About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Western Cape High Court, Cape Town
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2017
>>
[2017] ZAWCHC 50
|
|
Earthlife Africa Johannesburg and Another v Minister of Energy and Others (19529/2015) [2017] ZAWCHC 50; [2017] 3 All SA 187 (WCC); 2017 (5) SA 227 (WCC) (26 April 2017)
REPORTABLE
THE
REPUBLIC OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case
No: 19529/2015
Before
the Hon. Mr Justice Bozalek and the Hon. Ms Justice Baartman
Hearing:
13 December 2016; 22 – 24 February 2017
Judgment
Delivered: 26 April 2017
In
the review application between:
EARTHLIFE
AFRICA – JOHANNESBURG
1
st
Applicant
SOUTHERN
AFRICAN FAITH COMMUNITIES’
ENVIRONMENT
INSTITUTE
2
nd
Applicant
and
THE
MINISTER OF ENERGY
1
st
Respondent
THE
PRESIDENT OF THE REPUBLIC OF SOUTH AFRICA
2
nd
Respondent
THE
NATIONAL ENERGY REGULATOR OF SOUTH AFRICA
3
rd
Respondent
SPEAKER
OF THE NATIONAL
ASSEMBLY
4
th
Respondent
CHAIRPERSON
OF THE NATIONAL COUNCIL OF PROVINCES
5
th
Respondent
ESKOM
HOLDINGS (SOC) LIMITED
6
th
Respondent
JUDGMENT
BOZALEK
J (BAARTMAN J concurring)
[1]
This
application concerns challenges to various steps taken by the State
between 2013 and 2016 in furtherance of its nuclear power
procurement
programme. The steps challenged are two separate determinations made
by the Minister of Energy in 2013 and 2016, respectively,
in terms of
sec 34 of the Electricity Regulation Act, 4 of 2006 (‘ERA’),
whilst the second main focus of the challenge
is the
constitutionality of the tabling by the Minister before Parliament of
three intergovernmental agreements (IGA’s) during
2015.
THE
PARTIES
[2]
First
applicant is Earthlife Africa – Johannesburg, a
non-governmental non-profit voluntary association which mobilises
civil
society around environmental issues. The second applicant is
the Southern African Faith Communities’ Environmental
Institute,
a registered public benefit and non-profit organisation
which also concerns itself with environmental and socio economic
injustices.
[3]
First
respondent is the Minister of Energy (‘the Minister’) who
issued the two sec 34 determinations in question and
tabled the three
IGA’s relating to nuclear cooperation with other countries. The
President of the Republic of South Africa
(‘the President’)
is cited as second respondent by reason of his decision in 2014
authorising the Minister’s
signature of an IGA concluded in
2014 with the Russian Federation. Third respondent is the National
Energy Regulator of South Africa
(‘NERSA’), a statutory
body set up in terms of the National Energy Regulator Act, 40 of 2004
(‘NERA’),
which body concurred in the sec 34
determinations made by the Minister. The Speaker of the National
Assembly and the Chairperson
of the National Council of Provinces are
the fourth and fifth respondents, cited because of their interest in
the question whether
the IGA’s were properly tabled before
their respective houses. During the course of proceedings, Eskom
Holdings (SOC) Limited
(‘Eskom’) was joined as sixth
respondent but it, as well as the fourth and fifth respondents, abide
by the Court’s
decision. All the relief sought is opposed by
the Minister and the President to whom I shall refer as ‘the
respondents’.
BACKGROUND
[4]
In
late 2013, the Minister (with NERSA’s concurrence), acting in
terms of sec 34 of ERA determined that South Africa required
9.6GW
(‘gigawatts’) of nuclear power and that this should be
procured by the Department of Energy. The Minister purported
to make
the determination on or about 17 December 2013. It was, however, only
gazetted on 21 December 2015 and delivered to the
applicants as part
of the record in this matter on or about 23 December 2015. The
gazetting and production of this sec 34 determination
was at least
partly in response to the applicants’ initial case in which,
inter alia, a declarator was sought that, prior
to the commencement
of any procurement process for nuclear new generation capacity, the
Minister and NERSA were both required in
accordance with
‘
procedurally
fair public participation processes’
to
have determined that new generation capacity was required and must be
generated from nuclear power in terms of sec 34(1)(a) and
(b) of ERA.
[5]
The
applicants commenced their review application in October 2015. Prior
thereto, on or about 10 June 2015, the Minister had tabled
the three
IGA’s before Parliament which are the subject of the present
constitutional challenge. In chronological order these
were
agreements between the Government of the Republic of South Africa and
the United States of America, concluded in August 1995,
the
Government of the Republic of Korea, concluded in October 2010 and
the Government of the Russian Federation, concluded in September
2014, all in regard to cooperation in the field of nuclear energy.
[6]
On
or about 8 December 2016, during these proceedings, the Minister
issued a second sec 34 determination along similar lines to
the
previous sec 34 determination, but now identifying Eskom as the
procurer of the nuclear power plants. The determination was
made
public at the commencement of the initial hearing in this matter on
13 December 2016, occasioning its postponement for several
months,
and was gazetted on 14 December 2016.
EVOLUTION
OF THE LITIGATION
[7]
The
applicants’ case has evolved through three stages. The relief
initially sought was a review and setting aside of the Minister’s
decision to sign the Russian IGA, the President’s decision
authorising the Minister’s signature, and the Minister’s
decision to table the Russian IGA before Parliament in terms of sec
231(3) of the Constitution. Certain declaratory relief was
also
sought in relation to how the nuclear procurement process should
unfold in relation to the issuing of determinations under
sec 34(1)
of ERA and sec 217 of the Constitution which deals with the
requirements for a fair procurement system for organs of
state.
[8]
After
the respondents furnished the first sec 34 determination as part of
the record, the applicants filed an amended notice of
motion seeking
the review and setting aside of that determination and any ‘
Request
for Proposals’
issued by the Department of Energy pursuant thereto.
[9]
Finally,
after postponement of the proceedings in December 2016, the Minister
filed a supplementary affidavit explaining the circumstances
surrounding, and the rationale for, the second sec 34 determination.
The applicants were afforded an opportunity to file answering
affidavits to which they attached a draft order indicating that
further relief being sought was the review and setting aside of
the
Minister’s sec 34(1) determination gazetted on 14 December
2016, and the setting aside of any Requests for Proposals
or Requests
for Information issued pursuant to either determination.
[10]
The
hearing resumed on 22 February 2017 when the matter was fully argued.
OUTLINE
OF THE PARTIES’ CASES
[11]
In
broad terms the applicants’ challenge to the three IGA’s
is largely procedural in nature and based on the different
procedures
set out in sec 231(2) and 231(3) of the Constitution to render such
agreements binding over the Republic. Section 231(2)
provides that an
IGA binds the Republic only after it has been approved by resolution
in both the National Assembly (‘the
NA’) and the National
Council of Provinces (‘the NCOP’) ‘
unless
it is an agreement referred to in subsection (3)’
.
The latter subsection provides that IGA’s of a ‘
technical,
administrative or executive nature’
binds the Republic without the approval of the NA or the NCOP ‘
but
must be tabled in the Assembly and the Council within a reasonable
time’
.
The applicants aver that inasmuch as the US IGA was entered into more
than two decades before it was tabled in terms of sec 231(3),
and
nearly five years previously in the case of the Korean IGA, the delay
in so tabling them rendered them non-compliant with sec
231(3) and
therefore non-binding. The Russian IGA was also tabled in terms of
sec 231(3) but in its case the applicants aver that
it was not an
international agreement as envisaged in sec 231(3) and thus should
have been tabled before the two houses in terms
of sec 231(2) with
the result that it would only become binding after it had been
approved by resolution of those houses.
[12]
In
regard to the challenge to all three IGA’s the respondents
raise various preliminary points, namely, that there has been
a
material non-joinder inasmuch as none of the three countries have
been joined as parties to the proceedings. In any event, the
respondents contend that all three agreements, being international
agreements, are not justiciable by a domestic court. As regards
the
Russian IGA the respondents contend in the alternative that upon a
proper interpretation and construction thereof it is ‘
an
international framework agreement for cooperation between sovereign
states’
(and not a procurement contract) to cooperate on an executive level
in the field of nuclear energy and nuclear industry; furthermore,
the
respondents contend, the decision of the Minister to table the
Russian IGA in terms of sec 231(3) of the Constitution was beyond
reproach inasmuch as it falls within the general category of a
‘
technical,
administrative and executive agreement, not requiring ratification or
accession’
.
It is also contended by the respondents that, in any event, even if
the Russian IGA was tabled in Parliament in terms of the incorrect
procedure, the applicants have no standing to claim any relief in
relation thereto, this being a matter for Parliament to take
up with
the Minister.
[13]
In
regard to the US and Korean IGA’s the respondents, for the
reasons given above, again assert that the applicants have no
standing to claim any relief. They assert further that there was no
unreasonable delay in tabling either IGA and that what is reasonable
in any particular instance must depend on the facts and circumstances
pertaining to each IGA. They contend further that, even if
there was
an unreasonable delay in the tablings, it is only the delay itself
that is unconstitutional and this does not affect
the validity or
effectiveness of the tabling themselves nor render the two treaties
without any binding effect.
[14]
As
regards to the sec 34 determinations, in broad outline, the
applicants’ case is that both the Minister’s decision
as
contained in the determinations and NERSA’s concurrence therein
constituted administrative action but breached the requirements
for
such action to be lawful, reasonable and procedurally fair. Amongst
the grounds that they rely on in this regard are that neither
the
Minister’s decision nor that of NERSA’s was preceded by
any public participation or consultation of any ground.
Secondly, as
regards the first sec 34 determination the applicants contend it was
unlawful by reason of the two year delay in gazetting
it; thirdly,
they contend, both determinations were irrational, unreasonable and
taken without regard to relevant considerations
or with regard to
irrelevant considerations.
[15]
The
applicants rely on certain additional grounds in relation to the 2016
determination, more specifically that NERSA’s decision
to
concur therein was unlawful in that its key reason was that it
believed that it would be ‘
mala
fide for it not to concur in the Minister’s proposed
determination’
and
was thus predicated on a material error of law or fact. It is also
contended that NERSA failed to apply its mind to further
relevant
considerations, relating to the Minister’s proposed
determination, which arose after the 2015 determination.
[16]
A
further specific ground upon which the 2013 and 2016 determinations
is challenged is the absence therein of any specific system
for the
procurement of nuclear new build capacity which is said to be in
violation of sec 34 of ERA, read together with sec 217
of the
Constitution.
[17]
A
further procedural ground of review is based on the applicants’
contention that since the 2016 determination failed to withdraw
or
amend the 2013 sec 34 determination it resulted in the anomalous
situation of two gazetted sec 34 determinations which are mutually
inconsistent. As such the determinations violate the principle of
legality and fall to be reviewed and set aside. The applicants
contend, furthermore, that even if the Minister’s decisions as
expressed in the sec 34 determination are not administrative
but
executive action they are nonetheless susceptible to review by virtue
of the principle of legality and, even on this standard,
fall to be
set aside on the basis of irrationality.
[18]
For
their part the respondents contend that neither the decisions of the
Minister nor those of NERSA in concurring with the sec
34
determinations constitute administrative action. Instead, they
contend the determinations amount to ‘
encased
policy directives’
and that a ministerial determination under sec 34 of ERA amounts to
‘
executive
policy’
.
They argue that no actual procurement decisions, nor a decision to
grant a generation licence, were taken and the sec 34 determinations
were in substance nothing more than policy decisions by the national
executive binding only upon NERSA. The respondents dispute,
furthermore, the specific grounds of the applicants’ challenge
to the sec 34 determinations and contend that there is no
requirement
that a determination must specify the procurement system for the
nuclear new generation capacity. They contend further
that neither
the Minister’s decision nor NERSA’s decision was required
to be made in accordance with a procedurally
fair and public
participation process. The respondents concede that the
determinations are subject to review for rationality but
contend that
both determinations meet that standard.
[19]
The
respondents dispute, on various grounds, the specific bases upon
which the applicants contend that NERSA’s concurrence
in the
2016 determination was unlawful, unreasonable or irrational. As
regards the general ground advanced by the applicants that
the 2013
and 2016 determinations are mutually inconsistent and stand to be
struck down for this reason, the respondents’
case is that,
properly interpreted, the first determination was impliedly repealed
by the second determination but that, in any
event, even if both
determinations stand separately from each other they are not mutually
inconsistent.
THE
ISSUES
[20]
The
following main issues fall to be determined:
1.
Did
the Minister and NERSA breach statutory and constitutional prescripts
in making the 2013 and 2016 sec 34 determinations?
2.
Did
the President and the Minister breach the Constitution in deciding to
sign the 2014 Russian IGA in relation to nuclear procurement
and then
in tabling it under sec 231(3) of the Constitution rather than sec
231(2)?
3.
Did
the Minister breach the Constitution in tabling the US IGA and South
Korean IGA in relation to nuclear cooperation two decades
and nearly
five years, respectively after they had been signed?
CHRONOLOGY
OF EVENTS
[21]
Before
dealing with the issues it is useful to set out a chronology of
events as they relate to the sec 34 determinations and the
various
IGA’s concluded by the respondents relating to nuclear issues.
1.
In
March 2011 the Minister gazetted the Integrated Resource Plan for
Electricity 2010-2030 (IRP2010) which the Department of Energy
itself
stated should be revised every two years, but which, as at the date
of hearing, had yet to be revised.
2.
On
11 November 2013 the Minister signed a determination under sec 34(1)
of ERA in relation to the requirement for and procurement
of 9 600MW
of electricity from nuclear energy which secured NERSA’s
concurrence on 17 December 2013.
3.
On
20 September 2014 the President signed a minute approving the Russian
IGA in relation to a strategic nuclear partnership and
authorised the
Minister to sign the agreement.
4.
The
following day, the Minister signed the agreement on behalf of the
Government.
5.
A
day later, on 22 September 2014, the Department of Energy and
Russia’s atomic energy agency (‘Rosatom’), released
identical press statements confirming their joint understanding of
what the two governments had agreed, and advising that on 22
September 2014 the Russian Federation and the Republic of South
Africa had signed an Intergovernmental Agreement on Strategic
Partnership and Cooperation in Nuclear Energy and Industry.
[1]
6.
The
press releases recorded inter alia that:
‘
The
Agreement lays the foundation for the large-scale nuclear power
plants (NPP) procurement and development programme of South
Africa
based on the construction in RSA of new nuclear power plants with
Russian VVER reactors with total installed capacity of
up to 9.6 GW
(up to 8 NPP units). These will be the first NPPs based on the
Russian technology to be built on the African continent.
The signed
Agreement, besides the actual joint construction of NPPs, provides
for comprehensive collaboration in other areas of
the nuclear power
industry, including construction of a Russian-technology based
multipurpose research reactor, assistance in the
development of
South-African nuclear infrastructure, education of South African
nuclear specialists in Russian universities and
other areas.’
7.
In
a subsequent press release, however, the Department of Energy
described the Russian IGA as initiating ‘
the
preparatory phase for the procurement for the new nuclear build
programme’
and stated that ‘
(s)imilar
agreements are foreseen with other vendor countries that have
expressed an interest in supporting South Africa in this
massive
programme’
.
[2]
8.
In
further press releases in late 2014 and early 2015 the Department of
Energy advised that it had conducted vendor parades in relation
to
nuclear procurement, first with Russia and then with China, France,
South Korea and the United States.
9.
After
entering into the Russian IGA, the Government also entered into IGA’s
with China and France in late 2014.
10.
On
10 June 2015 the Minister authorised the submission for tabling in
Parliament of various IGA’s signed with various nuclear
vendor
countries in accordance with sec 231(3) of the Constitution.
11.
The
following IGA’s were tabled:
11.1
Agreement
for Cooperation between the Government of the Republic of South
Africa and the United States of America concerning Peaceful
Uses of
Nuclear Energy (‘the US IGA’), signed on 25 August 1995;
11.2
Agreement
between the Government of the Republic of Korea and the Government of
the Republic of South Africa regarding Cooperation
in the
Peaceful Uses of Nuclear Energy (‘the South Korean IGA’),
signed on 8 October 2010;
11.3
Agreement
between the Government of the Republic of South Africa and the
Government of the Russian Federation on Strategic Partnership
and
Cooperation in the fields of Nuclear Power and Industry (‘the
Russian IGA’), signed on 21 September 2014;
11.4
Agreement
between the Government of the Republic of South Africa and the
Government of the French Republic on Cooperation in the
Development
of Peaceful Uses of Nuclear Energy, dated 14 October 2014;
11.5
Agreement
between the Government of the Republic of South Africa and the
Government of the People’s Republic of China on Cooperation
in
the field of Civil Nuclear Energy Projects, signed on 7 November
2014.
12.
On
21 December 2015 the Minister’s 2013 sec 34 determination was
made public by publication in the government gazette.
13.
On
8 December 2016 the Minister issued a further determination under sec
34(1) of ERA in relation to the requirement for and procurement
of
9 600MW of electricity from nuclear energy with NERSA’s
concurrence, and published it in the government gazette on
14
December 2016.
THE
SECTION 34 DETERMINATIONS
[22]
Before
setting out the terms of the 2013 sec 34 determination regard must be
had to the relevant empowering legislation. The preamble
to ERA
records that its purposes were inter alia to establish a national
regulation framework for the electricity supply industry
and to make
NERSA the custodian and enforcer of the national electricity
regulatory framework. Section 2 provides that amongst
the objects of
ERA are to:
‘
(a)
achieve the efficient, effective,
sustainable and orderly development and operation of electricity
supply infrastructure in South Africa;
(b)
ensure that the interests and needs of present and future electricity
customers and
end users are safeguarded and met, having regard to the
governance, efficiency, effectiveness and long-term sustainability of
the
electricity supply industry within the broader context of
economic energy regulation in the Republic;
…
(g)
facilitate a fair balance between the interests of customers and end
users, licensees,
investors in the electric supply industry and the
public.’
[23]
Section
34 of ERA deals with the subject of new generation capacity and
provides in part as follows:
‘
(1)
The Minister may, in consultation with
the Regulator –
(a)
determine
that new generation capacity is needed to ensure the continued
uninterrupted supply of electricity;
(b)
determine
the types of energy sources from which electricity must be generated,
and the percentages of electricity that must be
generated from such
sources;
(c)
determine
that electricity thus produced may only be sold to the persons or in
the manner set out in such notice;
(d)
determine
that electricity thus produced must be purchased by the persons set
out in such notice;
(e)
require
that new generation capacity must:
(i)
be
established through a tendering procedure which is fair, equitable,
transparent, competitive and cost-effective;
(ii)
provide for private sector participation.
2.
…
3.
The
Regulator, in issuing a generation licence –
a)
is
bound by any determination made by the Minister in terms of
subsection (1);
b)
may
facilitate the conclusion of an agreement to buy and sell power
between a generator and a purchaser of that electricity.’
[24]
Section
34(1) therefore operates as the legislative framework by which any
decision that new electricity generation capacity is
required and any
decision taken by the Minister in that regard, has no force and
effect unless and until NERSA agrees with the
Minister’s
decision.
[25]
Commenting
on the role of administrative law in the field of electricity
regulation Klees
[3]
states as
follows:
‘
The
significance of administrative law for environmental law is beyond
dispute. Glazewski describes environmental law as “administrative
law in action, as environmental conflicts frequently turn on the
exercise of administrative decision-making powers”. Something
similar could be said of NERSA’s decision-making powers under
the ERA.’
[26]
The
Minister’s 2013 determination read, insofar as it is relevant,
as follows:
‘
The
Minister of Energy … in consultation with … (“NERSA”),
acting under section 34(1) of the Electricity
Regulation Act 4 of
2006 … has determined as follows:
1.
that
energy generation capacity needs to be procured to contribute towards
energy security and to facilitate achievement of
the greenhouse
gas emission targets for the Republic of South Africa, accordingly, 9
600 megawatts (MW) should be procured to be
generated from nuclear
energy (“nuclear programme”), which is in accordance with
the capacity allocated under the Integrated
Resource Plan for
Electricity 2010-2030 …;
2.
electricity
produced from the new generation capacity (“the electricity”),
shall be procured through tendering procedures
which are fair,
equitable, transparent, competitive and cost-effective;
3.
the
nuclear programme shall target connection to the Grid as outlined in
the IRP2010-2030 (or as updated), taking into account all
relevant
factors including the time required for procurement;
4.
the
electricity may only be sold to the entity designated as the buyer in
paragraph 7 below, and only in accordance with the power
purchase
agreements and other project agreements to be concluded in the course
of the procurement programmes;
5.
the
procurement agency in respect of the nuclear programme will be the
Department of Energy;
6.
the
role of the procurement agency will be to conduct the procurement
process, including preparing any requests for qualification,
request
for proposals and/or all related and associated documentation,
negotiating the power purchase agreements, facilitating
the
conclusion of the other project agreements, and facilitating the
satisfaction of any conditions precedent to financial closure
which
are within its control;
7.
the
electricity must be purchased by Eskom Holdings SOC Limited or by any
successor entity to be designated by the Minister of Energy,
as buyer
(off-taker); and
8.
the
electricity must be purchased from the special purpose vehicle(s) set
up for the purpose of developing the nuclear programme.’
[27]
On
11 November 2013 the Minister’s predecessor wrote to the
Chairperson of NERSA requesting its concurrence in the proposed
determination as set out above. Some five weeks later, on 20 December
2013, the Chairperson advised the Minister’s predecessor
that
NERSA had resolved to concur in the proposed determination. NERSA’s
decision was taken at a meeting of its board held
on 26 November
2013, two weeks after receiving the Minister’s proposed
determination. Minutes of those meetings record its
reasons for
concurring with the Minister’s proposed determination.
WERE
THE SECTION 34 DETERMINATIONS ADMINISTRATIVE ACTION AND, IF SO, WERE
THEY LAWFUL, REASONABLE AND PROCEDURALLY FAIR?
[28]
The
right to just administrative action is enshrined in sec 33 of the
Constitution and provides that everyone has the right to
‘
administrative
action that is lawful, reasonable and procedurally fair’
and
that national legislation must be enacted to give effect to the
right. Administrative action is then defined in section 1 of
the
Promotion of Administrative Justice Act, 3 of 2000 (‘PAJA’)
in part as follows:
‘…
any
decision taken, or any failure to take a decision, by -
(a) an
organ of state, when -
(i) exercising
a power in terms of the Constitution or a provincial constitution; or
(ii) exercising
a public power or performing a public function in terms of any
legislation; or
…
which
adversely affects the rights of any person and which has a direct,
external legal effect, but does not include -
(aa) the
executive powers or functions of the National Executive, including
the powers or functions referred to
in …’
[29]
Amongst
the excluded powers or functions is sec 85(2)(b) of the Constitution
which provides that the President exercises the executive
authority,
together with other members of the Cabinet by,
‘
(b)
developing and implementing national policy’.
[30]
On
behalf of the applicants it was contended that it was unnecessary to
determine whether the 2013 sec 34 determination amounted
to executive
action or administrative action since even if it was the former it
was subject to rationality review; therefore, the
argument continued,
the real question was whether the determination amounted to nothing
more than policy (or as it was put on behalf
of the respondents - ‘
an
encased policy directive’
).
In
SARFU
[4]
the Constitutional Court declared that the distinction between
executive and administrative action boils down to a distinction
between the implementation of legislation, which is administrative
action, and the formulation of policy, which is not. The Court
stated
that where the line is drawn will depend primarily upon the nature of
the power and the factors relevant to this consideration
which are in
turn, the source of the power, the nature of the power, its subject
matter, whether it involves the exercise of a
public duty and whether
it is related to policy matters or the implementation of legislation.
[31]
Woolman
[5]
cautions
against the over extension of executive policy decisions so as to
exclude a large range of actions from the application
of the right to
just administrative action. The authors contend that it is important
to distinguish between policy in the narrow
sense and policy in the
broad sense, of which only the latter should be excluded from the
ambit of administrative action. In
Ed-U-College
[6]
O’Regan J stated on behalf of the Court:
‘
Policy
may be formulated by the Executive outside of a legislative
framework. For example, the Executive may determine a policy
on road
and rail transportation or on tertiary education. The formulation of
such policy involves a political decision and will
generally not
constitute administrative action. However, policy may also be
formulated in a narrower sense where a member of the
Executive is
implementing legislation. The formulation of policy in the exercise
of such powers may often constitute administrative
action.’
[32]
In
the present matter the source of the power exercised by the Minister
was sec 34(1) of ERA and the nature of the power was one
which had
far reaching consequences for the public as a whole and for specific
role-players in the electricity generation field.
The determination
also had external binding legal effect in that, at the very least, it
bound or authorised NERSA to grant generation
licences for nuclear
energy subject to an overall limit of 9 600MW. Specific affected
parties in this case would be not only those
engaged in the field of
nuclear energy generation but other electricity generation providers
such as oil, gas or renewable energy
inasmuch as their potential to
contribute to the need for extra capacity would be removed. These
factors all point towards the
sec 34 determination constituting
administrative action.
[33]
Given
the critical role that NERSA has in the making of a ministerial
determination in terms of sec 34 of ERA, regard must also
be had to
its powers and the manner in which it is required to exercise these.
NERSA itself was established in terms of NERA which
was promulgated
to establish a single regulator to regulate the electricity,
piped-gas and petroleum pipeline industries.
[34]
Section
9 of NERA sets out the duties of members of the energy regulator who
must inter alia:
‘
(a)
act in a justifiable and transparent manner whenever the exercise of
their discretion is
required;
…
(c)
act independently of any undue influence or instruction;
…
(f)
act in the public interest
.’
[35]
Section
10 of NERA, which plays an important role in this matter, sets out
the requirements for the validity of NERSA’s decisions
and
provides as follows:
‘
1.
Every decision of the Energy Regulator must be in writing and be –
(a)
consistent
with the Constitution and all applicable laws;
(b)
in
the public interest;
(c)
…
(d)
taken
within a procedurally fair process in which affected persons have the
opportunity to submit their views and present relevant
facts and
evidence to the Energy Regulator;
(e)
based
on reasons, facts and evidence that must be summarised and recorded;
and
(f)
explained
clearly as to its factual and legal basis and the reasons therefor.
2.
Any decision of the Energy Regulator and the reasons therefor must be
available to the public
except information that is protected in terms
of the Promotion of Access to Information Act, 2000 (Act No. 2 of
2000).
3.
Any person may institute proceedings in the High Court for the
judicial review of an administrative
action by the Energy Regulator
in accordance with the Promotion of Administrative Justice Act, 2000
(Act No. 3 of 2000).
4.
a) Any person affected by a decision of the Energy
Regulator sitting as
a tribunal may appeal to the High Court against
such decision.
…’
[36]
There
is nothing to suggest that the decision taken by NERSA to concur in
the Minister’s proposed 2013 sec 34 determination
was one which
fell outside the ambit of sec 10 of NERA. An independent requirement
for a valid decision of this nature was thus
that it be taken ‘
within
a procedurally fair process in which affected persons have the
opportunity to submit their views and present relevant facts
and
evidence to the Energy Regulator’
.
Section 10(3) specifically provides for judicial review of
administrative action by NERSA.
[37]
Against
this background, when regard is had to the definition of
administrative action in PAJA it is clear that all its elements
are
satisfied at least as far as NERSA’s role in the sec 34
determination. NERSA is undoubtedly an organ of state which,
in
taking the decision to concur with the Minister’s proposed
determination, was ‘
exercising
a public power or performing a public function’
in terms of legislation, namely, sec 34 of ERA and sec 10 of NERA.
That decision had a direct, external legal effect and, at the
least,
adversely affected the rights of energy producers outside the stable
of nuclear power producers. None of the exemptions
or qualifications
referred to in sec 1(b)(aa) – (ii) of PAJA are met.
[38]
In
regard to the requirement that the action must ‘
adversely
affect the rights of any person’
there is authority that this threshold must not be interpreted
restrictively. In
Grey’s
Marine
[7]
the Supreme Court of Appeal dealt with this requirement, Nugent JA
stating as follows:
‘
While
PAJA’s definition purports to restrict administrative action to
decisions that, as a fact, “adversely affect the
rights of any
person”, I do not think that a literal meaning could have been
intended. For administrative action to be characterised
by its effect
in particular cases (either beneficial or adverse) seems to me to be
paradoxical and also finds no support from the
construction that has
until now been placed on s 33 of the Constitution. Moreover, that
literal construction would be inconsonant
with s 3(1)
[of
PAJA]
,
which envisages that administrative action might or might not affect
rights adversely. The qualification, particularly when seen
in
conjunction with the requirement that it must have a “direct
and external legal effect”, was probably intended rather
to
convey that administrative action is action that has the capacity to
affect legal rights, the two qualifications in tandem serving
to
emphasise that administrative action impacts directly and immediately
on individuals.’
[8]
[39]
In
Steenkamp
[9]
Moseneke DCJ held that a decision to award or refuse a tender
constitutes administrative action because the decision ‘
materially
and directly affects the legal interests or rights of tenderers
concerned’
giving
further weight to a non-restrictive interpretation of this
requirement.
[40]
The
power exercised by the Minister in terms of sec 34(1) of ERA is
unusual in that any decision on his part is inchoate until such
time
as NERSA concurs therein and the sec 34 determination is thereby
made. It is, however, the sec 34 determination which is challenged
as
unfair, unlawful and unreasonable administrative action. Having
concluded that NERSA’s role in concurring in the proposed
determination amounts to administrative action for the reasons
furnished, it is conceptually difficult to view the sec 34
determination,
as a whole, as anything other than administrative
action. Moreover, if NERSA’s action, as a vital link in the
chain which
makes up the sec 34 determination, does not meet the test
for fair administrative action, little point is served in
scrutinizing
any decision by the Minister, prior to the sec 34
determination being made, for fair administrative action. One link,
namely NERSA’s
action having proved to be fatally flawed from
an administrative law point of view, the chain, i.e. the sec 34
determination, is
broken.
[41]
On
behalf of the respondents it was contended that the requirement that
‘
every
decision’
of NERSA had to comply with the requirements of sec 10 of NERA could
not be taken literally. Although internal decisions of NERSA
which
fall outside the requirements of sec 10 can readily be imagined, its
decision to concur in the Minister’s proposed
determination can
hardly be categorised as a rote, everyday decision. Indeed the
decision to formally expand the nuclear procurement
programme to 9
600MW must surely rank as one of the most important decisions taken
by NERSA in the recent past.
[42]
Section
3 of PAJA echoes sec 10 of NERA to the effect that administrative
action which materially and adversely affects the rights
or
legitimate expectations of any person must be procedurally fair. It
stipulates that a fair administrative procedure will depend
on the
circumstances of each case. Also pertinent is sec 4 of PAJA which
deals with administrative action affecting the public
and provides
that the administrator:
‘
(I)n
order to give effect to the right to procedurally fair administrative
action, must decide whether -
(a) to
hold a public inquiry in terms of subsection (2);
(b) to
follow a notice and comment procedure in terms of subsection (3);
(c) to
follow the procedures in both subsections (2) and (3);
(d) …
or;
(e) to
follow another appropriate procedure which gives effect to section
3.’
[43]
NERSA
did not oppose the application and therefore offered no explanation
as to what procedure, if any, it followed to give effect
to the right
to procedurally fair administrative action. The minutes of the
meeting of NERSA at which the decision was taken reveal
no indication
of any prior process whereby ‘
affected
persons’
or the public had the opportunity to submit their views to NERSA. Nor
is there any indication in the record of any such procedure
having
been followed. The short period of time between the Minister’s
request to NERSA to consider the proposed determination
and its final
decision, a matter of weeks, renders it most unlikely that a fair
procedure could have been carried out even if NERSA
had been minded
to follow one.
[44]
There
is no serious dispute that the decision to procure 9.6GW of nuclear
new generation capacity will have far reaching consequences
for the
South African public and will entail very substantial spending on a
particular type and quantity of new infrastructure.
The applicants
estimated that the costs, which will ultimately be met by the public
through taxes and increased electricity charges,
could be
approximately R1 000 000 000 000 (one trillion Rand) and this
estimate was not disputed by the respondents. As the
applicants point
out, the allocation of such significant resources to the project will
inevitably effect spending on other social
programmes in the field of
education, social assistance of health services and housing. They
also point out that the decision embodied
in the sec 34 determination
has potentially far reaching implications for the environment.
[45]
In
my view, in light of these considerations, a rational and a fair
decision-making process would have made provision for public
input so
as to allow both interested and potentially affected parties to
submit their views and present relevant facts and evidence
to NERSA
before it took a decision on whether or not to concur in the
Minister’s proposed determination.
[46]
For
these reasons, I consider that NERSA’s decision to concur in
the Minister’s proposed 2013 determination without
even the
most limited public participation process renders its decision
procedurally unfair and in breach of the provisions of
sec 10(1)(d)
of NERA read together with sec 4 of PAJA.
[47]
Even
if I am wrong in concluding that NERSA’s decision to concur (or
the combined decision of the Minister and NERSA) amounted
to
administrative action, the decision/s still have to satisfy the test
for rational decision-making, as part of the principle
of legality.
Applying this to the applicants’ challenge on the basis of an
unfair procedural process the question is whether
the decision by
either the Minister or NERSA (or the combined decision of the
Minister and NERSA) fell short of constitutional
legality for want of
consultation with interested parties.
[48]
Our
courts have recognised that there are circumstances in which rational
decision-making calls for interested persons to be heard.
In
Albutt
v Centre for the Study of Violence and Reconciliation, and Others
[10]
the Court had to decide inter alia whether the President was
required, before exercising a power to pardon offenders whose
offences
were committed with a political motive, to afford a hearing
to victims of the offences. It was held that the decision to
undertake
the special dispensation process under which pardons were
granted without affording the victims an opportunity to be heard had
to be rationally related to the achievement of the objectives of the
process.
[11]
[49]
In
Democratic
Alliance v President of the Republic of South Africa and Others
[12]
Yacoob
ADCJ stated:
‘
It
follows that both the process by which the decision is made and the
decision itself must be rational. Albutt is authority for
the same
proposition.’
He
went on to state:
‘
The
conclusion that the process must also be rational in that it must be
rationally related to the achievement of the purpose for
which the
power is conferred, is inescapable and an inevitable consequence of
the understanding that rationality review is an evaluation
of the
relationship between means and ends. The means for achieving the
purpose for which the power was conferred must include
everything
that is done to achieve the purpose. Not only the decision employed
to achieve the purpose, but also everything done
in the process of
taking that decision, constitutes means towards the attainment of the
purpose for which the power was conferred.’
[13]
[50]
In
the present matter NERSA must have been aware that there were sectors
of the public with either special expertise or a special
interest
regarding the issue of whether it was appropriate for extra
generation capacity to be set aside for procurement through
nuclear
power. In addition, in taking the decision, NERSA was under a
statutory duty to act in the public interest and in a justifiable
and
transparent manner whenever the exercise of their discretion was
required but also to utilise a procedurally fair process giving
affected persons the opportunity to submit their views and present
relevant facts and evidence. These requirements were clearly
not met
by NERSA in taking its far reaching decision to concur in the
Minister’s sec 34 determination. It has failed to explain,
for
one, how it acted in the public interest without taking any steps to
ascertain the views of the public or any interested or
affected
party. For these reasons I consider that NERSA’s decision fails
to satisfy the test for rationality based on procedural
grounds
alone.
A
FURTHER PROCEDURAL CHALLENGE BASED ON DELAY
[51]
There
is another procedural challenge to the 2013 sec 34 determination
which is based on the delay in gazetting the decision. The
facts were
that the Director-General in the Department of Energy submitted a
decision memorandum to the Minister on 8 November
2013. The
recommendation to the Minister was that she:
‘
7.1.
approves the sec 34 determination in annexure A
for promulgation in the government gazette, so that the
Nuclear
Procurement process can be launched; and
7.2.
signs the attached letter to NERSA seeking their
concurrence’
.
[14]
[52]
The
Minister approved and adopted the recommendation on 11 November 2013
whilst NERSA concurred in the decision, sending a letter
to this
effect to the Minister on 20 December 2013.
[53]
There
was no suggestion in either the decision memorandum, the Minister’s
approval of the recommendation or in NERSA’s
concurrence in the
decision that it should
not
be gazetted. This last aspect is not surprising given that sec 9 of
NERA provides that NERSA must act in a ‘
justifiable
and transparent manner and in the public interest’
.
More pointedly sec 10 of NERA requires that any decision of NERSA and
the reasons therefor ‘
must
be available to the public’
.
It was, however, only on 21 December 2015, some two years after the
sec 34 determination was made that it was gazetted. This was
the
first occasion on which the 2013 sec 34 determination was made
public. The gazetting followed a further decision memorandum
from the
Director-General to the Minister dated 1 December 2015
[15]
which sought to explain why the determination had not been gazetted
earlier as follows:
‘
3.4
Although the determination process was completed in 2014 with NERSA
and signed by the previous Minister of Energy, Ben Martins,
the
determination was not gazetted due to change in the leadership in the
Ministry and to further conduct some work prior to gazetting.
As a
result there has been progress on the nuclear build work done by the
Department and relevant stakeholders, it is therefore
deemed
appropriate to publish it. The determination needs to be gazetted
…’
There
is, however, no indication what work had to be conducted prior to
gazetting and no evidence thereof in the record.
[54]
As
the applicants point out, however, the sec 34 determination might
never have been communicated had the present application not
been
launched and the record obtained from the respondents. This is borne
out by the decision memorandum in which the Director-General
explained to the Minister that the publishing of the determination
had ‘
become
urgent’
as the Department was facing the present litigation wherein the
applicants claimed that ‘
the
Minister has not published a Section 34 determination nor conducted a
public participation process and therefore any decisions
to
facilitate, organise, commence or proceed with the procurement of
nuclear new generation capacity is unlawful’
.
[16]
The memorandum proceeds:
‘
3.6
During the meeting of 27 November 2015 to brief the legal counsel
defending the Department … (t)he
legal
counsel requested to include the determination when filing the record
for the court papers. The legal councel (sic) advised
that the
inclusion of the determination in the answering affidavit will weaken
the case for the applicant as it will show that
their application is
based on false assumption.’
[55]
It
requires mention that in July 2015 the applicants’ attorney
wrote to the Minister raising a number of questions regarding
nuclear
new generation capacity procurement and compliance with any related
statutory or legal processes. One of the questions
was whether the
Minister had, in consultation with NERSA, made any determinations in
terms of sec 34(1)(a) and (b) of ERA that
new generation capacity was
needed and must be generated from nuclear energy sources. No
substantive reply was received from the
Minister where after the
present application was launched in October 2015.
[56]
Various
consequences flow from the Minister’s failure to gazette the
2013 sec 34 determination after NERSA’s concurrence
therein.
Firstly, until the gazetting in December 2015 the Minister was in
breach of his/her own decision. Secondly, it is open
to serious
question whether the 2013 sec 34 determination could have had any
legal effect until such time as it was gazetted. Although
ERA does
not require that a sec 34 determination be gazetted this is one of
the recognised means for giving public notice of a
decision. In
SARFU
[17]
the Constitutional Court held in regard to the President’s
appointment of a commission of enquiry that:
‘
In
law, the appointment of a commission only takes place when the
President’s decision is translated into an overt act, through
public notification. […] Section 84(2)(f) does not prescribe
the mode of public notification in the case of the appointment
of a
commission of inquiry but the method usually employed, as in the
present case, is by way of promulgation in the
Government
Gazette
.
The President would have been entitled to change his mind at any time
prior to the promulgation of the notice and nothing
which he might
have said to the Minister could have deprived him of that power.
Consequently, the question whether such appointment
is valid, is to
be adjudicated as at the time when the act takes place, namely at the
time of promulgation.’
[57]
The
inordinate delay in gazetting the 2013 sec 34 determination raises a
further problem inasmuch as NERSA’s consent to the
gazetting in
December 2015 was neither sought nor obtained. This raises the
question of whether NERSA’s concurrence in 2013
in the
Minister’s proposed determination necessarily constituted a
valid concurrence in 2015. Developments in the intervening
two years
may well have afforded NERSA material reason to question whether
nuclear new generation capacity was required, the amount
required or
other elements of the 2013 sec 34 determination. Furthermore, had
NERSA’s concurrence been sought afresh in December
2015, new
factors which might have emerged from a fresh public participation
process may have changed its initial views.
[58]
In
these circumstances the failure to gazette or otherwise make the
determination public for two years not only breached the Minister’s
own decision, thus rendering it irrational and unlawful, but violated
the requirements of open, transparent and accountable government.
Furthermore, since the sec 34 determination was in effect only made
on publication, the Minister’s failure to consult NERSA
anew in
December 2015 on her decision to gazette the determination in
unaltered form constituted a breach of sec 34 of ERA, a mandatory
empowering section.
[59]
These
defects, in my view, rendered the Minister’s 2013 sec 34
determination unconstitutional and unlawful, in the latter
case by
virtue of breaches of the principle of legality and thus liable to be
set aside.
SUBSTANTIVE
CHALLENGES TO THE 2013 SECTION 34 DETERMINATION
[60]
Apart
from the grounds relating to the procedural fairness of the 2013 sec
34 determination, the applicants raise several substantive
grounds of
review in challenging the 2013 determination. They contend that the
decision contained in the 2013 sec 34 determination
was irrational,
unreasonable and taken without regard to relevant considerations, or
with regard to irrelevant considerations.
Commencing with the
Minister’s decision, the applicants contend that he
irrationally relied upon the outdated IRP2010. It
would appear that
at the time the Minister took the decision which led to the sec 34
determination, the IRP2010-had been updated
although it was still in
draft form and a further ground of review is that the Minister had
failed to have regard to the contents
of the draft update. A further
ground is that the determination contained no specific procedure for
the procurement of nuclear
new build capacity, the applicants
contending that this was in breach of sec 34 of ERA, read with sec
217 of the Constitution.
As far as NERSA’s role is concerned,
the applicants’ substantive challenges are firstly that NERSA
erroneously viewed
its role as no more than a rubber stamp for the
Minister’s initial decision and, secondly, that it too relied
on the outdated
IRP2010.
[61]
Given
the finding that the challenges based on the procedural fairness of
the 2013 determination and its delayed publication must
succeed, I
consider that no point is served by considering the merits of the
substantive challenges to the 2013 determination based
on
reasonableness or rationality.
THE
2016 DETERMINATION
[62]
I
turn now to deal with the challenge to the 2016 determination which
was gazetted on 14 December 2016. The core of the 2016 sec
34
determination is the same as that of the 2013 determination, namely,
‘
that
energy generation capacity needs to be procured to contribute towards
energy security and to facilitate achievement’
of the country’s ‘
greenhouse
gas emission targets … accordingly, 9 600 megawatts (MW)
should be procured to be generated from nuclear energy’
;
secondly, that the electricity so produced is to be procured through
‘
fair,
equitable, transparent, competitive and cost-effective’
tendering procedures. However, the 2016 determination provided ‘
that
the procurer in respect of the nuclear programme shall be the Eskom
Holdings (SOC) Limited or its subsidiaries’
as opposed to 2013 determination which appointed to the Department of
Energy to this role.
[18]
[63]
The
background to the 2016 determination appears from the Minister’s
supplementary affidavit and the documents that form the
Minister’s
and NERSA’s record of decision which were attached thereto.
During September 2016 the Minister received
legal advice with regard
to the development of a procurement strategy for the nuclear
programme. This advice ‘
resulted
in revisiting of the appointment and role of the DOE (Department of
Energy) as the designated procurement agency in respect
of the
nuclear procurement programme’
.
Thereafter, on 29 September 2016, the Department’s
Director-General provided the Minister with a decision memorandum,
for
approval, in relation to the proposed 2016 determination.
[19]
[64]
The
rationale for the 2016 determination is contained in paras 3.1 –
3.4 of the decision memorandum and which read as follows:
‘
3.1
On 27 September 2016, the Minister of Energy informed the Department
that it was her intention
to have Eskom Holdings (SOC) Limited
(hereinafter referred to as “Eskom”) procure and be the
owner operator of the
new nuclear power plants.
3.2
It appeared that one of the factors the Minister considered in her
decision, was that it
was indicated in a legal opinion sought from
Adv Marius Oosthuizen that the Minister and/or the Department of
Energy is not
empowered by law to directly procure on behalf of other
juristic entities, which are also organs of state (such as Eskom)
unless
their consent is obtained. It was indicated by an authorised
representative from Eskom that Eskom would not provide consent for
the Minister and/or the Department of Energy to procure on their
behalf.
3.3
In order effect (sic) the Minister’s desired change(s) to the
Determination, it is
required that the existing Section 34(1)
Determination be amended.
3.4
Accordingly, the attached revised Section 34(1) Determination
(Annexure A) makes provision
for Eskom (or its subsidiaries –
in the event that a special purpose vehicle will be created and
utilised by Eskom to procure
new generation capacity from nuclear
power) to be the procurement agency and be the owner operator of the
new nuclear build programme.’
[65]
The
Minister duly approved the 2016 decision memorandum on 18 October
2016. On 5 December 2016 a letter was sent to the Chairperson
of
NERSA, attaching a draft of the proposed 2016 determination and
seeking its concurrence therein. The board of NERSA took its
decision
by way of a round robin resolution on or about 8 December 2016.
[20]
The resolution was approved by the acting CEO of NERSA on 5 December
2016 (the same day as the Minister’s letter requesting
NERSA’s
concurrence was sent) and subsequently by the Chairperson on 8
December 2016. On 13 December 2016, at the initial
hearing of this
matter the applicants, together with the public, learnt for the first
time that the 2016 determination had been
made and it was published
in the government gazette the following day. The applicants seek to
review the 2016 determination on
various procedural and substantive
grounds.
[66]
Again,
relying on sec 3 and 4 of PAJA and sec 10(1)(d) of NERA, they contend
that the 2016 sec 34 determination was procedurally
unfair inasmuch
as it was not preceded by any public participation process or
consultation, whether by way of a notice and comment
procedure or
otherwise.
[67]
From
the record it appears that NERSA gave its concurrence to the 2016 sec
34 determination within three days of being asked by
the Minister and
there was therefore no question of any public participation process
or any form of external consultation prior
to NERSA’s decision.
Given the elapse of two years since NERSA’s concurrence in the
2013 determination and the changed
format of the determination, most
particularly in its designation of Eskom Holdings (SOC) Limited or
its subsidiaries as the procurer
in respect of the nuclear programme
it was, in my view, incumbent upon NERSA to afford members of the
public and/or interested
and affected persons (including the
applicants) an opportunity to influence the decision. My reasons for
reaching this conclusion
are in principle the same as those
underlying the same conclusion in respect of the 2013 sec 34
determination.
CAN
THE 2013 AND THE 2016 SECTION 34 DETERMINATIONS CO-EXIST?
[68]
A
further procedural challenge to the 2016 sec 34 determination arises
from the fact that it fails to expressly withdraw or amend
the 2013
determination. When the Minister wrote to NERSA requesting its
concurrence in the 2016 determination she indicated that
the 2013
determination had to be ‘
amended’
.
According to its resolution, NERSA similarly took the view that it
was concurring in an amendment to the 2013 sec 34 determination.
The
recommendation which it approved was that ‘
(c)oncurrence
with the proposed amendment by the Minister …’
and the ‘
amendment
of the decision of the Energy Regulator of 26 November 2013’
.
[21]
However, the determination does not on its own terms amend, revise or
withdraw the 2013 sec 34 determination and nor does it purport
to do
so. It makes no reference at all to the 2013 sec 34 determination
which results in the anomalous situation of there being
two gazetted
sec 34 nuclear determinations which are mutually inconsistent. By way
of example, the first designates the Department
of Energy as the
procuring agency in the nuclear power programme whilst the second
designates Eskom.
[69]
In
these circumstances, contend the applicants, the 2016 determination
is irrational or based on material errors of law or fact,
thereby
violating the principle of legality. In response, the respondents
contend that this ground of review is based on no more
than semantics
since the 2016 determination was in substance an amendment and was
intended and accepted as such by the Minister
and NERSA respectively.
[70]
This
line of argument does not, however, take into account the
consequences of this Court finding that the 2013 determination was
unconstitutional and invalid. In that event, the earlier
determination was valid
ab
initio
i.e. a nullity from the outset and could not be amended.
[22]
This principle was confirmed by the Constitutional Court in
Kruger
v President of the Republic of South Africa
[23]
which dealt with a proclamation issued by the President which the
High Court had held to be null and void and of no force and effect.
The President issued a second proclamation in substitution for the
first in order to correct a bona fide and acknowledged error
in the
first and was worded as ‘
amending’
the first proclamation.
[71]
The
Court found that the first proclamation was objectively irrational
and therefore regarded as a nullity from the outset. It found
further
that whilst the President could have withdrawn it before it came into
force he did not have the power to amend it inasmuch
as it was void
from its commencement and thus could not be amended. In so finding
the Court dismissed an argument that the second
proclamation should
be judged on its substance and not on its form, Skweyiya J stating in
this regard:
‘
While
I support in general the principle that substance should take
precedence over form, that principle must yield in appropriate
cases
to the rule of law’
.
[24]
Accordingly,
if notwithstanding that the 2016 sec 34 determination does not
purport to be an amendment of the 2013 determination,
it in fact was,
and given the finding that the 2013 determination was invalid and
unconstitutional, the 2016 determination is also
invalid as an
impermissible attempt to amend a nullity.
[72]
I
understand the respondents to also advance the argument that the 2016
determination impliedly repealed the 2013 determination.
However, as
the applicants point out, it does not purport to repeal the 2013
determination and neither NERSA nor the Minister claim
that they
intended to repeal the 2013 determination, which remains gazetted.
[73]
On
the assumption that the 2013 and 2016 sec 34 determinations (or at
least part thereof) remain valid, their co-existence is in
my view,
highly problematic. What is the reader or interested member of the
public to make of them? Are there two procurement agencies
i.e. both
Eskom Holdings (SOC) Limited and the Department of Energy? To whom
may the electricity generated from the 9.6 GW of nuclear
energy be
sold? Are there no constraints in this regard (as per the 2016
determination) or must it only be sold to Eskom Holdings
(SOC)
Limited (as per the 2013 determination)? What is the role of the
procurer? Is it as set out in para 6 of the 2013 determination
or
does it remain unspecified, as per the 2016 determination?
[74]
Possible
answers to these questions can be advanced but the lack of certainty
and the need for conjecture is inimical to the rule
of law. Although
vagueness is not specified in PAJA as a ground of review, under the
common law such a ground appears to have been
recognized under the
new constitutional dispensation.
[25]
This ground requires administrative action to be reasonably capable
of meaningful construction for it to be valid although absolute
clarity is not required.
[26]
In any event the grounds of review set out in PAJA are not
exhaustive, sec 6(2)(i) being a catch-all provision providing that
administrative action may be reviewed on other than the listed
grounds if it is ‘
otherwise
unconstitutional or unlawful’
.
[75]
Given
the mutual inconsistency of the 2013 and 2016 sec 34 determinations,
and the failure of the latter to expressly withdraw or
amend the
earlier determination, I consider that the 2016 determination was
irrational and must be set aside on this basis as an
independent
ground of review.
SUBSTANTIVE
CHALLENGES TO THE 2016 SECTION 34 DETERMINATION
[76]
The
applicants also challenge the 2016 determination on various
substantive grounds, contending that the Minister’s decision
was irrational and/or unreasonable and taken without regard to
relevant considerations or with regard to irrelevant considerations.
These attacks are largely based on what the applicants contend was
the Minister’s and NERSA’s reliance on the outdated
IRP2010 and the designation of Eskom as the procurer, apparently
because it refused to give its consent to allow the Department
of
Energy to procure on its behalf. Given the finding that the 2016
determination falls to be reviewed and set aside both by reason
of
NERSA’s failure to hold any public participation process and
for its inherent irrationality, I consider it necessary to
consider
only one of these substantive grounds.
[77]
The
ground in question is directed at NERSA’s role in concurring
with the 2016 determination and the basis of the challenge
is that
the key reason for NERSA giving its concurrence was that it believed
that it would be ‘
mala
fides’
for it not to concur in the Minister’s proposed determination.
This contention was based on an extract from NERSA’s
round
robin resolution approving its concurrence in the Minister’s
proposed determination by the acting CEO of NERSA on 8
December 2016
and reads in part as follows:
[27]
‘
2.1
Background
2.1.4
The Minister has proposed an amendment to the determination regarding
the Department of Energy as the procuring
agency and to be replaced
by Eskom. The amendment of the determination cannot be complete
without the concurrence of the Energy
Regulator therefore the
Minister is requesting the Energy Regulator to concur.
2.2
Issues
2.2.1
Without a decision by the Energy Regulator on the proposed amendment,
the determination will not be in compliance
with the Act and can
negatively impact on the nuclear procurement programme.
…
2.3
Problem Statement
2.3.1
Without the Energy Regulator decision to concur with the proposed
amendment, the nuclear procurement programme
can be negatively
affected.
2.3.2
Considering that the proposed amendment is on a determination that
the Energy Regulator has already concurred
(sic), it can be viewed as
mala fide for the Energy Regulator to delay or refuse to concur with
the proposed amendment by the Minister.
2.4
Motivation
2.4.1
The proposed amendment is procedurally and legally valid at (sic) the
Energy Regulator can concur and bring
finality to the implementation
of the nuclear procurement programme.
…
6
RECOMMENDATIONS
It
is recommended that Electricity Subcommittee approve the:
6.1
Concurrence with the proposed amendment by the Minister in relation
to clause 5 of the Energy
Regulator decision of 26 November 2013.
6.2
The amendment of the decision of the Energy Regulator of 26 November
2013.’
[78]
It
was submitted on behalf of the applicants that the key reason for
NERSA giving its concurrence was that it believed that it would
be
‘
mala
fides’
for it not to concur or, put differently, on the basis that since it
had previously concurred some three years earlier in the 2013
sec 34
determination, it was under an obligation to approve the amendment or
be seen to be acting ‘
mala
fides’
.
However, the applicants contend, there was no legal or factual basis
for any understanding that it would be ‘
mala
fides’
for NERSA not to concur. The 2016 sec 34 determination was, as was
the 2013 determination, a culmination of the exercise of a
discretionary statutory power vested in NERSA irrespective of whether
it was an amendment of the prior sec 34 determination or not.
In
terms of sections 9 and 10 of NERA, NERSA was required, in exercising
its discretion and its duty to decide whether to concur
or not, to
form an independent judgment and was not bound by its past
concurrence in the 2013 determination. NERSA was not required
to
accept that the Minister’s proposed determination was correct
or appropriate particularly since three years had passed
since it had
concurred in the 2013 determination and thus underlying circumstances
may well have changed. It bears repeating that
sec 9(c) of NERA
provides that the members of the Energy Regulator must ‘
act
independently of any undue influence or instruction’
.
[79]
In
the absence of any further explanation by NERSA as to why it took its
decision to concur, and bearing in mind that the terms
of NERSA’s
resolution was clearly an attempt to comply with sec 10(1)(f) of NERA
i.e. ‘
to
explain clearly its factual and legal basis and the reasons’
for its concurrence, these expressed reasons must be accepted. On its
own version, NERSA’s concern was that it would be seen
as
acting
mala
fides
if it did not concur with the Minister’s proposed determination
and this was one of its prime, if not the primary reason,
for its
decision. In these circumstances the applicants have, in my view,
established that NERSA’s concurrence was predicated
on a
material error of law or fact and/or that it failed to act
independently, as required by NERA.
THE
IGA’S
[80]
Two
further issues to be determined in this matter are:
1.
Whether
the President and the Minister violated the Constitution when
deciding to sign and then table the 2014 Russian IGA in relation
to
nuclear issues under sec 231(3) of the Constitution rather than sec
231(2)?
2.
Whether
the Minister violated the Constitution in tabling the US and South
Korean IGA’s in relation to nuclear cooperation
20 years and
almost five years respectively after they had been signed?
[81]
Against
the factual background set out in para 21 above, I deal firstly with
the question of whether the Russian IGA was properly
tabled under sec
231(3) of the Constitution. In relation to this IGA the applicants
seek an order declaring:
1.
the
President’s decision to authorise the Minister’s
signature, and the Minister’s decision to sign, and;
2.
the
Minister’s decision to table the IGA under sec 231(3), (rather
than sec 231(2)), unconstitutional and invalid, and reviewing
and
setting aside these decisions.
[82]
This
relief is sought on the basis that the Russian IGA contains binding
commitments in relation to nuclear procurement when no
similar
commitments were made in the IGA’s concluded with other
governments in relation to nuclear cooperation and it should
therefore have been tabled under sec 231(2) in order to give
Parliament an opportunity to consider whether to approve the
agreement.
The contents of the Russian IGA will be discussed below.
[83]
As
mentioned earlier in response to the applicants’ case, the
respondents raise a number of preliminary points, namely non-joinder
of the foreign governments, the alleged non-justiciability of the
IGA’s and the applicants alleged lack of standing to challenge
the manner of tabling the IGA’s in terms of sec 231 of the
Constitution. On the merits, the respondents contend that failing
the
upholding of any of these preliminary points the Russian IGA is, upon
a proper interpretation, not a ‘
procurement
contract’
with immediate financial application and falls within the category of
a ‘
technical,
administrative or executive agreement’
as envisaged by sec 231(3) of the Constitution, thus not requiring
ratification or accession, and was therefore properly tabled.
[84]
Section
231 of the Constitution deals with international agreements and
provides, in part, as follows:
‘
(1)
The negotiating and signing of all
international agreements is the responsibility of the national
executive.
(2)
An international agreement binds the Republic only after it has been
approved by resolution in both the National
Assembly and the National
Council of Provinces, unless it is an agreement referred to in
subsection (3).
(3)
An international agreement of a technical, administrative or
executive nature, or an agreement which does
not require either
ratification or accession, entered into by the national executive,
binds the Republic without approval by the
National Assembly and the
National Council of Provinces, but must be tabled in the Assembly and
the Council within a reasonable
time.
(4)
Any international agreement becomes law in the Republic when it is
enacted into law by national legislation;
but a self-executing
provision of an agreement that has been approved by Parliament is law
in the Republic unless it is inconsistent
with the Constitution or an
Act of Parliament.
(5)
…’
NON-JOINDER
[85]
The
respondents maintain that the foreign contracting states –
Russia, the United States of America and South Korea –
are
‘
essential
parties’
which have a direct and substantial interest in any orders which the
Court might make and which thus cannot be made or carried
into effect
without prejudicing such parties. They contend further that the
relief sought in relation to the Russian IGA is in
substance an order
to invalidate it by nullifying the conduct of the South African
government in entering therein. As regards the
US and South Korean
IGA’s, the respondents contend that the order sought by the
applicants declaring the manner of their
tabling unconstitutional and
unlawful and reviewing and setting these tabling decisions aside, is
also in substance an attempt
to invalidate the two treaties and thus
by the same token these two governments are also necessary parties.
[86]
Our
law recognises a limited right to object to non-joinder, the limits
of which were defined as follows by Brand JA:
[28]
‘
The right to demand
joinder is limited to specified categories of parties such as joint
owners, joint contractors and partners,
and where the other
party(ies) has (have) a direct and substantial interest in the issues
involved and the order which the court
might make.’
[87]
A
full bench of this Court has held that:
‘
It is well established
that the test whether there has been non-joinder is whether a
party has a direct and substantial interest
in the subject-matter of
the litigation, that is, a legal interest in the subject-matter which
may be prejudicially affected by
the judgment or the order.’
[29]
[88]
In
the present matter, leaving aside the relief relating to the
Minister’s signature of the agreement, no order is sought
against any foreign government, the Court being asked rather to
determine whether the Minister’s actions in terms of sec
231 of
the Constitution were lawful, as a matter of domestic law. The
Minister’s obligations to act constitutionally and
in
accordance with sec 231 are owed to the citizens of this country and
not to foreign governments. Seen from this perspective
none of the
foreign governments that are party to the IGA’s have any direct
and substantial legal interest, as a matter of
South African domestic
law, in the constitutionality of the Minister’s actions. This
view is borne out by recent decisions
of our courts which have never
required the joinder of foreign governments even where the judicial
review of the executive’s
exercise of its domestic powers
related to affairs with a foreign government.
[89]
In
President
of the Republic of South Africa and Others v Quagliani,
[30]
the Constitutional Court was required to determine the validity of
the government’s actions in entering into an international
agreement in relation to extradition with the USA in circumstances
where it had been alleged that the agreement had not been validly
entered into because the President had delegated his own
responsibility in that regard to members of his cabinet. The Court
ultimately
held that the government had acted lawfully in entering
into the international agreement but it was noteworthy that the
United
States government was not a party to the litigation and there
was no suggestion that it should be, merely because the
constitutional
validity of the South African government’s
action in entering into the international agreement was to be
determined.
[90]
Furthermore,
our courts have never required a joinder of foreign governments in
cases involving challenges to the legality of executive
conduct which
directly implicated foreign governments.
[31]
In my view, it is a misnomer on the part of the respondents to
state that the applicants seek orders to ‘
invalidate’
any international agreements. The relief sought by the applicants is,
at its broadest, a declaration that the decisions by the
Minister and
the President in signing, approving and tabling the IGA’s
before Parliament were unconstitutional and invalid,
this as a
matter of domestic constitutional law. Section 172(1)(a) of the
Constitution places an obligation on the courts
to declare any law or
conduct inconsistent with the Constitution invalid to the extent of
its inconsistency. The Court has not
been asked to determine whether
the IGA’s are valid as a matter of international law at the
international level. In the circumstances
the relevant foreign
governments have, as a matter of South African law, no legal interest
in the domestic constitutionality of
the actions of the South African
government. It is not surprising therefore that the respondents were
unable to cite any direct
authority for the proposition that a
foreign government should be joined in a matter such as the present.
Instead they rely only
on the authorities relating to the validity of
domestic contracts enforceable as a matter of South African law.
[91]
In
the circumstances of this matter I consider that there is no need to
join the foreign states and therefore the joinder point
has no merit.
DO
THE APPLICANTS HAVE STANDING?
[92]
The
respondents contend that the applicants have no standing to claim any
relief in relation to the tabling of the Russian IGA since,
if the
incorrect tabling procedure has been utilised, this is a matter
for Parliament to take up with the Minister. By implication
this
contention extends also to the relief sought in relation to the US
and South Korean IGA’s. If this proposition were
correct one
might expect that the Speaker of the NA and the Chairperson of the
NCOP would enter these proceedings and assert that
point of view but
instead neither opposes the relief sought in this regard.
[93]
Whilst
it is correct that in terms of sec 92 of the Constitution, members of
the cabinet, which includes the President, are accountable
collectively and individually to Parliament for the exercise of their
powers and the performance of their functions, it does not
follow
that the applicants lack standing in relation to these issues, either
acting in their own interests or in the public interest.
The first
applicant, Earthlife Africa- Johannesburg, is a non-governmental,
non-profit voluntary association having the power to
sue and be sued
in its own name. The second applicant is a registered public benefit
and non-profit organisation and both brought
this application in
terms of sec 38 of the Constitution in their own right and in the
public interest as contemplated by sec 38(d).
[94]
Section
38 deals with the enforcement of rights and, insofar as it is
material, reads as follows:
‘
38
Enforcement of rights
Anyone
listed in this section has the right to approach a competent court,
alleging that a right in the Bill of Rights has been
infringed or
threatened, and the court may grant appropriate relief, including a
declaration of rights. The persons who may approach
a court are –
(a)
anyone acting in their own interest;
(b)
…
(c)
anyone acting as a member of, or in the interest of, a group or class
of persons;
(d)
anyone acting in the public interest; and
(e)
an association acting in the interest of its members.’
[95]
It
has been held that the provisions of sec 38 ‘
introduces
a radical departure from the common law in relation to standing. It
expands the list of persons who may approach a court
in cases where
there is an allegation that a right in the Bill of Rights has been
infringed or threatened …
’
[32]
[96]
Section
19 of the Bill of Rights guarantees every citizen certain political
rights. Many of these rights find fulfilment in the
representation of
such citizens in Parliament which, in terms of sec 42(2) of the
Constitution, consists of the NA and the NCOP.
Section 42(3) provides
that the NA ‘
is
elected to represent the people to ensure government by the people
under the Constitution’
.
On these grounds alone, I consider that parties other than Parliament
or members of Parliament have a legitimate interest in the
question
of whether IGA’s have been properly tabled in Parliament in
terms of the Constitution.
[97]
In
making their argument the respondents placed reliance on
Metal
and Allied Workers Union and Another v State President of the
Republic of South Africa and Others
[33]
where the court dealt with a challenge to certain emergency
regulations made in terms of sec 3 of the Public Safety Act, 3 of
1953 which had been promulgated in the government gazette but not
tabled in Parliament within 14 days of promulgation as required
by
the Act. Didcott J, on behalf of the full bench, held that the
purpose of tabling was to inform members of Parliament and therefore
conceived for the benefit of, and enforceable by, no one but such
members. However, apart from the fact that this judgment obviously
predates the new constitutional dispensation, the court took this
view ‘
with
some hesitation’
,
recognising the force of the argument to the contrary.
[34]
[98]
In
any event the Constitutional Court has now repeatedly confirmed the
broad grounds of standing in relation to constitutional challenges,
including those relating to executive action.
[35]
Furthermore, the fact that the executive is accountable to Parliament
in relation to the exercise of its power does not detract
from the
principle that the exercise of all public powers must be
constitutional, comply with the principle of legality and that
these
powers are subject to judicial review at the instance of the public.
This was well illustrated by
Economic
Freedom Fighters v Speaker, National Assembly and Others
[36]
where Parliament and the President’s failure to fulfil a
constitutional obligation was vindicated at the instance of a
political
party. As was contended on behalf of the applicants, any
action by the President and the Minister in violation of the
Constitution
are matters of legal interest to the public and to
applicants representing that interest and are not merely a concern of
Parliament.
[99]
Finally,
as the Constitutional Court has held, it is the courts that must
ultimately determine whether any branch of government
has acted
outside of its powers. This was made clear by the following dictum of
Moseneke DCJ on behalf of the Constitutional Court
in
International
Trade Administration Commission v SCAW South Africa (Pty) Ltd
[37]
:
‘
In
our constitutional democracy all public power is subject to
constitutional control. Each arm of the state must act within the
boundaries set. However, in the end, courts must determine whether
unauthorised trespassing by one arm of the state into the terrain
of
another has occurred. In that narrow sense, the courts are the
ultimate guardians of the Constitution. They do not only have
the
right to intervene in order to prevent the violation of the
Constitution, they also have the duty to do so.’
[100]
In
short, if the challenge to the constitutionality of the procedure
whereby the relevant IGA’s have been placed before Parliament
has merit, such conduct must be declared unconstitutional
irrespective of at whose behest this relief is sought. In the
circumstances,
I find that the applicants have standing both in their
own right and in the public interest to challenge the
constitutionality
of the tabling of the relevant IGA’s.
IS
THE RUSSIAN IGA JUSTICIABLE?
[101]
The
respondents contend that the Russian IGA, being an international
agreement, is not or should not be justiciable by a domestic
court,
which may not even interpret or construe such an agreement nor may it
determine the legal consequences arising therefrom.
In doing so they
rely primarily on the authority of
Swissborough
Diamond Mines (Pty) Ltd and Others v Government of the Republic of
South Africa and Others
[38]
where it was held that a domestic court may not interpret or construe
an international agreement nor determine the true agreement
allegedly
concluded between South Africa and another sovereign state.
[102]
The
role of the international treaty in
Swissborough
appears
to have been quite different to that in the present matter. The
plaintiffs had instituted action against the defendants,
the first of
which was the South Africa government, arising out of an alleged
interference with certain mining rights held by the
plaintiffs in
Lesotho. The alleged interference related to the implementation of a
treaty between the South African government
and Lesotho’s
government which provided for the Lesotho Highlands Water project. It
became necessary for the court to decide
whether the determination of
the true agreement between the South Africa government and the
Lesotho government, as an international
law agreement between two
sovereign states and not incorporated into South African municipal
law, was a justiciable issue. The
rationale for the court’s
approach was that it would have to be a very particular case, even if
such a case could exist,
that would justify a court interfering with
a foreign Sovereign. However, the court did find that it could take
cognisance of the
agreements between the governments of the two
countries as well as the contents thereof as facts. The court was
unwilling, however,
to take decisions in regard to the alleged
unlawful conduct of the government of Lesotho, the control of the
government of Lesotho,
and its relationship with the South African
government. It found, as far as the latter was concerned, that there
could be little
doubt that this was not an area for the judicial
branch of government.
[103]
The
situation in the present matter is quite different inasmuch as the
scope of the enquiry into the Russian IGA is limited to a
determination of whether it should have been tabled in Parliament in
terms of sec 231(2) or 231(3) of the Constitution. There are
a number
of reasons why, at least for this limited purpose, the Russian IGA
cannot be regarded as non-justiciable. Firstly, the
conclusion and
tabling of an international agreement before Parliament in terms of
either sec 231(2) or 233 of the Constitution
is an exercise of public
power and the Constitutional Court has made clear that all such
exercises of public power are justiciable
in that they must be lawful
and rational. These include exercises of public power relating to
foreign affairs.
[39]
Secondly,
should an international agreement be tabled incorrectly under sec
231(3) rather than sec 231(2) the review of any such
decision can be
seen as upholding rather than undermining the separation of powers.
The separate but interrelated roles of the
executive and the
legislature in relation to international agreements were clarified by
Ngcobo CJ in
Glenister
v President of the Republic of South Africa and Others
[40]
as follows:
‘
[89]
The constitutional scheme of s 231 is deeply rooted in the separation
of powers, in particular the checks
and balances between the
executive and the legislature. It contemplates three legal steps that
may be taken in relation to an international
agreement, with each
step producing different legal consequences. First, it assigns to the
national executive the authority to
negotiate and sign international
agreements. But an international agreement signed by the
executive does not automatically
bind the Republic, unless it is an
agreement of a technical, administrative or executive nature. To
produce that result, it requires,
second, the approval by resolution
of Parliament
.
…
[95]
To summarise, in our constitutional system, the making of
international agreements falls within the
province of the executive,
whereas the ratification and the incorporation of the international
agreement into our domestic law
fall within the province of
Parliament. The approval of an international agreement by the
resolution of Parliament does not amount
to its incorporation into
our domestic law. Under our Constitution, therefore, the actions of
the executive in negotiating and
signing an international agreement
do not result in a binding agreement. Legislative action is required
before an international
agreement can bind the Republic.’
[104]
Accepting
that the constitutionality and lawfulness of the exercise of powers
under sec 231(2) or (3) of the Constitution by the
President and the
Minister is justiciable, then clearly a review of the lawfulness and
rationality of the exercise of those powers
may well require a court
to consider the content of the relevant international agreement. It
would not be possible for a court
to determine whether or not a
particular IGA should have been tabled under sec 231(2) or 231(3) of
the Constitution without it
having regard to the nature and contents
of that agreement. If this Court were to be precluded from having
regard to the contents
of the Russian IGA for the limited purposes of
determining whether it should have been tabled under sec 231(2) or
231(3) of the
Constitution, this would render nugatory its power to
subject the executive’s conduct to constitutional scrutiny. An
argument
to the contrary was rejected by the Constitutional Court in
Mohamed
v the President of the Republic of South Africa
.
[41]
[105]
For
these reasons I consider that not only is it permissible for this
Court to interpret the Russian IGA to determine its proper
tabling
procedure and whether the Minister acted unconstitutionally or not,
but it is the Court’s duty to do so. I find therefore
that the
respondents’ contention that the Russian IGA is non-justiciable
is without merit.
THE
TERMS OF THE RUSSIAN IGA
[106]
In
broad outline the applicants’ case is that the Russian IGA
contains binding commitments in relation to nuclear procurement,
including providing the Russian Federation with an indemnification,
which takes the IGA well outside the category of those of a
‘
technical
administrative or executive nature’
requiring only tabling in the NA and the NCOP within a reasonable
time to bind the country. They contend further that the terms
of the
Russian IGA are much more far-reaching than those in any of the
comparable IGA’s relating to nuclear cooperation that
were
either tabled before Parliament at the same time or earlier. The
applicants contend that as a result it was irrational for
the
President to approve the signature of the Russian IGA and for the
Minister to sign it. They contend further that, at the very
least,
the Russian IGA should have been tabled under sec 231(2) of the
Constitution, thereby requiring Parliamentary approval.
[107]
For
their part the respondents contend that should the Court find that
the Russian IGA is indeed justiciable or not, a subject for
the
exercise of judicial restraint, it is not a procurement contract of
any sort but an ‘
international
framework agreement for cooperation between sovereign states’
.
They submit that the Russian IGA makes it clear that it is a
bilateral international agreement providing for cooperation between
two sovereign states and is not, nor was it ever intended to be, a
binding agreement in relation to the procurement of new nuclear
reactor plants from a particular country; the only purpose for such
cooperation being the creation of conditions in which the
establishment of a self-sufficient nuclear programme can be pursued.
[108]
Turning
to the contents of the Russian IGA certain key provisions stand out:
1.
Both
the overall description of the agreement and the preamble refer to
the establishment of a ‘
strategic
partnership’
in
the field of nuclear power and industry between the two countries;
2.
The
preamble records by way of background, furthermore ‘
the
intentions of the Government of the Republic of South Africa for the
implementation of a large-scale national plan for the power
sector
development, involving the construction by 2030 of new nuclear power
plant (hereinafter referred to as “NPP”)
units in the
Republic of South Africa’;
3.
The
preamble concludes with a reference to the ‘
legal
fixation’
of the strategic partnership in the field of nuclear power before
setting out the terms of the agreement.
4.
Article
1 provides that the agreement ‘
creates
the
foundation for the strategic partnership in the fields of nuclear
power and industry… aimed at the successful implementation
of
the national plan for the power sector development of the Republic of
South Africa…’.
It is noteworthy that none of the other IGA’s make reference to
the agreements creating a ‘
strategic
partnership’
.
5.
Article
3, using peremptory language, provides that:
‘
The
Parties shall create the conditions for the development of strategic
cooperation and partnership in the following areas:
i.
development of a
comprehensive nuclear new build program for peaceful uses in the
Republic of South Africa, including enhancement
of key elements of
nuclear energy infrastructure …;
ii.
design, construction,
operation and decommissioning of NPP units based on the VVER reactor
technology in the Republic of South Africa,
with total installed
capacity of about 9.6 GW;
iii.
design, construction,
operation and decommissioning of the multi-purpose research reactor
in the Republic of South Africa. …’
It
is common cause that the VVER reactor technology is unique to Russia.
6.
Article
4 of the agreement is noteworthy for its specificity and detail,
providing:
‘
1.
The Parties collaborate in areas as outlined in Article 3 of
this Agreement which are needed for the implementation of
priority
joint projects of construction of two new NPP units with VVER
reactors with the total capacity of up to 2,4 GW at the
site selected
by the South African Party (either Koeberg NPP, Thyspunt or
Bantamsklip) in the Republic of South Africa and other
NPP units of
total capacity up to 7,2GW at other identified sites in the Republic
of South Africa and construction of a multi-purpose
research reactor
at the research centre located at Pelindaba, Republic of South
Africa. The mechanism of implementation of these
priority projects
will
be governed by separate intergovernmental agreements, in which the
Parties
shall
agree on the sites, parameters and installed capacity of NPP units
planned to be constructed in the Republic of South Africa.’
[my
underlining]
7.
Article
6.1 provides for the establishment of a Joint Coordination Committee
‘
to
provide guidance, to coordinate and to control the implementation of
this Agreement’
.
8.
Article
6.4 provides as follows:
‘
In
three years of entry into force of this Agreement the co-chairs of
the Joint Coordination Committee shall make comprehensive
review of
the progress in the implementation of this Agreement and provide
appropriate recommendations to the Competent Authorities
of the
Parties regarding further implementation of this Agreement’.
9.
Article
7 provides that:
‘
Cooperation
in areas as outlined in Article 3 of this Agreement, will be governed
by separate agreements between the Parties, the
Competent
Authorities’
and
goes on to state ‘
(t)he
Competent Authorities of the Parties can, by mutual consent, involve
third countries’ organizations for the implementation
of
particular cooperation areas in the framework of this Agreement.’
It
was contended on behalf of the applicants that the latter part of
this clause would appear to preclude, absent Russia’s
consent,
a situation where at least some of the proposed nuclear power plants
are constructed or operated by other countries in
addition to Russia.
10.
Article
9 provides as follows:
‘
For
the purpose of implementation of this Agreement the South African
Party will facilitate the provision of a special favourable
regime in
determining tax and non-tax payments, fees and compensations, which
will be applied to the projects implemented in the
Republic of South
Africa within the areas of cooperation as outlined in Article 3 of
this Agreement, subject to its domestic legislation’
.
This
commitment by the South African government to afford Russia a
favourable tax regime in relation to the construction of new
nuclear
power plants is not to be found in any other IGA under
consideration.
11.
On
behalf of the applicants it was contended that in terms of Article 15
the government of the Republic of South Africa agreed to
incur
liability arising out of any nuclear incident occurring in relation
to any nuclear power plant to be constructed in terms
of the
agreement, or agreements arising therefrom, and also provides an
indemnification to Russia and its entities from any ensuing
liability. Insofar as it is relevant, Article 15 reads:
‘
1.
The authorized organization of the South African Party at any time at
all stages of the construction and operation of the NPP
units and
Multi-purpose Research Reactor shall be the Operator of NPP units and
Multi-purpose Research Reactor in the Republic
of South Africa and be
fully responsible for any damage both within and outside the
territory of the Republic of South Africa caused
to any person and
property as a result of a nuclear incident … and also in
relation with a nuclear incident during the transportation,
handling
or storage … of nuclear fuel and any contaminated materials …
both within and outside the territory of the
Republic of South
Africa. The South African Party shall ensure that, under no
circumstances shall the Russian Party or its authorized
organization
nor Russian organizations authorized and engaged by their suppliers
be liable for such damages as to the South African
Party and its
Competent authorities, and in front of its authorized organizations
and third parties.’
It
is unnecessary to analyse in detail the structure of liability
indemnification which this Article provides. Its suffices to state
that it clearly has potentially far-reaching financial implications
for the South African government or state agencies, quite apart
from
any persons or instances which may be involved in a nuclear incident.
12.
Article
16 provides for all disputes arising from the interpretation or
implementation of the agreement to be settled ‘
amicabl
y’
by ‘
consultations
or negotiations through diplomatic channels’
.
Significantly, it provides that ‘
(i)n
case of any discrepancy between this Agreement and agreements
(contracts), concluded under this Agreement, the provisions of
this
Agreement shall prevail’
.
This provision appears to make it clear that the Agreement is to take
precedence over any subsequent agreement, underscoring the
importance
of its provisions.
13.
Article
17 provides in part as follows:
‘
This
Agreement shall enter into force on the date of the receipt through
diplomatic channels of the final written notification of
the
completion by the Parties of internal government procedures necessary
for its entry into force’.
14.
It
provides further that the agreement shall remain in force for a
period of 20 years and thereafter be renewed automatically for
a
period of 10 years unless terminated by either party giving one year
written notice thereof. Article 17.4 provides, significantly,
‘
(t)he
termination of this Agreement shall not affect the rights and
obligations of the Parties which have arisen as a result of
the
implementation of this Agreement before its termination, unless the
Parties agree otherwise’
and
further provides that its termination ‘
shall
not affect the performance of any of the obligations under agreements
(contracts) which arise during the validity period of
this Agreement
and are uncompleted at the moment of such termination, unless the
Parties agree otherwise’
.
[109]
Apart from the tone and content of these provisions, which speak for
themselves, as a whole they illustrate that three hallmarks
of the
Agreement are its degree of specificity, the frequent use of
peremptory language and the scope and importance of key elements
which form the bedrock of the Agreement. All these factors combine to
suggest a firm legal commitment by the contracting parties
to the
‘
strategic
partnership’
which the Agreement establishes between the two countries, as well as
in relation to the future, steps and developments which the
far-reaching Agreement clearly foreshadows. Although it is clear that
the Agreement could or will be followed by further agreements,
the
importance and permanence of many of its provisions are, in my view,
unmistakeable.
[110]
It
may well be difficult to delineate the precise line between an
agreement relating to the procurement of new nuclear reactor plant
as
distinct from one dealing with cooperation towards this end. In my
view, however, seen as a whole, the Russian IGA stands well
outside
the category of a broad nuclear cooperation agreement and, at the
very least, sets the parties well on their way to a binding,
exclusive agreement in relation to the procurement of new reactor
plants from that particular country.
[111]
It
would appear that the competent authorities under the agreement, the
Department of Energy and Rosatom, laboured under a similar
apprehension when, the day after the Agreement was concluded, they
issued a joint press statement announcing that the ‘
Agreement
lays the foundation for the large-scale nuclear power plants (NPP)
procurement and development programme of South Africa
based on the
construction in RSA of new nuclear power plants with Russian VVER
reactors with total installed capacity of up to
9,6 GW (up to 8 NPP
units)
’
which would be ‘
the
first NPPs based on the Russian technology to be built on the African
continent.’
[42]
Be that as it may, whatever its true nature the Russian IGA is, in my
view, clearly more than a mere ‘
framework’
or non-binding agreement as contended by the respondents.
[112]
The
conclusion which I have reached in this regard is reinforced by a
comparison of the 2014 Russian IGA with the 2004 Russian IGA
and each
of the other IGA’s tabled in June 2015. The 2004 Russian IGA
contains no liability or indemnification clause in
relation to the
construction and operation of nuclear power plants indemnifying the
Russian government or its agencies from any
damages and placing
responsibility on the South African government both within and
outside the country. Nor is there firm commitment,
let alone any
reference, to the construction of new nuclear plants based on Russian
reactor technology. Likewise there is no prohibition,
save with the
consent of Russia, on involving third countries’ organisations
in the construction, operating or decommissioning
of nuclear power
plants. The 2004 IGA contains no undertaking by the South African
government to facilitate a special tax regime
applying to the
construction and operation of new nuclear power plants in South
Africa. Nor is there any provision envisaging the
conclusion of
further ‘
agreements
(contracts)’
under the 2004 IGA or that its provisions would prevail over the
terms of later contracts. The presence of the above-mentioned
terms
in the 2014 Russian IGA begs the question why it was concluded when a
general nuclear cooperation agreement, concluded in
2004, already
existed.
THE
CORRECT PROCEDURE TO RENDER THE RUSSIAN IGA BINDING
[113]
The
structure of and rationale behind sec 231 of the Constitution has
been addressed by academic writers. Professor Dugard has commented
that ‘
the
practice of the government law advisors is to treat agreements ‘of
a routine nature, flowing from daily activities of
Government
departments’ as not requiring parliamentary approval. Where,
however, there is any doubt the agreement is referred
to
Parliament’.
[43]
Professor Botha,
[44]
noting
that the Constitution is silent on the question of who makes the
classification as to whether an IGA is to be tabled under
sec 231(2)
or (3), comments as follows:
‘
Current
practice is that the determination of whether a treaty falls under
section 231(3) and therefore does not require parliamentary
approval,
vests in the line-function minister within whose portfolio the
subject matter of the treaty falls. This decision must
be taken in
conjunction with the law advisors of the Departments of Justice and
Foreign Affairs..
[45]
However,
Professor Botha expresses his reservations about the wisdom of this
practice insofar as the party negotiating the treaty
also decides
upon its classification for tabling purposes.
[114]
I
agree with the argument made on behalf the applicants that sec 231
and, in particular, the interplay between sec 231(2) and 231(3),
must
be interpreted in order to give best effect to fundamental
constitutional values and so as to be consistent with the
constitutional
scheme and structure.
[46]
The tabling of an IGA under sec 231(3) permits the executive to bind
South Africa to an agreement without parliamentary approval
or the
public participation that often accompanies any such parliamentary
approval process. Limiting those international agreements
which may
be tabled under sec 231(3) to a limited subset of run of the mill
agreements (or as Professor Dugard puts it, agreements
‘
of
a routine nature, flowing from daily activities of government
departments’
)
which would not generally engage or warrant the focussed attention or
interest of Parliament would give optimal effect to the
fundamental
constitutional principles of the separation of powers, open and
accountable government, and participatory democracy.
For the reasons
given earlier the Russian IGA is, in my view, certainly not an
agreement of a routine nature.
[115]
The
treatment of the Russian IGA by the State Law Advisor (International
Law) (and presumably the drafter or co-drafter of the IGA)
also casts
light on the issue of the correct procedure to be followed in laying
it before Parliament. In an explanatory memorandum
which served
before the Minister and the President, the senior State Law Advisor
concluded: ‘
The
Agreement falls within the scope of section 231(2) of the
Constitution and Parliamentary approval is required’.
The
Minister’s decision not to act in accordance with this view but
rather to table the Russian IGA under sec 231(3) of the
Constitution
is explained on behalf of the respondents on the basis that the State
Law Advisor’s view ‘
was
and is wrong’
.
There is no indication in the record however that the Minister sought
or obtained any alternative legal advice and her decision
to proceed
in terms of sec 231(3) is not explained in any documents forming part
of the record.
[116]
Having
regard to all these factors I consider that the Russian IGA cannot be
classified as falling within that category of international
agreements which become binding by merely tabling them before
Parliament. I am unable to accept that the Russian IGA can notionally
be considered a routine agreement. The Agreement’s detail and
ramifications are such that it clearly required to be scrutinised
and
debated by the legislature in terms of sec 231(2) of the
Constitution. It follows that the Minister’s decision to table
the agreement in terms of sec 231(3) was, at the very least,
irrational. At best the Minister appears to have either failed to
apply her mind to the requirements of sec 231(2) in relation to the
contents of the Russian IGA or at worst to have deliberately
bypassed
its provisions for an ulterior and unlawful purpose.
THE
ALLEGED UNLAWFUL AUTHORISATION BY THE PRESIDENT AND SIGNATURE, BY THE
MINISTER, OF THE RUSSIAN IGA
[117]
The
relief sought by the applicants in relation to the Russian IGA is not
confined to its review and setting aside on the basis
that the
Minister employed the incorrect procedure in placing it before
Parliament. They seek also a declaration that the Minister’s
decision to sign the agreement and the President’s decision to
authorise the Minister’s signature were unconstitutional
and
unlawful, as well as the reviewing and setting aside of these
decisions.
[118]
The
applicants’ case in this regard is based on the argument that
the Agreement violates sec 217 of the Constitution which
requires
that when the national sphere of government ‘
contracts
for goods or services, it must do so in accordance with a system
which is fair, equitable, transparent, competitive and
cost
effective’.
The applicants contend that, viewed as a whole the Russian IGA
contains sufficient particularity and commitment as to fall within
the ambit of a contract ‘
for
goods and services’
under
sec 217 although, at the time the Minister signed and the President
authorised her signature, there was no procurement system
in place
that complied with sec 217 in relation to the procurement of nuclear
new generation capacity. It will be recalled that
the 2013 sec 34
determination (and the 2016 determination) merely repeated the key
wording of sec 217(1) of the Constitution without
specifying the
tendering procedures. In the alternative, the applicants contend that
even if the Russian IGA did not fall within
the meaning of a contract
under sec 217, at the very least it expressly formed part of the
first steps of a procurement process.
[119]
In
my view it is neither necessary nor desirable to address this ground
of review in these proceedings. Doing so at this stage could
well
offend against the doctrine of the separation of powers and could be
an instance of the court interpreting an international
agreement when
it would be appropriate for it to exercise judicial restraint. In
this regard it will be recalled that the findings
in relation to the
nature of the Russian IGA were made solely for the purposes of
determining whether the Agreement was one which
should have been put
before the legislature in terms of sec 231(2) or 231(3) of the
Constitution.
[120]
The
underlying reason why the applicants’ argument in this respect
should not be entertained at this stage arises from the
nature of the
further relief they seek in relation to the Russian IGA, namely, that
the decision to table it under sec 231(3) be
reviewed and set aside.
If such relief is granted the effect thereof will be that the
Agreement will have no binding effect in
domestic law. Should the
executive then choose to table the Agreement before Parliament in
terms of sec 231(2), a parliamentary/political
process will follow in
which the Agreement will be debated in both the NA and the NCOP with
a view to its approval or disapproval
by Parliament. It may very well
also be the subject of a process of public participation conducted
through Parliament. The
outcome of this process cannot be
foreseen nor should it be anticipated. In these circumstances it
would be invidious if the Court
were, at this stage, to declare that
certain of its provisions are inconsistent with the Constitution and,
more specifically, sec
217 thereof. This is not to suggest, however,
that the Court will lack jurisdiction to deal with such a question in
future if the
need should arise.
[121]
For
these reasons I consider that the principle of separation of powers
calls for the Court to exercise judicial restraint at this
stage and
to decline to consider the further relief sought by the applicants in
relation to the Russian IGA.
WERE
THE US AND SOUTH KOREAN AGREEMENTS PROPERLY TABLED IN TERMS OF SEC
231(3)?
[122]
The
final issue to be addressed is whether the IGA’s concluded with
the United States of America and South Korea relating
to nuclear
cooperation were properly tabled in Parliament in terms of sec 231(3)
of the Constitution.
[123]
The
parties appeared to be in agreement that in the ordinary course the
two IGA’s would properly fall to be tabled in Parliament
in
terms of sec 231(3) in that they were treaties or agreements of a
‘
technical,
administrative or executive nature’
or not requiring either ratification or accession. Where they
differed was on the consequences of the delay in tabling the
agreements.
It will be recalled that on or about 10 June 2015 the
Minister decided to table five separate IGA’s relating to
nuclear matters
before Parliament in accordance with sec 231(3) of
the Constitution. Three of these IGA’s, the Chinese, the French
and the
Russian, were signed or concluded in late 2014 but the
remaining two, the US and the South Korean IGA’s were signed on
25
August 1995 and 8 October 2010, respectively. They were,
therefore, as at the date of tabling, concluded more than two decades
previously and just more than four years and eight months,
respectively.
[124]
The
applicants’ challenge to the constitutionality of the tabling
of the US and South Korean IGA’s is based upon what
they
consider to be the unlawful and unconstitutional delay in tabling
those agreements before Parliament. They contend that the
only
reasonable inference to be drawn from these delays is that the two
IGA’s in question were tabled as ‘
mere
window dressing’
and to minimise the damage caused by the revelations regarding the
Russian IGA and the joint press statement portraying it as a
fait
accompli
that Russia would construct nuclear power plants in South Africa. The
applicants contend that this ulterior purpose rendered the
Minister’s
decision unlawful and unconstitutional since it was not rationally
connected to the purpose for which the power
was conferred and was
therefore in breach of the principle of legality. In the view that I
take of this matter, however, it is
not necessary to determine
whether the Minister acted with an ulterior motive in tabling the US
and South Korean IGA’s under
sec 231(3) of the Constitution.
[125]
The
second leg of the applicants’ challenge is simply that the
length of the delay could not constitute a ‘
reasonable’
period
and therefore the tablings violate sec 231(3). For their part the
respondents seek to justify the delays on the basis that
the
reasonableness thereof must be determined with regard to the relevant
surrounding circumstances and, secondly, contend that
the purpose of
tabling under sec 231(3) is simply to notify or inform Parliament of
a treaty that binds the Republic and that,
at worst, it is only the
delay itself that is unconstitutional.
[126]
I
cannot agree with this latter interpretation which seeks to remove
the obvious linkage in sec 231(3) between the tabling of the
agreement in Parliament, and thus it being rendered binding, and the
requirement that this be done within a reasonable time. As
was
stated by Ngcobo CJ in
Glenister
,
‘
T
he
constitutional scheme of s 231 is deeply rooted in the separation of
powers, in particular the checks and balances between the
executive
and the legislature’
[47]
.
Section
231(3) establishes a procedure whereby the State is bound by a
particular class of international agreements without the
formal
approval of Parliament. The requirement that the tabling takes place
‘
within
a reasonable time’
and the use of the word ‘
must’
clearly indicates that this is a prerequisite for the lawful
invocation of sec 231(3) or, put differently, a jurisdictional
requirement
of the procedure. The interpretation contended for on
behalf of the respondents would result in a situation where the
executive
can, as one arm of government, bind the State on the
international plane whilst at the same time keeping another arm of
government,
the legislature, in the dark about such international
agreements. Such an interpretation pays scant respect to the
principles of
openness and accountability which are enshrined in the
Constitution. Section 41(1) requires all spheres of government and
all organs
of state within each sphere to ‘
provide
effective, transparent, accountable and coherent government for the
Republic as a whole’
whilst sec 1 of the Constitution sets out these attributes as
founding values in a multi-party system of democratic government.
[127]
Seen
in this light it is clear that where the national executive utilizes
sec 231(3) to render the Republic bound under an international
agreement, its exercise of the power is subject to the requirement
that it makes such agreement public and tables it before Parliament
within a reasonable time. In this sense it is a composite
requirement, the power not being properly exercised unless the
agreement
is tabled before Parliament within a reasonable time.
[128]
On
behalf of the respondents the delays were explained on the basis that
although the two IGA’s were signed much earlier there
was no
need to rely on them as binding agreements until 2015 since prior
thereto there was ‘
no
practical or immediate need for nuclear cooperation’
.
This explanation fails to explain why, in the first place, if there
was no need for nuclear cooperation at those times, the IGA’s
were concluded in 1995 and 2010. Nor does it offer an adequate
explanation as to why, having gone to the trouble of signing the
two
IGA’s, they were then not simply tabled in Parliament and
thereby rendered binding, against the eventuality that the
‘
practical
need’
for cooperation might arise in due course. However, even if one
accepts at face value the respondents’ explanation for the
delays, they are in my view of such magnitude that they could never
qualify as reasonable, not least because accepting such delays
would
render the time requirement in sec 231(3) meaningless.
[129]
The
respondents also contend that any alleged unreasonable delay in the
tabling of the US and South Korean IGA’s in Parliament
is a
matter for that body to deal with. However, as was pointed out on
behalf of the applicants, the Speaker of the NA and the
Chairperson
of the NCOP are also respondents in this matter and have neither
opposed the relief sought nor made any submissions
regarding
Parliament’s disagreement with the interpretation of sec 231(3)
contended for by the applicants. In any event,
as stated earlier, it
is the duty of the courts to determine whether the executive has
failed to comply with the Constitution and
declare such failure
invalid and/or unconstitutional to that extent. For these reasons I
conclude that the tabling of the US and
South Korean agreements
violated the provisions of the Constitution and fall to be set aside.
THE
APPROPRIATE RELIEF
[130]
Largely
as a result of the introduction by the respondents of the two sec 34
determinations well after the commencement of the litigation,
the
applicants amended the relief initially sought. For the sake of
convenience the applicants put up a draft order in which they
set out
the range of relief sought.
[131]
In
considering the appropriate relief to be granted the Court is guided
firstly by sec 172 of the Constitution which provides that:
‘
(1) When deciding a
constitutional matter within its power, a court -
(a)
must declare that any law
or conduct that is inconsistent with the Constitution is invalid to
the extent of its inconsistency; and
(b)
may make any order that is
just and equitable, including –
…
.
(ii) an order suspending the
declaration of invalidity for any period and on any conditions, to
allow the competent authority to
correct the defect.’
[132]
The
respondents have not suggested that any declarations of invalidity
sought in this matter should be suspended or offered a justification
as to why any such suspension would be just and equitable. The
Constitutional Court has emphasised, moreover, that ‘
the
Constitution, and the binding authority of this court all point to a
default position that requires the consequences of invalidity
to be
corrected or reversed where they can no longer be prevented. It is an
approach that accords with the rule of law and the
principle of
legality
.
[48]
[133]
In
the applicants’ draft order there are four sections dealing
respectively with the Russian IGA, the tabling of the US and
South
Korean IGA’s, the processes to be followed by the Minister in
regard to a procedurally fair public participation process
prior to
the commencement of any procurement process for nuclear new
generation capacity and, finally, the sec 34 determinations.
I shall
deal with them in that order.
THE
RUSSIAN IGA
[134]
The
applicants seek an order declaring unlawful and unconstitutional, and
reviewing and setting aside, the Minister’s decision
to sign
the Russian IGA, the President’s decision to authorise the
Minister’s signature thereof, and the Minister’s
decision
to table the Russian IGA before Parliament in terms of sec 231(3) of
the Constitution.
[135]
As
concluded earlier, the Minister’s decision to table the Russian
IGA before Parliament in terms of sec 231(3) of the Constitution
must
be declared unlawful and unconstitutional and reviewed and set aside.
However, for the reasons given relating to the separation
of powers
and the Court’s reluctance to consider at this stage whether
the Russian IGA in its present form is unconstitutional
for lack of
compliance with sec 217, the balance of the relief is refused.
THE
TABLING OF THE US AND SOUTH KOREAN IGA’S
[136]
The
applicants seek a declaration that the tabling of the US and South
Korean IGA’s in terms of sec 231(3) was unlawful and
unconstitutional and reviewing and setting aside the Minister’s
decision to so table them. In this regard the respondents
submitted
that, on its interpretation of sec 231(3), namely that tabling within
a reasonable time is not a jurisdictional requirement,
the Court
should, at worst for the respondents, merely declare that the
Minister’s delay in the tabling of the IGA’s
was
unconstitutional. No such order is competent, however, given the
finding which this Court has made, namely that tabling within
the
reasonable period is a jurisdictional requirement for compliance with
sec 231(3).
[137]
The
question of what steps the respondents should or might take in
consequence of our holding the Minister’s tabling decision
invalid is not a matter which we have been asked to consider, leaving
the Minister free to take whatever steps, including steps
on the
international plane, may be considered necessary in the light
of the Court’s order. A consequence of such a
finding is that
the US and South Korean IGA’s in their present form cannot be
tabled under sec 231(3). It is apposite to
point out, however, that
it may well be open to the executive to utilise the more onerous
procedure set out in sec 231(2) of the
Constitution with a view to
rendering the US and South Korean IGA’s binding. In my view
that procedure is non-exclusive in
the sense that the executive is
not precluded from utilising its provisions in relation to treaties
which fall within the ambit
of sec 231(3). If I am correct in this
view it serves to emphasise that the executive will not be stultified
by the Court’s
order.
[138]
In
the result the applicants are entitled to the declarator which they
seek and the review and setting aside of the Ministers’
decisions to table the US and South Korean IGA’s under sec
231(3) of the Constitution.
THE
2013 AND
2016 SEC 34
DETERMINATIONS
[139]
The
applicants seek a declaration that the 2013 and 2016 sec 34
determinations are unlawful and unconstitutional and reviewing and
setting them aside. For the reasons given the basis for such relief
has been established and in my view it would be just and equitable
to
grant such relief.
[140]
The
applicants seek an order setting aside any ‘
Requests
for Proposals’
or
‘
Requests
for Information’
issued pursuant to the aforesaid determinations. There is limited
information in the papers on the extent to which such Requests
have
been issued and the consequences thereof. However the 2013 sec 34
determination makes it clear that part of the procuring
agency’s
role is to prepare, and presumably issue, Requests for Proposals.
Since both sec 34 determinations fall to be set
aside as unlawful and
unconstitutional, it follows that identifiable steps taken pursuant
to those determinations must suffer the
same fate and thus relief
sought in this regard is appropriate and must be granted.
FUTURE
PUBLIC PARTICIPATION PROCESSES
[141]
The
applicants seek a declarator that, prior to the commencement of any
procurement process for nuclear new generation capacity,
which stage
they define, the Minister and NERSA:
‘
are
required in consultation, and in accordance with procedurally fair
public participation processes, to have determined that:
(a)
new
generation capacity is required and that the electricity must be
generated from nuclear power and the percentage thereof;
(b)
the
procurement of such nuclear new generation capacity must take place
in terms of a procurement system which must be specified
and which
must be fair, equitable, transparent, competitive and cost
effective.’
[142]
This
Court has not dealt specifically with the question of whether the
Minister must follow a procedurally fair public participation
process
before exercising his/her powers under sec 34(1) of ERA and
accordingly it would be inappropriate to make any order in
this
regard. It has, however, considered the question of whether NERSA,
before concurring in any such decision, must follow a public
participation process. The finding that it is under such a duty is
central to this judgment and does not require restatement in
a
declarator and to that extent the declaratory relief sought in this
regard is unnecessary and superfluous.
[143]
Similarly,
the Court has not found it necessary to address to the question of
whether any sec 34 determination must specify the
terms of the
procurement system which must apply to nuclear new generation
capacity. Given that the 2013 and 2016 sec 34 determinations
fall to
be set aside and that the Minister must, so to speak, start with a
clean slate it would in our view be inappropriate for
the court to
prescribe to the Minister the form of any procurement process to be
adopted. In any event it is self-evident that
any large scale
procurement process initiated by the state or its agencies must
comply with sec 217 of the Constitution and other
relevant
legislative enactments and that it be specified before any
procurement process commences. In my view it would be unnecessary
to
restate these obvious requirements and indeed, both sec 34
determinations provided that the electricity produced from such new
generation capacity should be procured through a tendering procedure
with the aforementioned attributes although the procedure
was not
specified. For these reasons the declaratory relief sought in this
section is refused.
COSTS
[144]
The
applicants have achieved substantial success in the application and
therefore it is appropriate that they are awarded their
costs. The
applicants sought the costs of three counsel. Given the complexity,
novelty and importance of the matter there can be
no quarrel with an
order on such terms. Although the applicants sought a costs order
against both the President and the Minister,
jointly and severally,
and the application was opposed by the President, no specific relief
was granted against him or in relation
to any conduct on his part. In
the circumstances any costs order should be against the Minister
alone.
[145]
The
applicants sought also a special order of costs in relation to that
aspect of the relief in which it sought a declarator on
the
assumption of there being no relevant sec 34 determination in place.
The Minister only revealed in the Rule 53 record that
such a
determination was in place, despite having been pertinently asked
about the existence of any such determination prior to
the
commencement of the litigation. For these reasons the applicants
contend that the Minister should be held responsible for the
wasted
costs associated with them having to amend their relief and the
delays created by having to supplement their challenge.
The
circumstances in which the 2013 sec 34 determination was only
revealed at a comparatively advanced stage in this litigation,
and
apparently in order to gain some advantage, have been set out
earlier. In my view it is appropriate that the Minister should
have
to pay the extra costs on the scale of attorney and client as a mark
of this Court’s displeasure at the manner in which
this issue
was handled on her behalf.
[146]
In
the result the following order is made:
1.
It
is declared that:
1.1
The first respondent’s (the Minister’s) decision on or
about
10 June 2015 to table the Russian IGA before Parliament in
terms of sec 231(3) of the Constitution is unconstitutional and
unlawful
and it is reviewed and set aside;
1.2.
The first respondent’s decisions on or about 10 June 2015 to
table the
following agreements before Parliament in terms of sec
231(3) of the Constitution:
1.2.1
The
Agreement for Cooperation between the Government of the Republic of
South Africa and the United States of America concerning
Peaceful
Uses of Nuclear Energy; and
1.2.2
the
Agreement between the Government of the Republic of Korea and the
Government of the Republic of South Africa regarding Cooperation
in
the Peaceful Uses of Nuclear Energy; are unlawful and
unconstitutional, and are reviewed and set aside.
1.3.
the determination under sec 34(1) of the Electricity Regulation Act,
gazetted on 21 December 2015 (GN
1268, GG 39541) in relation to the
requirement and procurement of nuclear new generation capacity, made
by the first respondent
on 11 November 2013, with the concurrence of
NERSA given on 17 December 2013, is unlawful and unconstitutional,
and it is reviewed
and set aside;
1.4.
the determination under sec 34(1) of Electricity Regulation Act
gazetted on 14 December 2016 (GNR 1557,
GG 40494) in relation to the
requirement and procurement of nuclear new generation capacity,
signed by the first respondent on
5 December 2016, with the
concurrence of NERSA given on 8 December 2016, is unlawful and
unconstitutional, and it is reviewed and
set aside;
2.
Any
Request for Proposals or Request for Information issued pursuant to
the determinations referred to in paras 1.3 and 1.4 above
are set
aside;
3.
The
first respondent is to pay the costs of this application;
4.
The
first respondent is to pay those costs incurred by the applicants as
a result of the late disclosure of the 2013 sec 34 determination,
on
an attorney and client scale.
____________________
BOZALEK
J
____________________
BAARTMAN
J
APPEARANCES
For
the Applicants
:
Adv
D Unterhalter
(SC)
Adv
M Du Plessis
Adv
A Coutsoudis
Adv
S Magardie
As
Instructed by
: Adrian
Pole Attorneys
Ref:
A Pole
For
the 1
st
& 2
nd
Respondents
: Adv MM
Oosthuizen (SC)
Adv
K Warner
Adv
RM Molea
As
Instructed
: State
Attorney: Pretoria
Ref:
E Snyman
[1]
Media Release “Russia and
South Africa sign agreement on strategic partnership in nuclear
energy” Pretoria, 22 September
2014 – record volume 1 p
131.
[2]
Media Release “Minister
Joemat-Petterson concludes her visit to Vienaa, Austria” 23
September 2014 – record
volume 4 p 1293.
[3]
A Klees
Electricity
Law in South Africa
(2014)
p 16 para 3.4.3.
[4]
President of
the Republic of South Africa and Others v South African Rugby
Football Union and Others 2000 (1) SA 1 (CC).
[5]
S Woolman and
M Bishop
Constitutional
Law of South Africa
2
nd
ed vol 4 [original service: 06-08] p 63-32.
[6]
Permanent Secretary,
Department of Education and Welfare, Eastern Cape, and Another v
Ed-U-College (PE) (Section 21) Inc
2001
(2) SA 1
(CC) para 18.
[7]
Grey’s Marine Hout Bay
(Pty) Ltd and Others v Minister of Public Works and Others
2005 (6) SA 313 (SCA).
[8]
Grey’s
Marine
n
7
para 23.
[9]
Steenkamp NO v Provincial
Tender Board, Eastern Cape
2007
(3) SA 121
(CC) para 21.
[10]
2010 (3) SA 293 (CC).
[11]
Albutt
n
10 para 68-69.
[12]
2013 (1) SA
248
(CC) para 34.
[13]
Democratic
Alliance
n
12
para 36.
[14]
Memorandum –
Department of Energy “Determination in respect of the Nuclear
Programme” (11 November 2013) –
record volume 2 p
488
para 8.6.
[15]
Memorandum –
Department of Energy “
Determination
under Section 34 (1) of the Electricity Regulation Act No. 4 of 2006
– Nuclear Procurement Programme”
(1 December 2015) –
record volume 7 p 108 document no. 19.2.
[16]
Memorandum
n
15 p 110 para 3.5.
[17]
SARFU
n
4 para 44.
[18]
The 2016 sec
34 determination reads in full as follows:
‘
NUCLEAR
PROGRAMME
DETERMINATION
UNDER SECTION 34(1) OF THE ELECTRICITY REGULATION ACT 4 OF 2006
PART
A
The
Minister of Energy (“the Minister”), in consultation
with the National Energy Regulator of South Africa (“NERSA”),
acting under section 34(1) of the Electricity Regulation Act 4 of
2006 (as amended) (the “ERA”) has determined as
follows:
1.
that
energy generation capacity needs to be procured to contribute
towards energy security and to facilitate achievement of the
greenhouse gas emission targets for the Republic of South Africa,
accordingly, 9 600 megawatts (MW) should be procured to be
generated
from nuclear energy (“nuclear programme”), which is in
accordance with the capacity allocated under the
Integrated Resource
Plan for Electricity 2010-2030 (published as GN 400 of 06 May 2011
in
Government
Gazette
No. 34263) (“IRP 2010-2030” or as updated);
2.
that
electricity produced from the new generation capacity (“the
electricity”), shall be procured through tendering
procedures
which are fair, equitable, transparent, competitive and
cost-effective and provide for private sector participation;
3.
that
the nuclear programme shall target connection to the Grid as
outlined in the IRP2010-2030 (or as updated), taking into account
all relevant factors including the time required for procurement;
4.
that
the procurer in respect of the nuclear programme shall be the Eskom
Holdings (SOC) Limited or its subsidiaries.’
[19]
Decision
Memorandum – Department of Energy “Determination under
Section 34(1) of the Electricity Regulation Act 4
of 2006 –
Nuclear Procurement Programme” (29 September 2016) –
record volume 5A p
1546.
[20]
Round Robin
Resolution – NERSA “Confirmation of the Approval of the
Round Robin Resolution: Concurrence with the Proposed
Amendment of
Section 34(1) of the Electricity Regulation Act, 2006 (Act No. 4 of
2006) Determination.” (8 December 2016)
– record volume
5A p
1566.
[21]
Round Robin
Resolution n 20 p
1570
para 6.1.
[22]
C Hoexter
Administrative
Law in South Africa
2
nd
ed (2012) at p 547: ‘An invalid act, being a nullity, cannot
be ratified, “validated” or amended’.
[23]
[2008] ZACC 17
;
2009 (1) SA 417
(CC) para 61-
64.
[24]
Kruger
n
23 para 62.
[25]
See in this
regard
SARFU
n
4 para 227-231.
[26]
Durban
Add-Ventures Ltd v Premier, KwaZulu-Natal, and Others (No 2)
2001 (1) SA 389
(N) at 400C-D.
[27]
Round Robin
Resolution n 20 p
1568-1570.
[28]
Burger v
Rand Water Board and Another
2007 (1) SA 30
(SCA) para 7.
[29]
Tlouamma
and Others v Speaker of the National Assembly and Others
2016 (1) SA 534
(WCC) para 159.
[30]
2009 (2) A
466 (CC).
[31]
See in this regard
Mohamed
and Another v President of the Republic of South Africa
and Others (Society for the Abolition of the Death Penalty in South
Africa and Another Intervening)
[2001] ZACC 18
;
2001 (3) SA 893
(CC);
Kaunda
and Others v President of the Republic of South Africa and Others
2005 (4) SA 235
(CC);
Geuking
v President of the Republic of South Africa and Others
2003 (3) SA 34
(CC);
National
Commissioner of Police v Southern African Human Rights Litigation
Centre and Another
2015 (1) SA 315
(CC
);
Krok and Another v Commissioner, South African Revenue Service
2015
(6) SA 317
(SCA); and
Minister
of Justice and Constitutional Development and Others v Southern
African Litigation Centre and Others
2016 (3) SA 317
(SCA).
[32]
Kruger
n
23 paras 20–23.
[33]
1986 (4) SA 358 (D).
[34]
Ibid
at
364C-D.
[35]
Kruger
n
23 paras 20 – 23.
[36]
2016 (3) SA 580
(CC) paras
22-24.
[37]
2012 (4) SA 618
(CC) para 92.
[38]
1999 (2) SA 279
(T) at
329J-330C.
[39]
See
Kaunda
and Others v President of the Republic of South Africa and Others
2005 (4) SA 235
(CC) para 78.
[40]
2011 (3) SA 347 (CC).
[41]
Mohamed
n
32
paras 70 and
71.
[42]
Media Release n 1 p 131.
[43]
J Dugard
International
Law – A South African Perspective
4
th
ed (2011) p 417.
[44]
N Botha ‘Treaty making in
South Africa: A reassessment’ (2000) 25 South African Yearbook
of International Law 69 p
77-78.
[45]
Professor
Botha goes on to state at p 77 that: ‘
Ideally,
this decision should lie outside of the party negotiating the
treaty. Without in any way impugning the integrity of these
decision-makers, one must question the wisdom of a process in terms
of which the party who negotiated a treaty at the same time
decides
on its nature and therefore on the way in which it will be dealt
with by parliament. There is, after all, a considerable
difference
between an agreement being subjected to parliamentary approval (with
the possibility of rejection which this process
holds) and the mere
tabling of a provision in both houses which, although allowing an
opportunity for debate and criticism, is
in the final instance no
more than a process of notification of a
fait
accompli
.
The provisions of sec 231(2) imply a democratisation of the treaty
process unprecedented in South African law before 1993. In
terms of
this section, the individual citizen has,
through
parliamentary representation, at least as much say in what treaties
will bind the Republic as he or
she
has
in
what laws will govern his or her life. It would appear that by
failing to specify the instance which must decide on the nature
of a
treaty, section 231(3) holds the potential for the manipulation of
the system and the undermining of this democratisation
in a very
real sense.’
[46]
See
Matatiele
Municipality and Others v President of the RSAand Others (No 2)
[2006] ZACC 12
;
2007
(6) SA 477
(CC) para 36-37 where Ngcobo J stated,
‘
Our
Constitution embodies the basic and fundamental objectives of our
constitutional democracy. […] Individual provisions
of the
Constitution cannot therefore be considered and construed in
isolation. They must be construed in a manner that is compatible
with those basic and fundamental principles of our democracy.
Constitutional provisions must be construed purposively and in
the
light of the Constitution as a whole. […] Any construction of
a provision in a constitution must be consistent with
the structure
or scheme of the Constitution.’
[47]
Glenister
n
41 para 89.
[48]
Allpay Consolidated
Investment Holdings (Pty) Ltd and Others v Chief Executive Officer,
South African Social Security Agency and
Others
2014
(4) SA 179
(CC) para 30.