interdict, including whether there was a clear right, injury committed or reasonably apprehended, and the absence of an adequate alternative remedy.


Court’s Reasoning


The court approached the matter on the basis that final relief was sought. It set out the requirements for a final interdict, namely a clear right, an injury committed or reasonably apprehended, and the absence of similar protection by another ordinary remedy. It emphasised that irreparable harm is not a requirement for a final interdict, and noted that a clear right is a matter of substantive law.


Because the matter proceeded by motion, the court reaffirmed that motion proceedings are generally suited to resolving legal issues on common-cause facts, and not to determining probabilities on disputed factual disputes. The court applied the Plascon-Evans approach, explaining that final relief can be granted only where the admitted facts in the applicant’s affidavits, together with the respondent’s version, justify the order. At the same time, it considered the recognised qualification that a court is not required to accept denials that are bald, fictitious, palpably implausible, far-fetched, or clearly untenable on the papers.


On the 2016 order, the court identified the respondent’s own admissions as decisive in important respects. The respondent admitted installing the 110 mm pipe, which the court treated as a clear contravention of the 2016 order. The Sheriff’s return of 23 October 2017, which was not disputed, recorded that the furrow and relevant works were closed by the applicants’ side in execution of the order; however, the court noted that what the Sheriff found (including a new pipe positioned and conveying water to the manhole, and non-closure of the manhole and underground pipe) indicated that the respondent had failed to comply with what the 2016 order required, namely closure of the furrow, manhole, and pipes. The court rejected as contrived and highly improbable the respondent’s suggestion that someone else had staged the contravention by moving the pipe and sandbags, reasoning that the admitted facts supported the inference that the respondent had removed the pipe reluctantly and left it close enough to enable further diversion.


Regarding the August 2020 reopening, the court rejected the respondent’s explanation that flash flooding had washed open the works. It reasoned that the state of the site as discovered—reopening of the manhole and renewed flow via the furrow to the manhole and then through the 110 mm pipe—was inconsistent with the closure measures previously put in place with the Sheriff’s assistance, and that the respondent’s flood narrative was improbable and far-fetched, particularly given the physical indications referred to by the applicants (including the persistence of logs while rocks were allegedly displaced).


The respondent’s interpretive contention that the 2016 order did not require closure of the manhole and large pipe unless used for Watervalstroom sources was addressed by reference to the express wording of the order, which required closure of the furrow together with all pipes and works installed in terms of which water had been diverted from the Watervalstroom or its sources to Kanonkop. The court considered there to be no doubt that the manhole and large pipe were included because they were central to the prior litigation. The court nevertheless accepted, as a matter of interpretation of the order’s language, that if water were in fact from a different source (not the Watervalstroom or its sources), that abstraction would not be covered by the 2016 order’s prohibition as framed, while adding that any such abstraction would still have to be lawful and respectful of other parties’ rights. This interpretive issue was treated as intertwined with the small fountain dispute.


On the small fountain itself, the court held that the conflicting expert evidence and the broader disputes about whether the fountain formed part of the Watervalstroom system could not appropriately be resolved on affidavit. It considered the dispute to involve significant factual disagreements requiring testing through oral evidence. The court also treated it as material that, although the respondent alleged knowledge of the fountain since 2016, it had not been raised previously as an existing lawful use and thus had not been adjudicated. Because the small fountain question bore on whether contravention (and particularly contempt) could be determined, the court declined at that stage to grant the contempt relief sought in respect of the 2016 order, but still ordered the respondent to comply with the 2016 order to the extent that it applied to diversion from the Watervalstroom or its sources.


On the 2014 order, the court focused on the undisputed fact that the respondent demolished and reconstructed the deflection wall in June 2019, and on the consequences of the rebuilt wall’s operation. It reasoned that, even if the respondent’s stated motives were to restore proper operation, the 2014 order conferred the right to erect the wall on the applicants, not the respondent, and the respondent was not entitled to unilateral self-help. The court found the respondent’s attempt to attribute responsibility to the applicants’ later repairs to be improbable, particularly in light of the respondent’s own correspondence indicating he had recently reconstructed the wall, and because it would make little sense for the applicants to build a structure detrimental to their own water allocation.


The court treated it as not seriously disputed that the reconstructed wall’s outcome was that only about two-thirds of the water flowed towards De Liefde at that division point, with a larger portion flowing through to Kanonkop than previously, and concluded that this was contrary to the express terms of the 2014 order. It therefore found that the respondent had transgressed the 2014 order.


On the assault and threats, the court reasoned that, on common cause facts, the respondent admitted conduct amounting to assault, and that even on the respondent’s version any asserted provocation did not justify the extent of the admitted violence (including holding the applicant down and striking him). The court further interpreted the August 2020 WhatsApp message (“again time for a lesson in manners”) as a reference to the earlier assault and as a threat of repetition, supporting a conclusion that further assault was reasonably apprehended. It accepted that the absence of prosecution of the 2017 incident left the applicant without an adequate alternative remedy and justified final interdictory protection.


On costs, the court considered that costs should follow the result and criticised the respondent’s conduct as demonstrating disregard of existing court orders and repeated self-help. It regarded the applicants as having been compelled to return to court to vindicate rights already secured by previous orders, warranting censure through a punitive scale.


Outcome and Relief


The court ordered the respondent to comply forthwith with the 13 December 2016 order by closing the furrow, pipes, and manhole by which water was being diverted from the Watervalstroom or its sources to Kanonkop. It referred for oral evidence the question whether the small fountain used by the respondent from 2016 formed part of the Watervalstroom or came from a different source.


The court ordered the respondent to comply forthwith with the 25 June 2014 order by demolishing the stone deflection wall erected by him at the first division point and permitting the applicants to erect a stone deflection wall in its place. The respondent was called upon to give reasons why he should not be held in contempt of the 2014 order, and those contempt-related proceedings were referred to oral evidence on the opposed motion roll, with directions regarding exchange of witness statements where witnesses were to be called.


The court granted a final interdict restraining the respondent from assaulting or threatening to assault the fourth applicant, from interfering with the applicants’ inspection and maintenance of the Watervalstroom and Donkerkloofstroom sources, and from coming within 100 metres of the fourth applicant or his employees at any time.


The respondent was ordered to pay the applicants’ costs on the scale as between attorney and client.


Cases Cited


Stern & Ruskin NO v Appleson 1951 (3) SA 800 (W).


National Director of Public Prosecutors v Zuma [2009] ZASCA 1; 2009 (2) SA 277 (SCA).


Plascon-Evans Paints (TVL) Ltd v Van Riebeck Paints (Pty) Ltd 1984 (3) SA 623 (A).


Fakie NO v CCII Systems (Pty) Ltd 2006 (4) SA 326 (SCA).


Thint (Pty) Ltd v National Director of Public Prosecutions; Zuma v National Director of Public Prosecutions [2008] ZACC 13; 2008 (2) SACR 421 (CC).


Petersen v Cuthbert & Co Ltd 1945 AD 420.


Truth Verification Testing Centre CC v PSE Truth Detection Centre CC 1998 (2) SA 689 (W).


Rosen v Ekon [2000] 3 All SA 23 (W).


Ripoll-Dausa v Middleton NO [2005] ZAWCHC 6; [2005] 2 All SA 83 (C); 2005 (3) SA 141 (C).


President of the Republic of South Africa v South African Rugby Football Union 2000 (1) SA 1 (CC).


Legislation Cited


Government Notice 538 of 2016 (General Authorization).


Rules of Court Cited


No specific rule of court was expressly cited in the judgment, although the judgment referred generally to motion-proceeding principles and to referral of disputes to oral evidence.


Held


The court found that the respondent had acted in breach of the 2016 order by installing and utilising diversion works (including the 110 mm pipe) contrary to the order’s requirement to close the furrow and associated works used to divert water from the Watervalstroom or its sources to Kanonkop, and it ordered immediate compliance. However, because a material factual dispute existed as to whether the small fountain constituted part of the Watervalstroom system, the court referred that issue to oral evidence and did not grant contempt relief in respect of the 2016 order at that stage.


The court found that the respondent had transgressed the 2014 order by unilaterally demolishing and reconstructing the stone deflection wall at the first division point, in circumstances where the order conferred the right to erect the wall on the applicants. It ordered demolition of the respondent’s wall and restoration of the applicants’ right to erect the wall. It further initiated contempt-related proceedings concerning the 2014 order by calling upon the respondent to show cause and referring the contempt issue to oral evidence.


The court found on common cause material that the respondent had assaulted the relevant applicant in 2017 and that a further assault was reasonably apprehended in light of the respondent’s later threatening communication, warranting final interdictory relief restraining assault, threats, interference with inspection and maintenance, and proximity within 100 metres.


LEGAL PRINCIPLES


A party seeking a final interdict must establish a clear right, an injury committed or reasonably apprehended, and the absence of similar protection by another ordinary remedy. The judgment treated irreparable harm as not being a requirement for a final interdict, while recognising its relevance to interim relief, and it approached the applicants’ entitlement through the ordinary final-interdict framework.


In motion proceedings, final relief depends primarily on the resolution of legal issues on common-cause facts, and disputes of fact are governed by the Plascon-Evans principle: a final order may be granted only if the facts admitted by the respondent, together with the respondent’s version, justify the relief. The judgment applied the qualification that courts are not bound to accept versions that are bald, fictitious, palpably implausible, far-fetched, or untenable on the papers, while emphasising that courts should also not uncritically accept all asserted disputes at face value where they are not genuine.


Where there are real, material disputes of fact that cannot satisfactorily be resolved on affidavit, especially where expert opinion is diametrically opposed on a question central to the relief, the appropriate course is referral to oral evidence. The judgment applied this approach to the disputed hydrological and factual question of whether the small fountain formed part of the Watervalstroom system.


The judgment applied the principle that parties are expected to comply with existing court orders and should not resort to unilateral self-help in circumstances regulated by such orders. In determining contravention of the 2014 order, the judgment treated unilateral demolition and reconstruction by a party not authorised by the order as conduct inconsistent with compliance, regardless of asserted benign motive, particularly where the order allocated the right to erect the relevant structure to the opposing party.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Western Cape High Court, Cape Town
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2021
>>
[2021] ZAWCHC 235
|

|

Viljoen N.O and Others v Du Preez (13082/2020) [2021] ZAWCHC 235 (16 November 2021)

IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case
No: 13082/2020
In
the matter between:
PHILIPPUS
JAKOBUS VILJOEN (SNR) NO
First Applicant
(in
his capacity as co-trustee of the PJ VILJOEN
BOERDERYTRUST)
PHILIPPUS
JAKOBUS VILJOEN (JNR) NO
Second
Applicant
(in
his capacity as co-trustee of the PJ VILJOEN
BOERDERYTRUST)
ARNOLDUS
JACOBUS STOFBERG NO
Third Applicant
(n
his capacity as co-trustee of the PJ VILJOEN
BOERDERYTRUST)
PHILIPPUS
JAKOBUS VILJOEN (JNR) NO
Fourth
Applicant
and
HENNIE
DU PREEZ
Respondent
JUDGMENT
DELIVERED ELECTRONICALLY ON 16 NOVEMBER 2021
MANGCU-LOCKWOOD,
J
I.
INTRODUCTION
[1]
This
is an application to compel compliance with two orders of this Court
which were granted on 25 June 2014 (per Gamble, J under
case number
9833/14) and 13 December 2016 (per Davis, J under case number
8067/2016); to declare the respondent in contempt thereof;
and to
interdict the respondent from assaulting and threatening the fourth
applicant. Although the applicant initially sought the
relief in the
form of a rule
nisi
and interim relief, by the time the matter appeared before me, final
relief was sought.
[2]
The
parties are farming neighbours who have been embroiled in litigation
for a considerable period of time. The applicants represent
a trust
referred to as the Viljoentrust, which owns De Liefde the farm. The
respondent occupies Kanonkop, Dennelaan and Bergplaas,
and has been
in the process of buying them.
[3]
The
litigation between the parties involves a water source that serves De
Liefde, Kanonkop and Dennelaan. The water source is a
stream known as
Watervalstroom, which flows from an upper source, the
Donkerkloofstroom. The origin of the water is a mountainous
area from
which the water flows in a southerly direction over Bergplaas towards
Kanonkop, Dennelaan and then De Liefde.
[4]
The
comprehensive background to this matter is set out in the judgment of
Davis, J of 13 December 2016 (“
the
2016 Order”
),
which was a sequel
to
the 2014
order granted by Gamble J (“
the
2014 Order”)
.
Both of these orders were interim orders pending finalisation of
action proceedings which are pending under case number 15076/14.
II.
APPLICABLE LAW
[5]
Since what is now sought
is final relief, the applicants are required to establish a
(a) a clear right; (b) an injury actually committed or reasonably
apprehended; and (c) the absence of similar protection by any
other
ordinary remedy.
[6]
Irreparable
injury, though relevant in the context of interim interdicts, is not
a requirement for the grant of a final interdict. A
clear right
is a matter of substantive law.
In
respect of a vindicatory claim it is presumed, until the contrary is
shown, that the applicant will suffer irreparable harm,
absent an
interdict.
[1]
[7]
As
regards the resolution of disputes, motion proceedings, unless
concerned with interim relief, are all about the resolution of
legal
issues based on common cause facts. Unless the circumstances are
special they cannot be used to resolve factual issues because
they
are not designed to determine probabilities.
[2]
[8]
It
is well-established under the
Plascon-Evans
[3]
rule
that where in motion proceedings disputes of fact arise on the
affidavits, a final order can be granted only if the facts
averred in
the applicant's affidavits, which have been admitted by the
respondent, together with the facts alleged by the latter,
justify
such order.
[9]
It
may be different if the respondent’s version
consists
of bald or uncreditworthy denials, raises fictitious disputes of
fact, is palpably implausible, far-fetched or so clearly
untenable
that the court is justified in rejecting them merely on the
papers.
[4]
[10]
On
the other hand, it is equally undesirable for a court to take all
disputes of fact at their face value.
[5]
If this were done a respondent might be able to raise fictitious
issues of fact and thus delay the hearing of the matter
to the
prejudice of the applicant.
[6]
For example, a
hollow
denial or a detailed but fanciful and untenable version does not
create a dispute of fact.
[7]
[11]
In
every case the court should examine the alleged disputes of fact and
determine whether in truth there is a real
[8]
issue of fact that cannot be satisfactorily resolved without the aid
of oral evidence. Whether a factual dispute exists is not
a
discretionary decision;  it is a question of fact and a
jurisdictional pre-requisite for the exercise of the discretion
given
by the rule.
[9]
It is not a question of any difference of character between the
various kinds of claims being enforced, but a question of the proper

method of determining in each case the facts upon which any claim
depends.
III.
CONTRAVENTION
OF THE 2016 ORDER
[12]
The
events resulting in the 2016 Order were that in 2015
the
respondent had opened an old, unused man-made water channel
which
the parties referred to as ‘the furrow’,
and
used it to extract water from the Donkerkloofstroom into a large
underground pipe that he had laid over Bergplaas, to convey
water
directly to Kanonkop.
[13]
The 2016 Order ordered
the respondent and other respondents in that case to “
close
the manmade water channel referred to as ‘the furrow’
together with all pipes and other relevant works installed
by first
respondent in terms of which water has been diverted from the
Watervalstroom or the sources of the Watervalstroom to the
farm
Kanonkop”
. The
respondent appealed the 2016 Order, and the appeal was dismissed on
11 October 2017 by a full bench of this Division.
[14]
However,
in
July 2017, while the 2016 Order was under appeal, the respondent
installed a new PVC pipe of 110 millimeters in diameter leading
from
the entrance of the furrow to the manhole. According to him this was
in the hope that the 2016 judgment would be successfully
appealed.
The respondent also admits that on 11 October 2017, when the appeal
was dismissed, his attorney informed him to close
the furrow
immediately, in compliance with the 2016 Order. The respondent
maintains that he did remove the upper section of portion
of the pipe
away from the furrow, and placed it against a bush on higher ground,
and has attached photographs that he took on 13
October 2017 to
support his version.
[15]
The
fourth applicant refutes the respondent’s version, stating that
he (fourth applicant) personally attended the area on
17 October 2017
and discovered that a new pipe had been positioned in the
Donkerkloofstroom, and was used to convey water
via
the furrow to the manhole; and that the manhole was not closed but
that water was conveyed from it
via
the pipeline to Kanonkop.  On the same day, 17 October 2017 the
applicants’ attorney sent a letter to the respondent’s

attorneys recording the transgression encountered, and attached
photographs depicting the new pipe leading from the furrow to the

manhole. The respondent vehemently denies the applicants’
version in this regard and suggests that someone must have moved
the
pipe from where he had left it on 11 October 2017, as well as
sandbags that were placed in the entrance to the furrow.
[16]
What
is not in dispute is that on 23 October 2017 the Sheriff attended the
location, and thereafter issued a return of service which
recorded as
follows: “
The
manmade water channel referred to as “the furrow” with
all pipes and other relevant works, installed by the first
respondent
in terms of which water has been diverted from Watervalstroom or the
source of the Watervalstroom to the farm Kanonkop,
was closed by the
second applicant, Phillip Viljoen and his workers as per order.
Photos attached”.
Indeed
the Sheriff’s return was accompanied by photographs to this
effect.
[17]
The
evidence of the Sheriff's visit is not disputed by the respondent.
The respondent also admits that some water did flow through
the
asbestos pipe that served as an intake into the manhole. He states
however, that this water originates from a small fountain

approximately 40 metres upstream from the manhole, and states that
this small fountain is not relevant to any previous court
applications
between the parties. According to the respondent this
small fountain has, for a couple of years during the winter months
flowed
down to join the furrow from where it flowed for about 20
meters further downstream to the manhole. I deal with the issue
regarding
the small fountain below.
[18]
What
is relevant for present purposes is that the respondent admits to
installing the 110mm pipe, which was a clear contravention
of the
2016 Order. In addition, what the Sheriff found on the day in
question is not in dispute, namely a new pipe which had been

positioned in the furrow exit and conveying water to the manhole;
that the manhole had not been closed; and that the large underground

pipe had not been closed. What the 2016 Order required was closure of
the furrow, the manhole and pipes, and the respondent failed
to
comply with it. There is no doubt that the respondent acted in clear
breach of the 2016 Order in October 2017.
[19]
As
regards the respondent’s version of events - that someone else
must have staged the contempt of the 2016 Order - I find
it contrived
and highly improbable. Rather, the admitted facts show that it was
the respondent who removed the pipe reluctantly,
and thereafter left
it not too far away, and in fact only moved the front end a few
metres away. It is not too hard to conclude
that this was to enable
him to continue with unlawful abstraction of water from the
Watervalstroom at will.
[20]
I take
note of the fact that the applicants did not immediately approach the
Court for assistance to enforce the 2016 Court Order
after the
respondent’s transgression in October 2017. However, it was to
become a precursor to the events that precipitated
these proceedings.
[21]
In
August
2020,
after
heavy winter rains, De Liefde
had received
minimal water and, upon inspection, the applicants discovered that
the manhole had been opened again, and that water
was again flowing
from the Donkerkloofstroom
via
the furrow to the manhole, and from there
via
the 110 mm pipe to Kanonkop.  This was in contrast with what the
applicants had left in place with the assistance of the Sheriff
in
October 2017, namely the closure of the manhole by placing large
rocks in it and also removing rocks, logs and branches supporting
the
lower embankment thereof; and removing the 110mm pipe.
The
applicants took drone footage of what they saw on 23 August 2020, and
also addressed a letter through their attorneys dated
24 August 2020
which recorded the further contravention of the 2016 Order, and
demanded closure of the furrow and all pipes and
waterworks and
removal of all obstructions, failing which legal action would be
taken. No response was received to this letter.
[22]
The
respondent does not deny what was discovered by the applicants on 23
August 2020, although he denies that he personally re-opened
the
furrow. The respondent relies on three main contentions to refute the
claim against him in this regard.
[23]
First, the
respondent relies on the discovery of the small fountain I have
briefly mentioned earlier. According to the respondent,
abstracting
water from the smaller fountain via a smaller furrow does not amount
to a transgression of the 2016 Order because the
smaller fountain and
furrow do not constitute sources from the Watervalstroom, and this
water abstraction is lawful in terms of
the general authorization
promulgated in Government Notice 538 of 2016 (“
the
General Authorization”
).
[24]
In dealing with
the issue of
the small fountain, both parties rely on expert reports which are
diametrically opposed. According to the applicants’
expert,
Professor du Plessis, the water emanating from the small fountain
would form part of the Watervalstroom, whereas the respondent’s

expert, Mr Theron, states the opposite.
In
my view, the issue of whether or not the small fountain is separate
from the Watervalstroom water, including the expert evidence
upon
which the parties rely on this issue, is not appropriate for
resolution on the papers, and should be referred for oral evidence.

There are vast and  significant disputes between the parties
regarding these issues which need to be tested by means of oral

evidence.
It
is also common cause that the small fountain, although allegedly
discovered by the respondent in 2016, was not raised in the

litigation by the respondent as an existing lawful use, and as a
result, did not form part of the consideration by the Court. In
other
words, it is yet to be considered by a Court of law as an existing
lawful use. In light of all these considerations, I take
the view
that the issue relating to the small fountain should be referred for
oral hearing.
[25]
Second,
the respondent’s response to the applicant’s complaint is
an interpretative argument that it was not the intention
of the 2016
Order to close the big pipe flowing from the manhole to Kanonkop
unless it is utilized to convey water from the furrow
and/or the
Watervalstroom or Donkerkloofstroom to Kanonkop. In other words, the
2016 Order does not require that the manhole and
large underground
pipe be closed if it is used for purposes of abstracting water from a
source that does not form part of the Watervalstroom.
[26]
The
express terms of the Order were for the furrow to be closed,

together
with all pipes and other relevant works installed by first respondent
in terms of which water has been diverted from the
Watervalstroom or
the sources of the Watervalstroom to the farm Kanonkop”.
There is no doubt that the large
pipe and manhole were included in the 2016 Order since they were the
subject of the litigation.
If, however, water should be discovered
from a source other than the Watervalstroom, then, subject to other
parties’ rights
to water use, my view is that it is not covered
by the terms of the 2016 Order. This is because the 2016 Order
proscribes respondent’s
installations  “
in
terms of which water has been diverted from the Watervalstroom or the
sources of the Watervalstroom”.
After
all, the litigation between the parties which resulted in the 2016
Order related to abstraction of water from the Watervalstroom
or from
sources thereof.
If,
h
owever, such a
different source should be discovered, the water must be abstracted
lawfully, with due regard to other parties’
rights to shared or
communal water rights. It is clear that this interpretative argument
is related to the respondent’s contention
regarding the small
fountain discussed above, in that, if
it
is found that the small fountain does constitute a different source
from the Watervalstroom, then the respondent may well have
a right to
abstract the water, provided that is done lawfully, without resorting
to unlawful means.
[27]
Third,
the respondent’s explanation for what was discovered on 23
August 2020 is that the furrow had been washed open by extensive

flooding which took place over the previous three years.  One
only needs to restate what was discovered on that day in order
to
reject the respondent’s version as being highly improbable and
far-fetched. The manhole had been re-opened; water was
again flowing
from the Donkerkloofstroom
via
the furrow to the manhole, and from there
via
the 110 mm pipe to Kanonkop.  This was in contrast with what the
applicants had left in place with the assistance of the Sheriff
in
October 2017, namely the closure of the manhole by placing large
rocks in it and removing rocks, logs and branches supporting
the
lower embankment thereof; packing the furrow with rocks and logs; and
removing the 110mm pipe. As pointed out by the applicants,
floods
that were allegedly strong enough to remove the rocks from the furrow
would have completely scoured the entire area, including
the logs.
Yet in this case, the logs inexplicably remained in place. The
applicants have also placed sufficient evidence disputing
the alleged
flash floods. I find the respondent’s version in this regard
improbable, far-fetched, and falls to be rejected.
[28]
To summarise my
conclusion on this section,
I
have rejected the respondent’s claims that a flash flood caused
the transgression in August 2020. I have also rejected
the
respondent’s interpretation of the 2016 Order which suggests
that any manhole and pipes installed by him for diverting
water from
the Watervalstroom sources were not covered by the ambit of the 2016
Order. To that extent the respondent remains under
an obligation to
comply with the 2016 Order, and is ordered to forthwith comply with
it. However, the issue regarding the abstraction
of water from a
small fountain, which is alleged to be a different source from the
Watervalstroom, is partly linked to the interpretative
argument, and
falls to be referred for oral evidence. For this reason, I do not
find it appropriate at this stage to grant the
contempt relief sought
by the applicants in respect of the 2016 Order.
IV.
CONTRAVENTION
OF THE 2014 ORDER
[29]
The
litigation in 2014 related to a point lower downstream in the
Watervalstroom from where the water had historically been divided

between De Liefde, Kanonkop and Dennelaan (“
the
first division point”
).
The system entailed a temporary deflection wall made of stacked rocks
(referred to as “klipkeerwal”), which would
be
constructed in the bed of the Watervalstroom to divert water to the
De Liefde until the dams on De Liefde were full, after which
it would
be taken down to allow water to flow down to Kanonkop. The Order of
25 June 2014 was the result of litigation between
the parties
regarding the deflective wall, and it granted the applicants a right
to annually erect a deflection wall, which would
be taken down by the
respondent once the dams on De Liefde were full.
[30]
In
2019, the respondent addressed a letter to the applicants complaining
that a deflection that the applicants had erected in 2018
pursuant to
the 2014 Court Order had become packed with sand and debris, thereby
naturally making it more dense, and allowing less
water to flow down
to Kanonkop. However, before the applicants had responded the
respondent demolished the deflection wall and
erected a new one in
its place. According to the applicants, the wall rebuilt by the
respondent now allowed far more water to go
through to Kanonkop -
approximately a third of the water from the Watervalstroom. The
result is that only about two thirds of the
water flows towards De
Liefde, which is divided at the second division point between De
Liefde and Dennelaan. In effect, instead
of receiving the majority of
the water flowing down the Watervalstroom until De Liefde dams are
full, De Liefde is now sharing
that water, a substantial portion of
which is already been extracted via the furrow, equally with Kanonkop
and Dennelaan. According
to the applicants, this means the De Liefde
dams may never be full.
[31]
The
respondent admits to demolishing and reconstructing the deflection
wall on 5 June 2019. He states that he did so because the
wall was
not operating as it should, and was allowing less water to flow
through the wall than was envisaged by the parties. He
states that he
removed sandbags, debris and other plant material like roots from the
wall, and repacked the wall to conform with
the 2014 Court Order. The
respondent denies that he reconstructed the wall more loosely, and to
benefit Kanonkop. To this effect
the respondent has attached
photographs, which he says support his version. Furthermore, the
respondent alleges that on 25 July
2019 he found the second applicant
and his workers busy repairing the deflection wall after a flash
flood had occurred on the previous
night. According to him, the flash
flood caused a section of the deflection wall and the soil embankment
immediately upstream of
the deflection wall to be washed away. On
this basis, the respondent alleges that it was the second applicant
and his workers who
caused the alleged unjust distribution of water
to flow to the First Division point.
[32]
In the
replying affidavit the applicants have attached correspondence from
the respondent dated 31 July 2019 in which it was stated
that the
respondent had recently reconstructed the wall. This correspondence
casts serious doubt on the probabilities of respondent’s

version that it was the second applicant who constructed the
deflection wall during that period. It would not, in any event make

sense for the second applicant to construct a wall and then complain
about it in these proceedings, especially in circumstances
where the
result is that the wall now allows approximately one third of the
water flowing down the Watervalstroom to pass through
to Kanonkop,
instead of allowing the majority of it to first benefit De Liefde
dams. The respondent’s version is even more
improbable given
that the applicants had been constructing the wall since the granting
of the 2014 Order, with no such complaints.
It would make no sense
for them to now build a wall that was to their detriment.
[33]
Furthermore,
the second applicant has produced a copy of the diary of his
assistant Mr Albert Viljoen, which establishes that there
was an
occasion in June 2018 when he (second applicant) and Mr Viljoen
repaired a broken wall, and states that the respondent could
be
mistakenly referring to that occasion, and not to the period under
scrutiny, namely June to July 2019.
[34]
Although it is vehemently
disputed that the repacked wall was
packed
more loosely than previous walls erected by the applicants, it is not
seriously disputed that the result of the repacked
wall is that it
allows for only about two thirds of the water to flow towards De
Liefde, which is divided at the second division
point between De
Liefde and Dennelaan. The effect is that, instead of receiving the
majority of the water flowing down the Watervalstroom
until De Liefde
dams are full, De Liefde is now sharing that water, a substantial
portion of which is already been extracted via
the furrow, equally
with Kanonkop and Dennelaan. This is quite clearly contrary to the
express terms of the 2014 Order.
[35]
Even if the respondent’s
intentions were noble in reconstructing the deflection wall,
in
circumstances where the 2014 Court Order entitles only the applicants
to reconstruct the wall, one would have expected the respondent
to
reconstruct such a wall only by agreement with the applicants. The
fact that the respondent sent correspondence to the applicants
before
demolishing and reconstructing the deflection wall was not enough,
because he did not await the response from the applicants.
In
reconstructing the deflection wall, he was required to await the
input of the applicants. This is because the 2014 Order does
not
grant the respondent a right to construct the deflective wall. Given
the litigiousness of the issues between the parties, specifically

regarding water abstraction from the Watervalstroom and the
construction of the deflection wall, one would have expected the
respondent
to be alive to the fact that he is not entitled to
unilaterally take the steps that he did.
[36]
I therefore find that
there was transgression of the 2014 Order by the respondent.
V.
THE ALLEGED
ASSAULT
[37]
The
second applicant claims that on 20 June 2017 he attended the area
with some workers in order to conduct maintenance on the
Donkerkloofstroom. The respondent arrived while the second applicant
was standing on a rock, approached the second applicant and
pushed
him off the rock causing him to fall to the ground. The respondent
then sat or kneeled on the second applicant and assaulted
him with
blows to his face, causing his mouth to bleed and causing bruises to
his eye. The second applicant has attached a medical
report showing
the injuries he suffered from the incident, and which concludes that
he suffered “
soft
tissue injuries as a result of blunt injury due to hitting or
falling”
.
[38]
The
respondent disputes that he was the cause of the second applicant’s
injuries. His version is that on the day in question
the second
applicant had arrived with his workforce without requesting his
(respondent’s) permission to visit his property.
He gained the
impression that they intended to interfere with the flow of water by
altering the bed or banks or course of the water.
He admits that the
second applicant was standing on a rock, and that he (respondent)
approached the second applicant asking what
he was doing there, while
pointing his (respondent’s) finger at him. The second applicant
refused to answer, put out his
hand, and slapped the respondent's
finger. According to the respondent, the finger was stitched up due
to an injury that he had
incurred a few days prior. The respondent
felt provoked, and immediately reacted by slapping the second
applicant across the face
causing him to fall from the rock on the
ground. Thereafter, the respondent held the second applicant down
with this right hand
and slapped him once or twice across his face
while he was lying on the ground.
[39]
Even
based on the common cause facts regarding the incident of 20 June
2017, the respondent admits to assaulting the applicant,
although he
claims that he was provoked when the applicant slapped his
stitched-up finger. However, even if the respondent’s

justification were accepted, his conduct went beyond averting the
alleged provocation to his stitched-up finger. He did not just
swat
the second applicant’s hand away, but first slapped the second
applicant across the face. Thereafter, he admits to holding
the
second applicant down with one hand and slapping him a few times with
the other, all because he regarded the second applicant
as being
arrogant and provocative.
[40]
What
is worse is that on 24 August 2020 the respondent sent a WhatsApp
message to the second applicant stating as follows: “
Lyk
my dus (sic) alweer tyd vir
ʼn
les in
maniere want lyk my nie jou pa kon dit doen nie”
.
This was in response to a message from the second applicant to the
respondent in which it was alleged: “
Jy
steel al weer”
.
According to the applicants this was a reference to the previous
assault of 2017, and a threat to repeat the assault if the second

applicant attempted to do anything regarding the extraction of water
in relation to the respondent. I agree with the applicants
in this
regard.
[41]
As I
have indicated, the common cause facts establish that the respondent
did assault the second applicant in 2017. I am also of
the view that
the August 2020 promise to teach the second applicant manners “
al
weer”
is a reference to the 2017 assault, and is a threat to assault him
(the second applicant) again. In other words, that an assault
is
reasonably apprehended. I furthermore agree that the fact that the
2017 assault case was not prosecuted has left the second
applicant
with no alternative remedy but to obtain and interdict in this regard
for protection.
VI.
COSTS
[42]
There
is no reason why costs should not follow the result. I have found
that the respondent has acted in blatant disregard of existing
Court
Orders, in circumstances where the parties have previously litigated
on the issues involved in this case. In other words,
the applicants
have been forced to return to Court to vindicate rights already
obtained in terms of previous Court Orders. Needless
to say, the
respondent's conduct that is encountered in this case is also
contrary to the rule of law, and exhibits repeated instances
of
self-help and lawlessness, which deserve censure.
VII.
ORDER
[43]
In the result the
following order is granted:
1.
The
respondent
is
ordered to comply forthwith with the order
granted
by this Court on 13 December 2016 under case number 8067/2016 by
closing the furrow, pipes and manhole by which water is
being
diverted from the Watervalstroom or sources thereof to the farm
Kanonkop.
2.
The question of whether
the small fountain used by the respondent as from 2016 forms part of
the Watervalstroom, or is from a different
source, is referred for
oral evidence.
3.
The respondent is ordered
to comply forthwith with the order granted by this Court on 25 June
2014 under Case No. 9833/14 by demolishing
the stone deflection wall
erected by him at the water division point located in the
Watervalstroom known as the “first division
point”, and
allowing the applicants to erect a stone deflection wall in its
stead.
4.
The
respondent is called upon to give reasons why he should not be held
in contempt of the 2014 Court Order and visited with such
sanction as
the Court considers appropriate. It is ordered that such proceedings
be referred to oral evidence on the opposed motion
roll
.
5.
Regarding
paragraphs 2 and 4 above, in the event that the parties wish to call
witnesses, witness statements signed by such perspective
witnesses
shall be delivered to the other party at least 14 days before the
hearing.
6.
The respondent is
interdicted from:
a.
assaulting and/or
threatening to assault the fourth applicant;
b.
in any manner interfering
with the applicants’ right to inspect the Watervalstroom and
Donkerkloofstroom water sources and
taking steps to maintain same;
c.
coming within 100m of the
fourth applicant or any of his employees at any time.
7.
The respondent is ordered
to pay costs of these proceedings, on a scale between attorney and
client.
N.
MANGCU-LOCKWOOD
Judge of the High Court
Appearances
For
Applicant

Adv D C Joubert SC
For
Respondent

Adv A Newton
[1]
Stern
& Ruskin NO v Appleson
1951
(3) SA 800 (W).
[2]
National Director of Public Prosecutors v Zuma
[2009] ZASCA 1
;
2009 (2) SA 277
(SCA) paras [26] – [27].
[3]
Plascon-Evans Paints (TVL) Ltd v Van Riebeck Paints (Pty) Ltd
1984 (3) SA 623 (A).
[4]
Plascon-Evans
Paints Ltd v Van Riebeeck Paints (Pty) Ltd
1984 (3) SA 623 (A)
634-5;
Fakie
NO v CCII Systems (Pty) Ltd
2006 (4) SA 326 (SCA)
para 55;
Thint
(Pty) Ltd v National Director of Public Prosecutions;
Zuma v
National Director of Public Prosecutions
[2008]
ZACC 13
;
2008
(2) SACR 421
(CC)
para 8-10;
National
Director of Public Prosecutors v Zuma
[2009] ZASCA 1
;
2009
(2) SA 277
(SCA) paras [26] – [27].
[5]
Harms
Civil
Procedure in the Supreme Court
,
Butterworths
B6.45.
[6]
Petersen
v Cuthbert & Co Ltd
1945
AD 420
428.
[7]
Truth
Verification Testing Centre CC v PSE Truth Detection Centre CC
1998
(2) SA 689
(W)
698;
Rosen
v Ekon
[2000]
3 All SA 23
(W)
39;
Ripoll-Dausa
v Middleton NO
[2005] ZAWCHC 6
;
[2005]
2 All SA 83
(C),
2005 (3) SA 141
(C).
[8]
Peterson
v Cuthbert & Co Ltd supra
429;
President
of the Republic of South Africa v South African Rugby Football
Union
2000
(1) SA 1
(CC)
pars 234-239.
[9]
Harms
Civil
Procedure in the Supreme Court
,
Butterworths
B6.45.