Abrahamse v Mobile Telephone Networks (Pty) Ltd and Others (21134/2015) [2016] ZAWCHC 186 (26 October 2016)

80 Reportability
Administrative Law

Brief Summary

Administrative Law — Review of administrative action — Application to review and set aside the City of Cape Town's decision to grant Mobile Telephone Networks (Pty) Ltd consent to construct a telecommunications base station — Applicant contending that his objections were not adequately considered, violating principles of procedural fairness under the Promotion of Administrative Justice Act 3 of 2000 — Court finding that the City failed to notify the applicant of the decision and did not consider all objections, rendering the decision procedurally unfair — Application granted.

Comprehensive Summary

Summary of Judgment


Introduction


The matter concerned an application for judicial review brought in terms of the Promotion of Administrative Justice Act 3 of 2000 (PAJA). The applicant sought to review and set aside decisions of the City of Cape Town that enabled the construction of a freestanding telecommunications base station in Morningstar, Philadelphia, Western Cape.


The applicant was Michael Bruce Abrahamse, the owner and resident of a property adjacent to the proposed base station site. The first respondent was Mobile Telephone Networks (Pty) Ltd (MTN), the telecommunications operator seeking to construct the base station. The second respondent was the City of Cape Town, the municipal authority that processed and approved the relevant applications. The third respondent was Mariza Delilan Cloete, the owner of the property on which MTN intended to construct the base station.


Procedurally, MTN’s land use application was approved by the City in March 2015 and became final after an appeal process in April 2015. Thereafter a minor works permit was issued in terms of building regulation legislation, enabling construction without ordinary local authority building plan approval. The applicant, unaware that approval had been granted and that construction could proceed, only discovered the construction once it had commenced. He first obtained interim interdictory relief (granted by Fortuin J on 9 October 2015) preventing continuation pending the review, and then launched this review application in November 2015. MTN opposed the review; the City abided the court’s decision; the third respondent did not participate.


The general subject matter was whether the City’s approvals for a telecommunications base station were lawful and procedurally fair, particularly in light of the City’s handling of public objections and notification.


Material Facts


MTN identified a need to increase network capacity and improve coverage in the relevant area, and selected the third respondent’s property as the proposed site for a base station. During June 2013, MTN lodged a consent use application with the City under the applicable land use regime. The City published a notice calling for comments and objections, with a closing date of 27 January 2014.


Four objections were received, including one by the applicant. The objections broadly raised concerns about aesthetics, health, and diminution in property values. The City, however, forwarded only one objection to MTN for response, namely an objection by Ms Colleen Durston. MTN provided a detailed response to that objection, addressing health-related concerns, visual impact, and property value allegations.


The applicant did not receive a response to his objection and repeatedly sought updates from City officials, but received no reply. After MTN’s response to the Durston objection, the City’s Land Use Management Department prepared a report recommending approval with conditions. The City’s decision-maker provisionally approved the application on 19 March 2015. After an appeal process, the approval became final on 29 April 2015.


A material fact relied upon by the court was that the City’s report did not include the other objections (including the applicant’s), with the consequence that the decision-making structure was not made aware of the applicant’s objection or the concerns particular to him.


After land use approval, MTN submitted a building plan-related application under the building standards legislation. The City approved the application and issued a minor works permit, which exempted MTN from obtaining ordinary local authority approval for building plans for the construction. The applicant was not informed that the consent use application had been approved, nor that a minor works permit had been issued.


Upon returning from holiday, the applicant observed that construction had commenced on 28 August 2015, during his absence. He then obtained an interdict restraining MTN pending the review.


Certain facts were treated as undisputed in the sense that the parties accepted that the City’s decision constituted administrative action subject to PAJA. The critical factual deficiency identified by the court was not a dispute about whether objections existed, but the City’s failure to ensure that all objections (including the applicant’s) were placed before the ultimate decision-maker and addressed through the prescribed process.


The court considered the applicant’s circumstances to be materially distinct from those of Durston. The applicant’s property was adjacent to the site, and the base station would be situated approximately 30 metres from the applicant’s front door. The applicant’s objection included site-specific assertions about direct overlooking of his home and erf, the adjacency to a low vineyard (with vines about one metre high), and the base station’s asserted industrial character in a rural-residential context. The court treated these as features not contained in the Durston objection and as relevant to what information the City’s decision-maker ought to have had.


Legal Issues


The central legal question was whether the City’s decision to grant land use consent for the base station was reviewable under PAJA on the basis of procedural unfairness, specifically whether the City failed to comply with the obligations of a notice-and-comment process by not ensuring the applicant’s objection was considered by the decision-maker.


A related legal question was whether, having invited objections, the City created a legitimate expectation that objectors’ submissions would be considered and that objectors would be notified of the decision, and whether a failure to do so infringed the requirements of procedural fairness under PAJA and the City’s own regulatory framework.


A further issue arose as to whether the base station qualified as a structure warranting only a minor works permit under the relevant building legislation, and whether the court should decide that question to provide certainty for future cases. The court ultimately declined to make a substantive determination on this classification question due to the evidentiary position and the City’s non-participation on that aspect.


The dispute primarily concerned the application of law to fact under PAJA (procedural fairness requirements applied to the City’s decision-making process), together with an evaluative assessment of whether the applicant’s objection contained materially distinct content requiring separate consideration and whether the City’s omission was outcome-relevant for procedural fairness.


Court’s Reasoning


The court proceeded from the accepted premise that the impugned municipal decision was administrative action and therefore subject to PAJA. It emphasised that where administrative action materially and adversely affects rights or legitimate expectations, procedural fairness is required, including an opportunity to make representations and the proper consideration of those representations.


In assessing the applicable procedural obligations, the court referred to the City’s regulatory and policy instruments governing zoning and notifications. The court highlighted that the zoning and notification framework contemplated that objections received by the closing date, together with responses, were to be incorporated into a departmental report that would be submitted to the relevant municipal decision-making structure, and that objectors must be notified after a decision is taken. Against this framework, the court treated the City’s decision-making process as one in which all timeous objections should have been placed before the decision-maker and considered.


The applicant confined argument to procedural grounds, contending that the City was obliged to consider his objection and that the failure to do so rendered the decision procedurally unfair. He also emphasised that he was the most directly affected party due to proximity. MTN’s response was that the applicant’s objection was substantially the same as Durston’s, that MTN had responded comprehensively to Durston’s objection, and that it would have been unnecessary to consider and respond separately to what MTN characterised as a “copy and paste” objection. MTN relied on Caine Brothers v Development Tribunal for KwaZulu Natal for the proposition that a complaint about not being furnished a further document for comment did not necessarily establish procedural unfairness.


The court rejected MTN’s reliance on Caine Brothers as misplaced. It distinguished that authority on the basis that, in Caine Brothers, the party complaining of an audi violation had in fact been afforded multiple opportunities to be heard at different stages and in different fora. In contrast, on the court’s assessment of the facts in the present matter, the applicant’s objection was not considered by the municipal decision-maker at all, and the applicant was effectively not heard in the decision-making process.


While acknowledging that the objections overlapped in general themes, the court found that the applicant’s objection contained distinct features related to proximity, direct visual impact, and the particular relationship of the structure to the applicant’s home and land. The court reasoned that these distinctions meant the City’s decision-maker did not have all relevant information before it when it approved the application, particularly given that the report to the decision-maker omitted the applicant’s objection entirely.


The court further rejected the suggestion that it was permissible for an administrator to disregard objections because dealing with them would be monotonous or tedious. It reasoned that there were only four objections, and therefore forwarding and considering all of them could not reasonably be characterised as an undue burden. The court held that the official who screened the objections was required to pass all objections to MTN for comment and thereafter ensure that objections and responses were placed before the Council or its delegates for the ultimate decision.


On the notion of legitimate expectation, the court held that by calling for objections and reasons, the City created a legitimate expectation that objections would be considered by the relevant decision-making structure. The omission to consider the applicant’s objection therefore constituted a breach of procedural fairness and violated the audi alteram partem principle as applied within PAJA’s procedural fairness framework.


Regarding the minor works permit issue, the court noted that ordinarily its finding on the consent use decision would dispose of the minor works permit issue because the latter depended on the former. Although MTN requested a ruling to obtain certainty on whether such a base station could be authorised via a minor works permit, the court declined to decide the point. It reasoned that the City was best positioned to address the issue comprehensively, and since the City had elected to abide and did not provide evidence on the economic and social differences between the minor works permit route and the ordinary local authority building plan approval process, the court lacked sufficient information to make a considered determination. The court indicated that additional input from the City by affidavit would have assisted.


Outcome and Relief


The court reviewed and set aside the City’s decision of 19 March 2015 granting MTN consent to construct the freestanding telecommunications base station on the third respondent’s property.


Because the land use consent decision was set aside, the court held that the City’s decision to grant a minor works permit to MTN had fallen away.


The court ordered that the first and second respondents pay the costs of the application jointly and severally, with the one paying the other to be absolved.


Cases Cited


| Case | Citation |
|---|---|
| Grey’s Marine Hout Bay (Pty) Ltd & Others v Minister of Public Works & Others | [2005] ZASCA 43; 2005 (6) SA 313 (SCA) |
| Brashville Properties v Colmant | [2014] ZASCA 61 |
| Masethla v President of the Republic of South Africa and Another | [2007] ZACC 20; 2008 (1) BCLR 1 (CC) |
| Walele v City of Cape Town & Others | [2008] ZACC 11; 2008 (6) SA 129 (CC) |
| Caine Brothers v Development Tribunal for KwaZulu Natal | (471/2015) [2016] ZASCA 81 (30 May 2016) |


Legislation Cited


| Legislation | Reference |
|---|---|
| Promotion of Administrative Justice Act | 3 of 2000 |
| Land Use Planning Ordinance | 15 of 1985 |
| National Building Regulations and Building Standards Act | 103 of 1977 |


Rules of Court Cited


No rules of court were cited in the judgment.


Held


The court held that the City’s approval of MTN’s land use consent application was procedurally unfair and therefore reviewable under PAJA, because the City failed to ensure that the applicant’s objection (and other objections) were placed before and considered by the decision-maker after the City had invited objections in a notice-and-comment process.


The court held further that, once the consent decision was reviewed and set aside, the minor works permit decision was not capable of standing independently and therefore fell away. The court did not make a definitive ruling on whether such a base station properly qualified for authorisation by way of a minor works permit, due to insufficient evidentiary material and the City’s non-participation on that aspect.


LEGAL PRINCIPLES


Procedural fairness under section 3 of PAJA requires that administrative action materially and adversely affecting rights or legitimate expectations must be procedurally fair, which includes affording affected persons a reasonable opportunity to make representations and requiring that those representations be duly considered by the decision-maker.


Where an administrator elects to follow a notice-and-comment procedure, the administrator must consider timeous comments and objections received in response to the notice, and must comply with the prescribed procedures applicable to such public participation mechanisms. An authority that invites objections may, on the facts and applicable regulatory framework, create a legitimate expectation that objections will be considered and that objectors will be notified of the decision.


The audi alteram partem principle remains a central component of procedural fairness in administrative decision-making. A failure to place an affected person’s objection before the decision-maker, in circumstances where objections were invited and were required to be taken into account, constitutes a material procedural defect rendering the resulting administrative decision reviewable.


Reliance on precedent concerning the sufficiency of hearing opportunities must be context-sensitive. A case in which a party was afforded multiple opportunities to make representations is not authority for the proposition that a decision-maker may omit to consider an objection altogether in a separate process where the objector was not heard.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Western Cape High Court, Cape Town
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2016
>>
[2016] ZAWCHC 186
|

|

Abrahamse v Mobile Telephone Networks (Pty) Ltd and Others (21134/2015) [2016] ZAWCHC 186 (26 October 2016)

SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case No: 21134/2015
In
the matter between:
MICHAEL
BRUCE
ABRAHAMSE
Applicant
and
MOBILE
TELEPHONE NETWORKS (PTY)
LTD
First
Respondent
THE
CITY OF CAPE TOWN
Second

Respondent
MARIZA
DELILAN
CLOETE
Third
Respondent
Court:
Canca,
AJ
Date
of Hearing:
18
August 2016
Date
of Judgment:
26
October 2016
JUDGMENT
INTRODUCTION
1.
This
is an application brought in terms of the provisions of the Promotion
of Administrative Justice Act, 3 of 2000 (“PAJA”).

The purpose of the application is to obtain an Order reviewing and
setting aside the decision of the second respondent to:
(a)
grant
the first respondent consent to construct a freestanding
telecommunications base station (“the base station”)
on
the third respondent’s property; and
(b)
grant
the first respondent consent to construct the base station by way of
a minor works permit.
2.
The
decision to grant the consent referred to in 1(a) above was taken in
terms of the Land Use Planning Ordinance 15 of 1985 (“LUPO”)

and the permission in 1(b) was granted in terms of the National
Building Regulations and Building Standards Act, 103 of 1977 (the

“NBR Act”) and its Regulations.
3.
Apart from
determining whether the relevant provisions of PAJA have been
complied with, a determination of whether the base station
qualifies
as a building warranting only a minor works permit might also be
called for.
4.
The first
respondent opposes the application.  The second respondent has
elected to abide the Court’s decision.
The third
respondent has not filed any papers and both she and the second
respondent were not represented at the hearing of this
matter.
THE
PARTIES
5.
The
applicant, Michael Bruce Abrahamse, an adult male businessman,
resides at 45 […], Morningstar, Philadelphia, Western
Cape
(“the applicant’s property”).
6.
The first
respondent, Mobile Telephone Networks (Pty) Ltd (“MTN”),
a company duly registered and incorporated in terms
of the company
laws of South Africa, is a well-known international mobile
telecommunications company, head-quartered in this country.
7.
The second
respondent is the City of Cape Town (“The City”), a
metropolitan municipality established in terms of South
Africa’s
municipal laws and the authority tasked with granting the permits
referred to in paragraph 1 above.
8.
The third
respondent, Mariza Delilan Cloete, is an adult female businesswoman
who resides at 141 […], Morningstar, Philadelphia,
Western
Cape (“the subject property”).
BACKGROUND
FACTS
9.
This
application has its genesis in Morningstar, Philadelphia, on the West
Coast of the Western Cape Province, an area comprising
mostly of
agricultural small holdings where equestrian activities appear to
dominate.
10.
In summary,
the background of this matter is the following.  MTN, in order
to increase capacity and to improve voice and data
network coverage,
needed to construct a base station in the area.  It identified
the subject property as the most suitable
site.
11.
During June
2013, MTN lodged an application in terms of LUPO to The City for
consent to construct the base station on the subject
property.
A notice, in terms of section 2.2.1 of the Cape Town Zoning Scheme
Regulations, calling on parties in the area
who might be affected by
construction, to submit comments and/or objections was then published
by The City.  The closing date
for submission of such comments
and/or objections, with reasons, was 27 January 2014.
12.
Four
objections, including one from the applicant, were submitted,
together with reasons and comment.  The objections, in the
main,
centred around aesthetics, health concerns and an anticipated
diminution of property values in the area, should the application

succeed.  The City only forwarded one objection to MTN for a
response, namely an objection by Ms Colleen Durston (“the

Durston objection”).  MTN responded comprehensively to the
Durston objection. It is worth noting that the Durston objection

covered most of the three concerns referred to above.
13.
MTN’s
stance to the Durstan objection was that:
(a)
current
research on base stations had reached the point where scientists were
satisfied that base stations do not pose a threat
to health;
(b)
not only
was the height of the proposed antennae to be erected going to be
shorter than most trees in the area, but that, as the
antennae was a
lattice, it would be see-through.  Its visual impact would
therefore be reduced; and
(c)
there was
no evidence that base stations reduced property values.  On the
contrary, the property values might improve with
the subsequent
increased virtual accessibility, so the contention continued.
14.
The
applicant, having not had a response to his objection, followed up by
addressing a number of requests for updates on the status
of MTN’s
application with the relevant official at The City.  These
requests met with no response.
15.
On receipt
of MTN’s response to the Durstan objection, The City’s
Land Use Management Department prepared a report which
recommended
the approval of MTN’s application, with conditions. The City’s
authority tasked with considering and approving
the application
provisionally granted MTN the approval it sought on 19 March 2015.
Following an appeal process, the provisional
approval was declared
final on 29 April 2015.  However, because the Land Use
Management Department’s report did not
include the other
objections, the Council was not aware of the applicant’s
objection and his reasons therefor.  The
report that went to
Council did not include the concerns that were specific to the
applicant.
16.
MTN
thereafter submitted a building plan application in terms of the NBR
Act to The City for the approval of building plans for
the base
station.  That application was approved.  The official who
granted the approval, acting in terms of the authority
granted to him
by section 13(1)(6) of NBR Act and its regulations, gave MTN a minor
works permit.  A minor works permit exempts
the holder from
obtaining local authority approval for the building plans of a
construction.
17.
The
applicant, who had not received any response to his correspondence,
was unaware that the MTN application for the construction
of the base
station had been approved.  The City failed to inform him that
MTN’s application had been successful.
He also did not
know that the building plans for the construction of the base station
did not require local authority approval
due to the base station
having been considered a minor construction.
18.
On his
return from a holiday abroad with his family, the applicant, on the
morning of 28 August 2015, noticed that construction
of the base
station had commenced during his absence.  Shortly thereafter he
launched an application interdicting MTN from
continuing with the
construction pending this review.  That application was
opposed.  However, on 9 October 2015, Fortuin
J, granted the
applicant the relief he sought, with certain conditions.
19.
The
applicant then launched this application in early November 2015.
It is appropriate to first set out the statutory regime
underpinning
the issues for determination in this matter.  I shall, for the
sake of convenience, first deal with the legislation,
regulations and
policies which applied when The City considered the application to
construct the base station (“the consent
use application”).
THE
LEGISLATIVE FRAMEWORK
20.
It is not
disputed that the impugned decision is an administrative act and
falls to be decided in terms of the provisions of PAJA.

Administrative actions have been eloquently and clearly defined by
the Supreme Court of Appeal on several occasions.  The

definition need not be repeated here.  See
Grey’s
Marine Hout Bay (Pty) Ltd & Others v Minister of Public Works &
Others
[2005] ZASCA 43
;
2005
(6) SA 313
(SCA) at para
[21]
and
Brashville
Properties v Colmant
[2014]
ZASCA 61
at para
[11]
.
21.
Section
3(1) of PAJA states that administrative action, which materially and
adversely affects the rights or legitimate expectations
of any
person, must be procedurally fair.  In order for the
administrative action to be considered procedurally fair, the

administrator, subject to certain conditions, must, in terms of
section 3(2)(b) of PAJA, afford the person so affected, or where

legitimate expectations have not been met, a reasonable opportunity
to make representations.  Such representations must, obviously,

be duly considered by the appropriate authority.
22.
Section
2.2.1 of the Cape Town Zoning Scheme Regulations, promulgated in
terms of section 9(2) of LUPO in November 2012 (“the
zoning
regulations”), state the following ‘
The
City Manager shall cause an application submitted in terms of the
zoning scheme to be advertised if, in his or her opinion,
any person
may be adversely affected by the proposed development’.
23.
Clause
6.3.2 of The City’s Policy (for) Cellular Telecommunications
Infrastructure (“the Telecommunications Policy”)
provides
that public participation should be “
in
accordance with the provisions of Council’s Public
Participation Policy for Land Use and Development Applications”
.
24.
In terms of
clause 2.3.3 of The City’s Notification Policy for Land Use
Development applications (“the Notification
Policy”), The
City may, where an application affects the public, call for a public
enquiry or follow a notice and comment
procedure or both, as provided
for in section 4(1) of PAJA.
25.
Where a
notice and comment procedure is followed, section 4(3) of PAJA
requires the administrator to, amongst others, consider any
comments
received and to comply with the prescribed procedures to be followed
with regard to notice and comment.  The aforementioned

prescribed procedures are contained in clause 2.3.4 of the Zoning
Regulations.  In summary, clause 2.3.4 of the Zoning Regulations

states that, on considering an application for approval in terms of a
zoning scheme, The City shall take into account any comments
or
objections received before the closing date in response to an
advertisement of the application and any existing rights.
26.
The
Notification Policy referred to in paragraph 24 above, also states
that:

3.5.1  Any
person has the right to submit comments or object to the proposal …

3.6.1
Comments and/or objections and the applicant’s response to
these are incorporated into a departmental report
which is submitted
for a decision to the relevant council decision-making structure …
3.6.2   …
3.6.3
After a decision has been taken by the Council or its delegates, the
applicant and the objectors (if any) must
be notified of the
decision.
3.6.4   …
3.6.5   …
…”
27.
Having
sketched the regulatory provisions applicable to the consent use
application, it now remains for me to consider whether,
based on the
law, there is merit to the applicant’s prayer that the consent
use application should be reviewed and set aside.
28.
It is trite
that our law requires decision-makers to act fairly towards those
affected by their decisions. See
Masethla
v President of the Republic of South Africa and Another
[2007] ZACC 20
;
2008 (1) BCLR 1
(CC) at para 183. Jafta AJ (as he then was) in
Walele
v City of Cape Town & Others
[2008] ZACC 11
;
2008
(6) SA 129
(CC) at 144B held that
:

The most
important component of procedural fairness is the one expressed by
the audi alteram partem principle (the audi principle)
which requires
that parties to be affected by an administrative decision be given a
hearing before the decision is taken …”
The
learned Judge then went on to state that the right to be heard is
based on “….
the negative impact of the decision on
the rights or legitimate expectations of the person claiming to have
been entitled to a hearing
before the decision was taken.”
29.
The
applicant attacks The City’s decision to grant the consent use
application on a number of fronts.  However, Mr Felix,
for the
applicant, during argument limited the attack to the procedural
aspects of the decision.  Firstly, he contended that,
having
followed the notice and comment procedure, The City had a duty to
consider the applicant’s objection, given the peremptory
nature
of the applicable regulatory regime.  Furthermore, unlike the
other objections, the applicant’s objection was
unique, given
the proximity of the base station to his property, making the
applicant the most directly affected party, so the
submission
continued.  The City’s failure to have considered the
abovementioned objections, particularly the one from
the applicant,
was procedurally unfair and, consequently, falls foul of PAJA and the
City of Cape Town’s own regulations
and policies, Mr Felix
contended further.
30.
MTN’s
response is that the applicant’s objection was exactly the same
as that of the Durstan objection which it had
considered and
responded to.  Therefore, it would have been “
monotonous
and tedious
[for
it to]
consider
something which does not bring any different aspect or new version”
,
particularly given that the applicant’s objection was a “
mere
copy and paste”
of the Durstan objection, so the submission went. The applicant was
not prejudiced by MTN only having considered and responded
to the
Durstan objection, as his views were captured by Durstan and thus,
they were considered and addressed by both MTN and The
City, so the
argument continued.  Mr Mokhari SC, for MTN, relied on
Caine
Brothers v Development Tribunal for KwaZulu Natal
(471/2015)
(2016) ZASCA 81
(30 May 2016) at paras 14 – 15, for
this rather novel argument.
31.
The
objections are indeed similar in several respects.  However, the
Durstan property is not as close to the base station as
that of the
applicant and her objection lays a lot of emphasis on the possible
side-effects of exposure to the electromagnetic
field emissions by
cellular base stations on the health of equines in the area.
Furthermore, regarding the issue of aesthetics,
the visual effect of
the base station and the mast will be more severe on the applicant’s
property, where he already has
a house.  Ms Durstan’s
objection states that “
The
mast area as shown on the applicant’s
[MTN]
drawing,
is directly opposite to the site of my proposed building”
.
So, it would appear that, unlike the applicant, Ms Durstan does not
yet have a building/homestead on her property and therefore
possibly
has the luxury of getting her architect to redesign her house or to
move its intended location such that the visual impact
of the base
station and mast does not negatively affect her view.  She
complains that the base station and mast will restrict
her view of
Table Mountain.  A further distinguishing feature of the
applicant’s objection is set out, in part, as follows
in his
objection:

The applicant
himself/herself [MTN] has provided the layout plan which clearly
shows that the mast directly overlooks the Objector’s
entire
home and erf.  The rectangle indicated in the applicant’s
drawings of the Objector’s front yard is directly
adjacent to
the site of the proposed mast.  The rectangle is in fact a small
vineyard, with the average height of the vines
being approximately
one meter.  The mast measures some 15 metres in height (the
equivalent to a 3 to 4 story building).

.
No matter what the
colour
[of]
the
structure, it will not blend with the surrounding area.  The
structure will still appear as an industrial-type installation

totally out of place in a rural-residential area.”
This
information is not contained in the Durstan objection which would
indicate that The City’s Council did not have all the
relevant
information before it when it took the decision to grant the consent
to construct the base station.
32.
The
applicant’s property is adjacent to the subject property.
The base station would be situated approximately 30 metres
from the
applicant’s front door.  According to MTN’s
application, the base station will consist,
inter
alia
,
of the following:
(1)
a
15-meter-high lattice mast,
(2)
3 MTN Omni
Antennae attached to the mast,
(3)
one
microwave dish attached to the mast,
(4)
a MTN
container and
(5)
a 2.4 meter
high palisade fence enclosing the base station.
In
addition, MTN also sought permission that the base station be
constructed such that MTN could in future install 6 panel antennae
(3
per future user), place 2 associated equipment containers (1 per
future user) and to install 3 microwave dishes. The rationale
for
this being MTN’s intention to share the base station with other
users at some time in the future.
33.
The
applicant was not, unlike Durstan, that concerned about the possible
side-effects of exposure to electromagnetic field emissions.
In
fact, the applicant states that he “
accepts
all the information offered by
[MTN]
under
[the]
heading
[Health
Issues]
however
studies are still on-going and nothing is conclusive at this stage”.
Regarding the diminution in property values concern of the objectors,
the proximity to the applicant’s property to
the base station,
and its situation next to the vineyard with one metre high vines (not
trees of equal or greater height), its
unsightliness might well
override the benefits of increased virtual accessibility and result
in reduced property values.
The fact that only one of the four
objections were considered by the Council might have given the
impression that the other adjacent
property owners were not concerned
about the unsightliness of the base station and mast and the possible
negative effect these
structures would have on the values of the
properties that were in close proximity to them.
34.
In his
Heads of Argument, after citing
Caine
Brothers
supra,
Mr
Mokhari states the following:

in this matter
[Caine
Brothers]
applicant
argued that the audi alteram partem principle had been violated in
that it had not been given an opportunity to be heard,
the SCA held
that “the fact that the amended plan was not furnished to it
[Caine Brothers] for comment is of no moment. ....
The high court
correctly found that the decisions were not reviewable on the ground
of procedural irregularity.”
What
Mr Mokhari, however, does not convey in his Heads of Argument, is
that the applicant in
Caine Brothers
had been heard on
more than one occasion and in different fora.  It is also
unhelpful to quote the judgment out of context.
Paragraph 14
starts with Lewis JA stating:

From the brief
history of the matter that I have traced, it is immediately apparent
that Caine Brothers was given more than a fair
hearing at every stage
of the process.  Mr Dickson and Mr Caine made representations at
every opportunity.  The fact
that the amended plan was not
furnished to it for comment is of no moment.  The request by the
tribunal for the plan and amended
conditions of establishment, and
the decision that followed on it, was precisely to take account of
the objections made by Caine
Brothers and others.  The amendment
was as a result of the hearings that were afforded to Caine
Brothers.  And the appeal
tribunal afforded Mr Dickson,
representing it, yet a further opportunity to put its case,
adjourning the proceedings so that he
could furnish a second set of
heads of argument.”
35.
It is
obvious from the above that reliance on
Caine
Brothers
in this application is misplaced.  The facts in this matter are
completely different to those in
Caine
Brothers
.
The applicant was simply not heard nor was his objection considered
by the Council.  That violated the
audi
alteram partem
principle.
It is not for an administrator, merely because he or she considers a
task to be “
monotonous
and tedious”
and
in his or her view, “
does
not bring
[a]
different
aspect or new version”
,
to shirk his or her duty to consider all objections.  In any
event, there were only four objections and therefore, considering
all
four objections could never be said to be “
monotonous”
or

tedious”
work.  The official who screened the objections was duty bound
to pass on to MTN, for comment, all the objections and most
certainly
that of the applicant.  Whatever response MTN would then have
given should thereafter have been forwarded to The
City’s
Council for an ultimate decision as to whether or not to grant the
application.   As a directly affected
party, the
applicant’s objection should have been considered by The City.
The City’s regulatory provisions are
peremptory. Having called
on persons who might potentially be affected by the installation of
the base station to submit objections
or comment, with reasons, The
City created a legitimate expectation in the minds of the objectors
that they would be heard and/or
that their objections or comments
would be considered by The City’s Council or its delegates.
See paragraphs 25 and
26 above.
36.
In the
light of the above, I am persuaded that The City’s decision to
approve MTN’s application stands to be reviewed
and set-aside
as having been procedurally unfair.
37.
Ordinarily,
this finding would have trumped the second relief sought by the
applicant as the grant of a minor works permit was dependent
on a
successful application for the base station.  However, when I
raised this point with counsel during argument, Mr Mokhari
requested
that I rule on this aspect as well as such a ruling would give
certainty to MTN and The City as to whether a base station
such as
the one planned in this matter only required a minor works permit.
I then asked counsel for written submissions on
the benefits, if any,
derived from obtaining a minor building works permit for an
installation such as the one planned.  I
thank counsel for these
submissions.
38.
I have
re-considered making a ruling on this aspect of the matter. Mr Felix,
correctly, contended that it was only the second respondent
who was
in a position to comprehensively address the issue. Having merely
elected to abide this Court’s decision, I have
no evidence, nor
was any offered, that when MTN asked that I provide certainty to both
it and The City, or that The City is, in
fact, interested in such
certainty. Although MTN has, in broad terms, set out the benefits, in
cost and time, of a grant of a minor
works permit for such a
construction, I am persuaded that, without the input by the second
respondent on the differences, economic
and social, between the grant
of a minor works permit and one granted via the local authority
process, I simply do not have sufficient
information before me to
arrive at a considered decision. It would have assisted me in making
a determination on this aspect of
the matter if MTN had requested The
City, notwithstanding it’s election to abide my decision, to
have deposed to an affidavit
with respect to this issue.
39.
In the
result, I order as follows:
(1)
The
decision taken by the second respondent on 19 March 2015 to grant the
first respondent consent to construct a freestanding
telecommunications base station on 141 […], Morningstar,
Zonnekus Road, (Reference number: 70168746), is reviewed and set

aside.
(2)
In light of
the finding in paragraph (1) above, the second respondent’s
decision to grant a minor works permit to the first
respondent has
fallen away.
(3)
The first
and second respondents are ordered to pay the costs of this
application jointly and severally, the one paying the other
to be
absolved.
---------------------------
CANCA,
AJ
Appearances
For
the Applicant
:
Adv J K
Felix
Instructed
by

:           Linzi
McHardy
Johan Victor Attorneys
Cape Town
For
the First Respondent   :
Adv WR Mokhari SC and Adv M Mtembu
Instructed
by

:           Mr
Maphakela
Mashiane, Moodley &
Monama Inc.
Sandton, Johannesburg