Phillips v Bradbury and Another (15570/2013) [2016] ZAWCHC 129 (10 October 2016)

78 Reportability
Land and Property Law

Brief Summary

Property Law — Neighbour disputes — Enforcement of development agreement — Applicant sought to compel first respondent to comply with a written agreement regarding property development and to rectify building works in contravention of title deed conditions — Applicant also sought to interdict further non-compliant construction and to review decisions by the City approving building plans — Court held that the first respondent's development contravened the agreement and title conditions, and granted the applicant's relief.

Comprehensive Summary

Summary of Judgment


1. Introduction


This was an opposed application in the Western Cape Division of the High Court, Cape Town, in which the applicant sought wide-ranging relief arising from the redevelopment of a neighbouring property in Bakoven on the Atlantic Seaboard. The proceedings combined claims for contractual enforcement and interdictory relief (including demolition and remedial work) with judicial review of municipal decisions approving building plans.


The parties were Ms Christine Phillips (applicant), the owner of an erf adjoining the development site, Mr David Stuart Bradbury (first respondent), the developer and owner of the redeveloped property, and the City of Cape Town (second respondent), which had granted various planning departures and approved building plans. The dispute was rooted in an agreement concluded between the first respondent, neighbouring owners (including the applicant), and the local ratepayers’ association, under which neighbours would not object to certain planning departures in exchange for development restrictions secured partly by registered title deed conditions.


The application was launched in September 2013. It initially sought orders compelling the first respondent to bring the structure into conformity with the agreement and associated plans, interdicting further non-compliant work, and reviewing and setting aside the City’s approval of building plans (with an extension of time under PAJA). In February 2014 the applicant amended the notice of motion to add a review of an earlier set of plans approved in April 2010, again coupled with a request for condonation/extension under PAJA.


During the hearing, the applicant sought a referral of disputes of fact to oral evidence, which was refused (with reasons), though the court left open the possibility of renewing the request. The court also conducted an inspection in loco immediately before argument. The first respondent brought a counter-application seeking removal of a timber screen erected on the applicant’s balcony, alleged to be unlawful.


The general subject-matter of the dispute concerned the legal consequences of material deviations from agreed development plans and registered title conditions; the appropriate remedy where a dwelling has been built substantially differently from an earlier agreement; the availability of specific performance in the form of demolition; and whether the City’s approvals could be reviewed and set aside under PAJA despite substantial delay.


2. Material Facts


Before redevelopment, the first respondent’s property contained a dwelling, a separate single garage with a flat roof, and a swimming pool. In approximately 2008, he applied to the City for approval of plans for a new dwelling. The property was then subject to the City’s zoning scheme regulations (as published in Provincial Gazette 4649 of 29 June 1990), including a “scenic drive” provision (section 93) intended to preserve views from Victoria Road, and a height restriction of 6 metres above finished ground level (section 98(4)(b)). The property was also subject to pre-existing title conditions, including a building frontage/setback requirement from Victoria Road and side streets.


It became clear by November 2008 that the proposed development would contravene the scenic drive provision and would exceed the 6-metre height restriction. The first respondent therefore began a process—through his town planner—of engagement with neighbours and the Camps Bay Residence Ratepayers Association (CBRRA) to secure support for required departures.


This process culminated in a written agreement dated 9 July 2009 between the first respondent and affected parties including the applicant and the CBRRA. The agreement’s core exchange was that the neighbours and the CBRRA would not object to the departure applications, in return for the first respondent’s undertaking to develop the property in a manner acceptable to them and in accordance with plans incorporated into the agreement (“the agreed plans”). The agreement provided, among other things, for restrictions on height above mean sea level, non-trafficable flat roofs, restriction to a single dwelling house, and that certain restrictions would be registered against the title deed by notarial deed. It further provided that the first respondent could not deviate without written consent of affected parties and that variations had to be in writing and signed by all parties.


The agreed plans contemplated a dwelling with basement, ground, and upper levels, with particular setbacks intended to reduce intrusion on the applicant’s privacy. They provided for retention of the existing garage and garden configuration and included stepped setbacks (including a 6-metre setback on parts of the upper level) and a “kink” in the western wall alignment influenced by the retained garage.


In May 2011, five clauses of the agreement were incorporated into a notarial deed and registered as title deed restrictions, including an “envelope” limitation for future development, restrictions on subdivision, and restrictions on use (private residential only).


The City granted a departure from the scenic drive provision in November 2009 in terms of LUPO, noting that neighbours had not objected. The City later granted a further departure on 9 April 2010 to permit exceedance of the 6-metre height restriction, describing it as a “technical” departure. Building plans dated November 2009 were approved by the City on 21 April 2010.


A key factual contention advanced by the applicant (and relevant to her case as framed) was that the November 2009 plans upon which departures were granted and the April 2010 approval was based differed from the agreed plans, including changes to the positioning/extent of the ground floor (removal of the “kink”), although still retaining some agreed features (such as setbacks and the garage). The judgment treated as common cause that the structure ultimately built was not in accordance with the agreed plans and that there were extensive deviations, though the reasons and implications of those deviations were contested.


From September 2010, demolition and construction commenced. The relationship between the parties deteriorated, with disputes about construction impacts and, by April 2011, a dispute over a boundary wall position prompted the applicant to retain a land surveyor. This led to the applicant becoming aware that the building under construction was not aligned with approved plans, resulting in a City building inspector issuing a cease works order in relation to unauthorised work (a roof/pergola structure), which the first respondent ultimately demolished.


In May 2011, the applicant complained to the City that the building was non-compliant in several respects, including alleged absence of the 6-metre upper-level setback, concerns about a swimming pool and other deviations, and she sought access to approved plans. A protracted consultative process followed from December 2011 to May 2012, consisting of multiple meetings involving the applicant’s representatives, the first respondent’s professional team, and City officials. The first respondent submitted revised (“rider”) plans; the applicant and CBRRA objected; nevertheless, the City approved revised plans in July 2012 (“the 2012 plans”). These plans included, among other features, a new garage and a swimming pool.


By mid-July 2012, the applicant knew that the City had approved the 2012 plans and that the first respondent intended to build in accordance with them. The first respondent’s attorney wrote to the CBRRA and copied the applicant and her legal representatives, stating that if litigation was intended it should be served promptly. Despite ongoing disputes, the application was only launched in September 2013, by which stage the dwelling was close to completion. The first respondent obtained occupancy certificates in October 2013, shortly after the application was instituted.


The court found it common cause that the completed works materially deviated from the agreed plans, including (as framed by the judgment) ground-floor elements nearer than 4.5 metres to the boundary (including the new garage), first-floor elements nearer than 6 metres, the construction of a swimming pool and associated changes to the garden/lawn concept, and changes affecting roof/deck areas and privacy-related features. The first respondent’s evidence was that demolishing and rebuilding to the agreed plans would be extremely costly and extensive.


3. Legal Issues


The dispute required determination of both private-law remedial questions and public-law administrative review questions, as well as the application of legal standards to a heavily fact-specific building dispute.


On the private-law side, the principal legal issue was whether the applicant was entitled to specific performance of the 2009 agreement and corresponding title conditions, particularly in the form of a mandatory interdict compelling demolition and reconstruction to align the dwelling with the agreed plans, and whether further (negative) interdictory relief should be granted to prevent future non-compliant construction.


This aspect primarily concerned the application of legal principles (discretion as to specific performance) to the facts, and required a value judgment about fairness, hardship, prejudice, and the practical consequences of demolition.


On the public-law side, the central issue was whether the applicant could obtain review and setting aside of the City’s plan approvals (2010 and 2012) under PAJA, including whether the PAJA 180-day time bar should be extended under section 9(2) in the interests of justice. This required determination of whether delay was unreasonable, whether a full explanation for delay had been provided, the extent of prejudice, and an assessment of the applicant’s prospects of success on the merits of review.


That portion of the dispute involved questions of law (the effect of PAJA sections 7 and 9, and what constitutes “applicable law” under the building-plan approval regime), together with the application of those rules to the chronology and the applicant’s conduct.


A further issue arose from the first respondent’s counter-application: whether the applicant’s timber screen was unlawful and should be removed, which turned on the absence of produced approval and the court’s acceptance of the first respondent’s case that it was unauthorised.


4. Court’s Reasoning


Specific performance and demolition


The court treated it as settled that an order of specific performance is granted at the court’s discretion, exercised judicially on the facts, with the aim of preventing injustice. The court applied the approach described in Benson v SA Mutual Life Assurance Society, including that justice may require refusing performance where it would operate unduly harshly on the defendant, and that the remedy must accord with legal and public policy.


The court accepted that it had the power, in principle, to order demolition of non-compliant works, and referred to Trustees, Brian Lackey Trust v Annandale for the proposition that courts have a “natural aversion” to ordering destruction of economically valuable building works. Although that case concerned an encroachment onto a neighbour’s land, the court treated its discussion of neighbour-law considerations—reasonableness and fairness in resolving conflicting ownership interests—as relevant to the present context.


Applying these principles, the court considered the nature and degree of non-compliance, the reasons advanced by the first respondent, the prejudice to the applicant if specific performance were refused, the prejudice to the first respondent if demolition were ordered, the role and effect of the lengthy consultative process, and the applicant’s delay in instituting proceedings.


On the first respondent’s conduct, the court rejected as non-cogent the explanations offered for failing to comply with the agreement and title restrictions. It emphasised that the agreement required strict adherence to the agreed plans and barred deviations without written consent, and it characterised the explanation that it “did not occur” to the first respondent to disclose amended plans to neighbours as disingenuous. The court considered it difficult to avoid the conclusion that, having secured neighbour consent for departures on the basis of the agreement, the first respondent did not deal openly with affected parties when circumstances changed.


However, despite this critical view of the breaches, the court’s remedial analysis focused on whether demolition would be fair and equitable in all the circumstances. A central factual consideration was the cost and scale of demolition and reconstruction. The first respondent’s quantity surveyor estimated the cost of rebuilding to the agreed plans at approximately R6.2 million and described extensive associated works. The applicant placed a much lower estimate (about R1.041 million) before court, but the court found that estimate excluded consequential internal reinstatement costs (plumbing, electrical, kitchen, installations) that could not be ignored when assessing hardship to the first respondent. The court concluded it was not possible on affidavit to determine a precise figure, but it considered it highly unlikely the cost would be less than R2–3 million, which it regarded as very substantial.


The court also evaluated the likely incremental benefit to the applicant if reconstruction were ordered. It accepted that rebuilding to the agreed plans would probably afford greater privacy, but found no evidence that the improvement would be striking. It noted that the setback differences were often a matter of approximately 1.5 metres (6 metres versus 4.5 metres). It further considered that reconstruction could revive entitlements under the agreed plans that were not present in the as-built arrangement, such as a cantilevered awning/pergola structure on the upper level, which the applicant had strongly opposed when previously constructed and later demolished.


The court placed weight on the consultative process between December 2011 and May 2012. Although it found no formal variation agreement was concluded, it held that the applicant had “considerable input” into what became the 2012 plans and that this engagement produced compromises tending to alleviate privacy impacts (including planters and window design choices). The court regarded these negotiated outcomes as reducing the justification for the most drastic remedy.


Delay was treated as a significant discretionary factor. The court found that by mid-July 2012 the applicant knew the 2012 plans had been approved, knew they differed from the agreed plans, and knew the first respondent intended to proceed. The court accepted that the applicant experienced difficulty obtaining copies of plans, but found that she had sufficient knowledge to act much earlier and that living next door meant she could observe the ongoing construction. The court considered there was no reasonable justification for waiting some 14–15 months after July 2012 before launching proceedings, especially given that occupancy certificates were issued shortly after institution.


The court also considered a practical contradiction: the agreed plans could not be approved in their original form due to the City’s lawful road improvement line requirements affecting the east corner. In the court’s view, this undermined the coherence of compelling performance strictly to plans that could not be implemented without modification to satisfy municipal requirements.


Weighing these factors cumulatively, the court concluded that ordering demolition and reconstruction would be unduly harsh to the first respondent and would not yield corresponding meaningful benefit to the applicant. It therefore refused the applicant’s principal “positive interdictory” relief.


Negative interdictory relief and undertakings


Although the court refused broad future interdicts, it accepted that some of the applicant’s fears—particularly about the roof of the new garage becoming trafficable and about privacy-protecting planters—were not fanciful, noting that the garage roof had at one stage been clad with wooden decking before removal after objections.


The court recorded that counsel for the first respondent addressed these concerns through undertakings that could be made an order of court. The court considered it salutary to convert these undertakings into enforceable orders. Beyond those targeted protections, the court found the applicant had not established a sufficient basis to infer a likelihood of future construction in breach of the agreement or title conditions, particularly as the project appeared complete.


Review relief under PAJA: extension of time and merits prospects


The court treated the review relief as governed by PAJA section 7(1), requiring review proceedings to be instituted without unreasonable delay and within 180 days of knowledge or when knowledge ought reasonably to have been acquired. Because the applicant was outside that period for both the 2010 and 2012 approvals, the threshold question was whether time should be extended under PAJA section 9(2), which permits extension where the interests of justice so require.


Relying on the Supreme Court of Appeal’s articulation of relevant factors (as cited in Aurecon South Africa (Pty) Ltd v Cape Town City), the court considered the nature of the relief, the extent and cause of the delay, the impact on administration of justice and other litigants, the adequacy of the explanation covering the entire delay period, the importance of the issue, and prospects of success.


On the facts, the court found that the applicant was aware of the substance of the 2010 plans by at least April 2011 (through commissioning a planner’s report and engagement with City inspectors) and certainly by October 2011 when a full report identifying alleged deviations existed. Yet review of the 2010 approval was only sought in February 2014, representing a delay of years. Regarding the 2012 plans, the court found the applicant knew by mid-July 2012 of the approval and her objections, but did not bring the review by the end of January 2013 (the PAJA 180-day benchmark) and instead instituted proceedings in September 2013.


The court rejected the applicant’s primary explanation that she relied on the City as “guardian” of her interests, holding that it conflated the City’s duty to regulate compliance with approved plans with the applicant’s responsibility to enforce private contractual rights. Once approvals were given, the City was functus officio as to the approval decision (while still empowered to act against construction that was not in accordance with approved plans). The court accepted that the applicant had difficulties obtaining copies of plans, but held she had enough knowledge of the discrepancies early on and, in any event, could have obtained the record through timeous review proceedings. The court also noted that the issue about PAIA difficulties was raised late in reply, leaving the City without an opportunity to explain its approach, and that the applicant had been able to inspect City files by September 2012.


In assessing prospects of success on the merits, the court considered the applicant’s principal review grounds and found them weak. It held that a private agreement between neighbours does not constitute “applicable law” for purposes of section 7 of the National Building Regulations and Building Standards Act 103 of 1977 (NBRBSA), and that the City was neither obliged nor permitted to enforce such a private agreement when deciding to approve building plans. The court similarly found that the registered title deed conditions relied upon by the applicant were not “applicable law” in the relevant sense (distinguishing title conditions imposed under statutory planning instruments from those created by private agreement), and that in any event the relevant title conditions were registered only in May 2011 and could not have affected the 2010 approval.


The court further reasoned that building plans submitted in support of departure applications need not necessarily be identical to the plans later approved under the NBRBSA, because the departure and building-plan approval processes are distinct. It accepted the City’s position that where amendments do not affect the substance of the departure, requiring a fresh departure would be unsensible, and noted that if an authority intended to link a departure to a particular plan set, it could do so by imposing conditions under LUPO, which had not been done.


Regarding the note on the City file suggesting that the 2012 plans had “the approval of all the parties”, the court considered the explanation for the note unsatisfactory. However, it accepted evidence that objections had in fact been recorded and considered by the Building Control Officer, whose recommendation made clear that objections existed but that compliance requirements were nonetheless met. The court concluded that the note did not, on the facts as presented, justify setting aside the approval.


Finally, the court weighed prejudice and the importance of finality: construction was long complete, occupancy certificates had been issued, and granting condonation would expose the first respondent to substantial prejudice if the reviews succeeded. Taking all factors together, the court held it was not in the interests of justice to extend the PAJA period for the 2010 approval (by more than three years) or the 2012 approval (by approximately eight months beyond the 180-day outer limit). It therefore held that it had no authority to entertain the review applications without an extension and dismissed the review relief on that basis, referencing Opposition to Urban Tolling Alliance v South African National Roads Agency Ltd.


Counter-application and striking out


The City brought an application to strike out portions of the applicant’s replying affidavit as scandalous, vexatious, or irrelevant. The court found it unnecessary to determine that application given the outcome on the merits, but remarked critically on the excessive length of the replying affidavit and reiterated that an applicant cannot make out a case in reply, referencing the SCA’s remarks on prolixity.


In the counter-application, the first respondent sought removal of a timber screen erected on the applicant’s balcony as an illegal structure. The applicant asserted that the City had approved it but failed to produce approval despite a Rule 35 notice. The court accepted there was no basis to dispute the first respondent’s claim that the screen was unauthorised and ordered its removal.


Costs


Although the applicant failed to obtain substantial relief, the court differentiated between the first respondent and the City on costs. As to the first respondent, the court considered it inappropriate and unfair to award him costs given the court’s findings that he materially breached the agreement, failed to deal candidly with neighbours regarding deviations, and engaged in conduct that made it appear he “had his cake and ate it.” The court held that a costs award in his favour would send the wrong message in circumstances where neighbourly consent for departures had been secured by agreement and then materially disregarded. The court therefore ordered that each party bear their own costs as between the applicant and the first respondent, in both the main application and the counter-application.


As to the City, the court held it had been drawn into proceedings mainly by the review relief, and the applicant had failed in that relief. The court rejected the submission that the City should bear its own costs simply because officials participated in consultative meetings. It also held that the Theron note issue was insufficient to justify depriving the City of costs. The applicant was ordered to pay the City’s costs, including the costs of two counsel.


5. Outcome and Relief


The court granted limited relief against the first respondent by making specified undertakings an order of court, requiring him to retain the privacy-related features and to keep the garage roof non-trafficable. The remainder of the applicant’s application, including the demolition/specific performance relief, broader interdictory relief, and the review relief, was dismissed.


The first respondent’s counter-application succeeded, and the applicant was ordered to remove the timber screen on her balcony within one month, failing which the Deputy Sheriff was authorised to remove it.


As between the applicant and the first respondent, each party was ordered to bear their own costs in both the application and the counter-application. The applicant was ordered to pay the City’s costs, including the costs of two counsel.


Cases Cited


Benson v SA Mutual Life Assurance Society 1986 (1) SA 776 (A).


Trustees, Brian Lackey Trust v Annandale 2004 (3) SA 281 (CPD).


Aurecon South Africa (Pty) Ltd v Cape Town City 2016 (2) SA 199 (SCA).


MEC for Health, Eastern Cape and Another v Kirland Investments (Pty) Ltd t/a Eye and Lazer Institute 2014 (3) SA 481 (CC).


Opposition to Urban Tolling Alliance v South African National Roads Agency Ltd [2013] 4 All SA 639 (SCA).


Minister of Environmental Affairs and Tourism and Others v Phambili Fisheries (Pty) Ltd; Minister of Environmental Affairs and Tourism and Others v Bato Star Fishing (Pty) Ltd 2003 (6) SA 407 (SCA).


Legislation Cited


Promotion of Administrative Justice Act 3 of 2000.


Promotion of Access to Information Act 2 of 2000.


National Building Regulations and Building Standards Act 103 of 1977.


Land Use Planning Ordinance 15 of 1989.


Roads Ordinance 19 of 1976.


Townships Ordinance 33 of 1934.


Municipality of the City of Cape Town Zoning Scheme Regulations (Provincial Gazette 4649 dated 29 June 1990), including section 93 and section 98(4)(b).


Rules of Court Cited


Uniform Rule 53.


Uniform Rule 35.


Held


The court held that, despite material deviations from the 2009 agreement and the agreed plans, an order compelling specific performance by demolition and reconstruction would be unfair and inequitable in the circumstances. The court exercised its discretion to refuse demolition relief, primarily due to the disproportionate hardship and cost to the first respondent, the limited demonstrated marginal benefit to the applicant, the applicant’s substantial delay in instituting proceedings despite knowledge that the 2012 plans had been approved and would be built upon, and the practical difficulty that aspects of the agreed plans could not be implemented due to lawful municipal road line requirements.


The court held that the applicant was not entitled to the review relief because she failed to bring review proceedings within the PAJA time limits and did not show that extension of the 180-day period was in the interests of justice. The court further considered that the applicant’s merits prospects on review were weak because a private agreement and privately generated title restrictions did not constitute “applicable law” binding the City’s plan approval decisions under the NBRBSA, and because departures and building plan approvals are distinct administrative processes.


The court held that limited protective relief should nonetheless be granted by making certain undertakings enforceable: the first respondent was ordered to keep specific privacy-protecting features (including planters and a steel balustrade) and to keep the garage roof non-trafficable.


The court held that the first respondent’s counter-application succeeded and ordered the applicant to remove an unauthorised timber screen on her balcony.


On costs, the court held that it would be inappropriate for the first respondent to recover costs given his material breaches and conduct, and ordered each party to bear their own costs as between them. The court held that the City was entitled to its costs (including two counsel) because it was successful and should not be penalised for participating in consultative processes.


LEGAL PRINCIPLES


The judgment applied the principle that specific performance is not granted as of right but lies within the court’s judicial discretion, exercised to prevent injustice and to avoid results that operate unduly harshly on a defendant, with regard to legal and public policy considerations as articulated in Benson v SA Mutual Life Assurance Society.


In considering demolition as a form of specific performance or mandatory interdict, the judgment applied the consideration that courts show a natural aversion to ordering the destruction of economically valuable building works, and that in neighbour disputes considerations of reasonableness and fairness are prominent in determining appropriate relief, as discussed in Trustees, Brian Lackey Trust v Annandale.


The judgment applied PAJA’s requirement that review proceedings be instituted within 180 days and without unreasonable delay, and that an extension of time under PAJA section 9 depends on whether the interests of justice require it, assessed with reference to factors including the nature of the relief, the cause and extent of delay, the adequacy of the explanation covering the whole period, prejudice, the importance of the issue, and prospects of success (with reference to Aurecon South Africa (Pty) Ltd v Cape Town City).


The judgment applied the principle that administrative decisions (including departures) remain effective until set aside by a court and cannot be ignored simply because their background circumstances are disputed, consistent with the approach referenced from MEC for Health, Eastern Cape and Another v Kirland Investments (Pty) Ltd t/a Eye and Lazer Institute.


On municipal plan approvals under section 7 of the NBRBSA, the judgment applied that a local authority approves plans if satisfied of compliance with the Act and “any other applicable law,” and held on the facts and argument presented that private agreements between neighbours and privately generated title deed restrictions are not, for these purposes, “applicable law” that the municipality is required (or entitled) to enforce through the building plan approval function.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: Western Cape High Court, Cape Town
SAFLII
>>
Databases
>>
South Africa: Western Cape High Court, Cape Town
>>
2016
>>
[2016] ZAWCHC 129
|

|

Phillips v Bradbury and Another (15570/2013) [2016] ZAWCHC 129 (10 October 2016)

SAFLII
Note:
Certain
personal/private details of parties or witnesses have been
redacted from this document in compliance with the law
and
SAFLII
Policy
THE
REPUBLIC OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
(WESTERN
CAPE DIVISION, CAPE TOWN)
Case
No:  15570/2013
Before
the Hon. Mr Justice Bozalek
Hearing:
10 – 12; 16 – 17 May 2016
Judgment
Delivered:  10 October 2016
In
the matter between:
CHRISTINE
PHILLIPS

Applicant
and
DAVID
STUART
BRADBURY

1
st
Respondent
THE
CITY OF CAPE TOWN

2
nd
Respondent
JUDGMENT
BOZALEK J
[1]
The applicant in this
matter, Ms Christine Phillips (‘the applicant’) seeks
extensive relief against her neighbour,
Mr David Bradbury (‘first
respondent’) and the City of Cape Town (‘the City’),
as second respondent, arising
out of first respondent’s
development of a property on the Atlantic Seaboard at the corner of
Victoria and Beta Roads, Bakoven.
Applicant is the owner of an
adjoining property, Erf [...] , located in B. Road.
[2]
The primary relief
sought by the applicant is the enforcement of the provisions of a
written agreement concluded between her and
other neighbouring
parties on the one hand, and first respondent on the other, relating
to the development of his property and
to enforce certain title
conditions registered against the title deed of his property
consequent upon that agreement. In essence
the applicant’s case
is that first respondent developed his property, through the
construction of a dwelling house and other
features thereon, in
disregard of the agreement and the title deed conditions registered
pursuant thereto. The applicant seeks
in the first place an order
compelling first respondent to bring his building/s into compliance
with certain building plans as
provided for in the agreement and to
demolish and rectify those parts of the structure which do not comply
with the agreement or
which are in contravention of the title deed
conditions.
[3]
In addition the
applicant seeks an interdict against first respondent restraining him
from any further construction work on his
property which does not
comply with certain agreed plans or certain registered title deed
conditions.
[4]
Finally, the applicant
seeks an order reviewing and setting aside two decisions taken by the
City approving two different sets of
plans for the construction of
the dwelling on first respondent’s property (‘the review
relief’).
[5]
The application was
opposed by both respondents and has given rise to a voluminous set of
papers, in excess of 1000 pages, plus
the Rule 53 record comprising
approximately another 150 pages. The papers are replete with numerous
sets of building plans, closely
typed ‘
minutes’
of meetings,
correspondence, including numerous emails, and other annexures.
THE
PROGRESSION OF THE APPLICATION
[6]
Because of its
relevance to certain questions which arise it is necessary to set out
the sequence of the main steps in the application.
It was instituted
in September 2013 when the main relief sought was for an order that
first respondent take all steps necessary
to rectify the dwelling
house to bring it in accord with the terms of the agreement, the
plans provided for therein and the conditions
of the title deed, more
particularly:
1.
to demolish those parts
of the ground floor of the building situated nearer than 4.5 meters
from the common boundary with applicant’s
erf, in particular a
newly built garage;
2.
to demolish all
elements of the first floor of the building situated nearer than 6
meters from the common boundary with applicant’s
erf;
3.
to demolish a newly
built swimming pool on first respondent’s property and
reinstate what was garden area on the north and
north-western side as
a level grassed lawn at the pre-existing ground level;
4.
to reinstate the garage
as it previously existed on the property;
5.
to interdict first
respondent from any building work or construction on his erf which
did not comply with the original agreement
and associated plans or
which contravened any of the title conditions;
6.
to review and set aside
the City’s decision approving, in June 2012, certain building
plans in relation to first respondent’s
dwelling;
7.
to extend the period
referred to in sec 7(1) of the Promotion of Administrative Justice
Act, No 3 of 2000 (‘PAJA’) within
which the aforesaid
review could be brought.
[7]
In February 2014 the
applicant filed an amended notice of motion in which she sought
further relief, namely, the review of the City’s
decision
approving, in April 2010, certain building plans in respect of first
respondent’s dwelling and similarly extending
the time period
within such review could be instituted. This amended notice of motion
was supported by a supplementary founding
affidavit by the applicant.
COMMON
CAUSE HISTORY
[8]
Prior to the
redevelopment of first respondent’s property the improvements
thereon comprised a dwelling house, a separate
single garage with a
flat roof and a swimming pool built into the grounds of the garden.
In approximately 2008 first respondent
applied to the City for the
approval of plans to build a new dwelling on the site and detailed
building plans were submitted by
his representatives. His property
was subject at that time to the Zoning Scheme Regulations of the
Municipality of the City of
Cape Town zoning scheme, as published in
Provincial Gazette 4649 dated 29 June 1990 (‘the scheme
regulations’). His
property was further subject to existing
special title conditions including one which provided that:

(c)
he shall be obliged to set back all
such building to a line of building frontage….which
shall not
be less than 4.72 meters from the back line of the footway in
Victoria Road, or in the case of side streets marked on
the plan, not
less than 3.15 meters, so as to form a forecourt or garden in front
thereof…’
[9]
Section 93 of the
applicable scheme regulations comprised a ‘
scenic
drive’
provision preserving most of Victoria Road, on which his property was
situated, as a scenic drive. In essence the provision was
designed to
preserve the ocean views from Victoria Road by providing that roofs
of buildings on the side of the road closer to
the ocean could not be
higher than the curb on that side of the road. In addition sec
98(4)(b) of the scheme regulations restricted
the height of buildings
on first respondent’s property to 6 meters from the finished
ground level.
[10]
In November 2008 it
came to first respondent’s attention that the proposed plans
for redevelopment of his erf were in contravention
of sec 93 of the
scheme regulations and that he would have to apply for a ‘
departure’
from the regulations to ‘
permit
structures above the footway of Victoria Road’
.
He also became aware that a further departure from the scheme
regulations was required in that his proposed dwelling would exceed

the 6 meter height restriction applicable under sec 98(4)(b) of the
scheme regulations.
[11]
These intended
departures required first respondent to give notice thereof to the
owners of adjoining erven and the relevant ratepayers
association,
the Camps Bay Residence Ratepayers Association (‘the CBRRA’).
[12]
Through his town
planner, Mr T Brummer, first respondent commenced a process of
discussion and negotiation with those of his neighbours,
including
the applicant, affected by his proposed building plans and
departures, and with the CBRRA. It is common cause that first

respondent was seeking the consent of his neighbours and the CBRRA to
his application to the City for the requisite departures
from the
applicable scheme regulations with a view to facilitating the
execution of his proposed development. This process culminated
in a
written agreement on 9 July 2009 which made provision for first
respondent to seek the departures which he required without
objection
from his neighbours or the CBRRA. In exchange, the agreement
regulated the future development of his property in a manner

acceptable to all interested parties.
[13]
In essence the affected
parties, i.e. first respondent’s neighbours and the CBRRA,
would not object to the departures required
by him in consideration
for his undertaking to adhere to the agreement and build only in
accordance with the plans incorporated
in the agreement and an agreed
development proposal - some of which protections would be secured by
way of conditions to be registered
against the title deeds to first
respondent’s property.
[14]
In particular, the
agreement provided that the height of the proposed structure would
not exceed 23.4 meters above mean sea level,
all flat roofs would be
non-trafficable and covered in a non-reflective material, the
property would be restricted to a single
dwelling house and certain
clauses in the agreement would be registered as new title deed
restrictions in a Notarial Deed of
Praedial
Servitude against the title deed of erf [...] . The agreement further
provided that first respondent would not be entitled to deviate
from
the conditions contained in the agreement without the written consent
of the affected parties.
[15]
The plans incorporated
in the agreement, which I shall refer to as ‘the agreed plans’,
provided for a dwelling with
a basement level, a ground floor level
and an upper level. This was possible, in theory, without infringing
too greatly on the
scenic drive provisions relating to Victoria Road
because there is a relatively steep fall-off from that level towards
the sea
i.e. as one progresses down Beta Road in the direction of
applicant’s property. The applicant’s property is a
double
storey dwelling, facing north i.e. away from first
respondent’s property, and only just over 1.3 meters from the
boundary
with first respondent’s property. The first
respondent’s plans provided inter alia that the existing garage
would be
retained, there would be no swimming pool on the ground
level and there would be a level grass area in front of the lounge,
the
retaining wall of the basement and the ground level of the
building would be set back 4.5 meters from the boundary of the
applicant’s
property whilst the side walls and deck area on the
top level would be set back 6 meters from the same boundary i.e. they
would
be ‘
stepped
back’
to
ensure that the top floor was set back further from the boundary of
the applicant’s property. In addition, approximately
half of
the western wall of the dwelling (on the northern side) would be set
back towards Victoria Road  to accommodate the
existing garage
and maintain the set back from the common boundary. This produced a
so-called ‘
kink’
in that wall. Further, the deck on the top floor would be set back
4.5 meters from the boundary on the Beta Road side of the
development.
[16]
Five clauses in the
agreement were incorporated into a notarial deed which was registered
in the deeds office in May 2011. These
provided inter alia that the

envelope’
of the stipulated plans would define and limit any future development
on the property, that no further subdivision of the property
would be
permitted and that the dwelling house could only be used for private
residential use and not, for example, as a guest
house or bed and
breakfast establishment.
[17]
As far as the applicant
was concerned the proposed development reflected on the agreed plans,
in conjunction with the retention
of the existing garage and the
retention of the garden area, would ensure that the intrusion on her
privacy would be kept to a
minimum. In particular the existing garage
created a barrier behind which was first respondent’s main
outdoor entertainment
area, the top floor deck, with the result that
overlooking, noise and any other intrusion into her property was
minimised.
[18]
In October 2009 the
CBRRA wrote to the City confirming that five neighbours, including
the applicant had concluded an agreement
with first respondent
following ‘
extensive
consultative meetings’
held with the CBRRA and that ‘
no
objections were submitted by any of the affected parties’
.
Importantly that letter from the CBRRA gave no detail of the
agreement, nor did it include a copy thereof.
[19]
Approximately a month
later the City advised first respondent’s town planner that a
departure from the ‘
scenic
drive’
provisions of sec 93 of the scheme regulations had been granted in
terms of sec 15 of the Land Use Planning Ordinance, 15 of 1989

(‘LUPO’). The letter recorded that the scenic drive
departure had been circulated to neighbours and that no objection
had
been raised by them. It recorded further that the increase in the
height of the proposed dwelling would have no material impact
on the
scenic drive experience and that there were other double storey
houses in the area. The scenic drive departure was granted
by the
City in relation to certain building plans dated November 2009, as
its letter indicated.
[20]
Subsequently, on 9
April 2010, the City granted a further departure, this time to permit
points on the structure to exceed the 6
meter height restriction, in
terms of sec 98(4)(b) of the scheme regulations. The City’s
letter incorporating its decision
also referred to building plans
dated November 2009. It recorded that the proposed structure was 8.6
meters above the lowest point
on the finished ground level but that
the new dwelling would not be higher than the top of the roof pitch
of the existing house
and neighbouring property owners would not be
able to view more than the top 6 meters of the building due to the
fact that the
building’s basement level was below the surface
of the ground. The departure was therefore regarded as a ‘
technical’
departure having no impact on the character of the surrounding
environment.
[21]
A motivating memorandum
prepared by a City planning official recorded that the proposed
departure had not been advertised to neighbours
because they had
previously had no objection to the same structure when the scenic
drive departure had been considered and thus
no point would be served
by further advertisement.
[22]
Later that month, on 21
April 2010, the November 2009 building plans were approved by the
City. It is the applicant’s case,
however, that the November
2009 building plans, upon the basis of which the two departures were
granted were, unbeknownst to her,
different from the agreed plans in
that the positioning of the ground floor of the dwelling had been
amended and extended up to
the garage on the western corner of the
property (i.e. the ‘
kink’
had been removed) although they still provided for the building to be
set back from the boundary of applicant’s erf, retained
the
existing garage, made no provision for a swimming pool and retained
the garden.
[23]
In September 2010 first
respondent commenced with the demolition of the existing dwelling and
then the building phase. However,
the entire building project was
marked by unharmonious relations between the neighbouring parties.
The applicant complained that
first respondent failed to erect
certain screens prior to demolition, that contractors’ vehicle
obstructed access to her
property and that first respondent failed to
ensure effective dust and dirt control. Finally, a dispute arose over
the position
of a partly demolished boundary wall which led, in April
2011, to the applicant retaining the services of a land surveyor to
investigate
this dispute. Through him the applicant became aware that
the dwelling under construction was not built in accordance with an
approved
building plan. A building inspector in the employ of the
City issued a ‘
cease
works’
order
and gave first respondent notice that he must obtain approval for an
unauthorised roof or pergola structure. Ultimately first
respondent
demolished the offending structure.
[24]
On 3 May 2011 the
applicant complained in writing to the City that the proposed
dwelling was non-compliant with the approved plans
in that the set
back of 6 meters on the top floor level was absent, a swimming pool
being constructed was not set back 3.15 meters
from Beta Road, the
basement had not been constructed according to plan and nor had the
balcony. In addition, the applicant sought
from the City a copy of
the building plans ‘
as
had been originally approved’
.
In the meantime first respondent had submitted a rider plan to
regularise the construction on his property, but approval thereof
was
refused by the City. What followed was a lengthy period of engagement
between the applicant, her representative/s, first respondent
and his
representatives and representatives of the City in which process the
applicant sought to have her concerns regarding the
building under
construction addressed whilst first respondent sought to satisfy
these concerns and proceed with construction.
[25]
The process comprised
meetings, letters and inspections in what can be fairly described as
a consultative process. According to
the applicant no success was
achieved by this process. However, according to first respondent the
process yielded various concessions
on his part although not overall
agreement.
[26]
This consultative
process commenced in December 2011. It comprised seven meetings and
lasted until May 2012. In that month first
respondent submitted an
application for the approval of rider plans. Despite objections by
the CBRRA on behalf of the applicant
and other affected parties,
these were approved by the City in July 2012. Amongst other features,
they contained a proposed new
garage and swimming pool. By June 2013
the parties were still at loggerheads with applicant complaining to
the City regarding a
trafficable deck on top of the newly built
garage, the set back of the garage from her boundary wall, aspects of
the basement courtyard
and the set back from the Beta Road street
boundary. In September 2013 a new building plan submitted on behalf
of first respondent
was approved by the City. The applicant’s
attempts to obtain copies of the 2012 plan were, for a lengthy
period, unsuccessful
inasmuch as first respondent refused to furnish
a copy of the plans to her and the City required her to follow a
process of application
for information under the Promotion of Access
to Information Act, 2 of 2000 (‘PAIA’). The applicant
duly followed this
process but the City only provided the plans on 19
July 2013. In September 2013 the applicant launched the present
application.
THE
APPLICANT’S CASE
[27]
The case made out on
behalf of the applicant is that at all material times the City’s
planning officials were aware that she
and other affected parties did
not object to the two departures obtained by first respondent but
solely on the basis of his undertaking
that his property would be
developed strictly in accordance with the terms of the agreement
between the parties and in accordance
with the plans annexed thereto
(the agreed plans) and the title deed conditions registered in terms
of that agreement. However,
unbeknownst to the applicant those
departures were granted on the basis of building plans other than the
agreed plans i.e. the
November 2009 building plans which were
approved in April 2010, but which contravened the title conditions
applicable by virtue
of the agreement.
[28]
The applicant’s
case is further that she then relied on the City to address her
various concerns concerning the proposed building
project and to
protect her interests in that regard. To the extent that first
respondent’s dwelling was eventually built
in accordance with
building plans approved in 2012, the applicant relies on the fact
that despite her best efforts to obtain such
plans from first
respondent and the City, she only received these from the City in
July 2013. Similar considerations apply, as
far as the applicant was
concerned, to the building plans approved by the City in September
2013. Her case is further that first
respondent was well aware that,
absent an agreement, he had no right to deviate from the agreed plans
and, to the extent that he
had, he should be compelled to demolish
the non-compliant features.
[29]
As far as the review
relief sought by the applicant against the respondents, her case is
that inasmuch as the dwelling constructed
by first respondent is not
in accordance with the agreement and the agreed plans, she had
provided the City with a copy of these
documents in 2011 and thus it
must be taken to have been aware of its terms and conditions.
[30]
As regards the 2012
building plans approved by the City, the applicant’s case is
that, once again, it must have been aware
of the basis upon which the
departure from the scenic drive provision had been procured; inasmuch
as the 2012 plans did not accord
with those plans upon which ‘
assent’
to the departure had initially been procured, the City should not
have granted approval of the 2012 plans without requiring first

respondent to apply afresh for a departure from the scenic drive
provision and affording affected parties the opportunity to object

thereto. The applicant also avers that inasmuch as the dwelling
contemplated by the 2012 plan exceeded a height restriction on
its
western façade, on similar grounds a further departure
requiring a deviation from the height restriction was required,
with
a similar process embracing the affected parties before such
departure could be granted.
[31]
To sum up, the
applicant’s case is that given the basis upon which the initial
scenic drive provision and height departures
and approval of the 2010
plans had been procured, fair administrative action required that
prior to the approval of the 2012 building
plans by the City, first
respondent should have applied afresh for the two departures, that
the affected parties should have been
given notice of those
applications and an opportunity to object before any decision was
taken by the City. Instead, the applicant’s
case proceeds, the
decision was taken on the explicit basis that the application for the
approval of the plans enjoyed ‘
the
approval of all the parties’
.
[32]
Before dealing with the
further aspects of the applicant’s case, essentially responses
to defences raised by the respondents,
it is appropriate to set out
the basis upon which first respondent and the City oppose the relief
sought against them.
THE
FIRST RESPONDENT’S CASE
[33]
First respondent’s
answer to the case made out by the applicant is essentially a
confession and avoidance. He concedes, as
he must, the agreement
concluded between himself and his neighbours, including the
applicant, and that his dwelling was ultimately
constructed on the
basis of the 2012 building plans approved by the City and not in
accordance with the agreed plans. However,
he contends that the
applicant had extensive input into the 2012 plans prior to their
approval through the consultative process
mentioned previously. His
case is further that he advised the applicant that he intended to
build according to those plans timeously
in July 2012 and that
notwithstanding this notification the applicant only launched the
proceedings in September 2013 by which
stage first respondent’s
dwelling was almost complete. Thus first respondent relies in the
main, in relation to the review
relief, on unreasonable delays on the
part of the applicant as precluding the granting of such relief. As
regards the deviations
from the agreed building plans first
respondent relies on an exercise in his favour of the Court’s
discretion to grant or
refuse orders of specific performance.
Finally, as regards the interdictory relief sought first respondent
denies that he has any
intention of further construction on the site
in contravention of the agreement, the agreed plans or the title deed
conditions.
[34]
By way of explanation
for his deviations from the agreed plans first respondent testified
that after the approval of the scenic
drive departure in November
2009 and the submission of his building plans to the City for
approval, it advised him that the eastern
corner of his proposed
dwelling protruded over the relevant road improvement line and thus
had to be reconfigured. Accordingly
he submitted amended plans to the
City in April 2010 which differed from the agreed plans. This he did
because the ‘
loss’
of the eastern corner of the dwelling resulted in the loss of some
9m² of floor area per level of the dwelling. To compensate
for
this loss first respondent’s new plans extended the northern
portion of the west wall on the ground floor with the result
that it
was 1.5 meters closer to the applicant’s property on the ground
floor i.e. the ‘
kink’
was eliminated. Apart from the lopping off of the east corner of the
house on all three levels the only other major change was
that a
cantilevered roof structure over the outdoor deck on the top floor
which was shown on the agreed plans but was mistakenly
omitted from
the 2010 plans.
[35]
The only explanation
afforded by first respondent for not presenting the 2010 plan to the
applicant or the CBRRA was that it simply

did
not occur to him’
that these deviations had to be approved since the proposed dwelling
remained within the ‘
development
envelope’
as
set out in the agreed plans.
[36]
First respondent
commenced demolition of the existing dwelling in September 2010 and
proceeded to build in compliance with the 2010
approved plans save in
two respects: firstly, he constructed the concrete cantilevered
structure to serve as a pergola although
it was not reflected on the
2010 approved plans and secondly, he also constructed the west wall
of the top floor in a non-set back
position i.e. closer to the
applicant’s property. He gives no feasible explanation for
those non-compliant actions. Upon
receipt of a ‘
cease
works’
order
in April 2011, at the instance of the applicant, he submitted rider
plans to the City which were then the subject of objections
from the
applicant. Following unsuccessful attempts to obtain her acceptance
of these plans, first respondent abandoned them and
resumed
construction in accordance with the 2010 approved plans. This
entailed demolition of the ‘
wrongly
positioned’
west wall of the top floor and replacing it with a ‘
no
set back’
wall
which nonetheless offered the applicant greater privacy and for which
option she had expressed a preference.
[37]
It should be said that
any overall agreement at that point appeared to flounder on first
respondent’s refusal to agree to
pay quite substantial damages
to various neighbours and submit to other punitive clauses to be
incorporated in an agreement.
[38]
In November 2011 a
series of seven meetings commenced between himself and/or his
representative, the applicant and/or her representatives
and City
officials, which extended over a period of six months. At these
meetings building plans revised by first respondent were
presented,
the applicant conveyed her concerns there and then and these were
addressed via amendments to the plans. According to
first respondent
the applicant indicated, by the end of this process, that she was
happy with the features of the new plan. Once
again, however, no
formal agreement was reached, the stumbling block again being first
respondent’s refusal to accept what
appears to have been a
financial ‘
package’
similar to that which blocked an agreement the previous year and the
plans were duly submitted for approval to the City. Accordingly,
the
applicant objected to the plans and these objections were considered
by the City, which in July 2012, approved the plans. In
that same
month, shortly after the plans were approved, first respondent’s
attorney wrote to the CBRRA and the applicant
advising them of this
fact, further that first respondent intended developing his house
accordingly and that if those parties intended
litigating to set the
plans aside or to stop construction they should serve papers on him
expeditiously. First respondent then
proceeded to execute the
construction works. In September 2013, fourteen months later, the
applicant launched the present proceedings.
First respondent’s
certificates of occupancy were issued three weeks later, in October
2013.
[39]
In relation to the
positive interdictory relief i.e. the specific performance sought by
the applicant, first respondent’s
case is that there are good
and sufficient grounds for refusing a decree of specific performance
taking into account the hardship
to him if it is ordered, the absence
of prejudice to the applicant if it is refused and particularly her
delay in initiating these
proceedings.
[40]
As regards the
application for review relief, which clearly also affects first
respondent, his case is that it should be dismissed
on the basis of
the applicant’s unreasonable delay in bringing the
applications. In this regard reliance is placed on sec
7(1) of PAJA
requiring judicial review to be brought without unreasonable delay
and within 180 days after the administrative action
or the aggrieved
party becoming aware of it or when she ought to have become aware of
it. In regard to the 2012 approved plan first
respondent points out
that the application to review was only brought fifteen months after
the applicant became aware of the approval.
As far as the 2010
approved plans are concerned the delay was even lengthier, from April
2011 until such supplementary relief was
sought by the applicant in
February 2014. As regards the merits of the review relief, first
respondent aligned itself with the
substantive defences raised by the
City.
THE
CITY’S CASE
[41]
The City also relied on
what it considered were unreasonable delays on the part of the
applicant in launching her applications for
review relief.  In
the alternative, as far as the merits were concerned, the City
contended that the review applications were
misconceived in that they
were premised on the mistaken notion that the City had an obligation
to enforce the private agreement
between first respondent, the
applicant and other affected parties. It contended that it was not
permitted to take such agreements
into account when approving
building plans in terms of the National Building Regulations and
Buildings Standards Act, 103 of 1977
(‘the NBRBSA’) and
that in any event doing so would be an impossible task.
THE
APPLICATION FOR REFERRAL TO EVIDENCE
[42]
At the commencement of
argument the applicant sought to have certain disputes of fact
referred to evidence, notably:
1.
whether the
scenic drive and height departures granted by the City in respect of
first respondent’s property were granted
on the basis of the
agreement, more particularly whether the City was aware of the
agreement and its terms;
2.
whether there had been
any amendment of the agreement or the agreed plans, whether by any
consultative process or otherwise;
3.
whether the
applicant represented to first respondent that she consented to an
amendment of the agreement or the agreed plans.
[43]
The application for the
referral of these and other factual disputes was opposed by both
respondents and argued at length. In the
result the application was
refused with full reasons. I shall accordingly not traverse that
ground again save to record that my
ruling was that the application
should be declined at that stage but that it would remain open to the
applicant to renew the application
in respect of some or all of the
factual disputes raised. Thereafter full argument was heard on the
merits of the matter as set
out in the papers. I understood Mr
Bremridge, on behalf of the applicant, to persist with the
application for a referral to trial.
Nothing I heard in argument
served to persuade me that my initial ruling was wrong, namely, that
a referral to evidence of any
of the alleged disputes of fact would
not contribute to the fair and expeditious resolution of the matter
as a whole for reasons
which are either apparent from the ruling that
I made or which will appear from this judgment.
INSPECTION
IN LOCO AND PHOTOGRAPHIC EVIDENCE
[44]
On 10 May 2016,
immediately before the start of the hearing, all parties attended an
inspection in loco where salient features of
first respondent’s
property were pointed out as well as some on the applicant’s
property. In relation to first respondent’s
property these
included the position of the east corner of the house, the view from
that property towards the applicant’s
property and the position
of the west wall on the top floor, the ‘
contested
roof area’
and planter structures. On the ground floor the position of the

kink’
on the northern portion of the west wall (as built and as per the
agreed plans), the swimming pool, the new garage and its roof
were
pointed out. The garage is separated from the deck or patio by a
simple (detachable) iron balustrade and was covered by artificial

turf.
[45]
Photographs in the
record confirm that the two properties lie in a densely built up
area, Bakoven being close to the ocean and a
sought after residential
area. They indicate further that large multi-storeyed dwellings are
not uncommon in the vicinity of the
two properties. These factors
make it likely that most residents in the area will have to sacrifice
some aspects of their privacy
for the advantages of living there. The
photographs of the two properties, post development, show that they
are in quite close
proximity and that this would be exacerbated were
the roof of the garage on first respondent’s property to be
used as a trafficable
area. As it is the planter boxes on both the
garage and top deck are necessary to afford the applicant a greater
degree of privacy.
The applicant’s dwelling is itself
double-storeyed and hard up on the boundary with first respondent’s
property.
[46]
On the basement level
the position of the ‘
kink’
was shown (as per the agreed plans and as built) and the garage and
courtyard area and the vibracrete boundary wall were inspected.
The
position of the timber screen constructed from wooden poles erected
by the applicant on her property was pointed out.
[47]
Aspects pointed out on
the applicant’s property were: on the ground floor the view
from her garden towards first respondent’s
property and from
her bedroom at that level. On the first floor, the view from her
balcony towards first respondent’s property
and the position of
the screen on the applicant’s property which is the subject of
first respondent’s counter-application
were pointed out. As
photographs in the record indicated, persons on the ground floor and
top decks are visible from the applicant’s
balcony and vice
versa.
THE
POSITIVE INTERDICTORY RELIEF
[48]
It is common cause that
there are extensive deviations from the agreed plans in the building
works as finally completed. These include
elements of the ground
floor of the building situated nearer than 4.5 meters to the common
boundary with the applicant’s
property including the new
garage, elements of the first floor of the dwelling which are
situated nearer than 6 meters to the common
boundary with the
applicant’s property, the swimming pool structure which was not
provided for in the agreed plans and the
concomitant failure to
reinstate the garden are on the western and north western side of
first respondent’s property. That
these deviations from the
agreed plans are significant is borne out by evidence presented by
first respondent himself to the effect
that should specific
performance be ordered this would cost in the region of R6 249 480-00
and would involve demolition
of parts of the roof slabs and walls,
the swimming pool, the garage, the north west corner of the house and
north east corner of
the basement. The brickwork walls and concrete
structure would then have to be rebuilt, bigger windows installed on
the top floor,
the entire kitchen dismantled and rebuilt, plus a host
of other consequential work.
[49]
This figure was
disputed by the applicant as will be dealt with in greater detail
hereunder.
[50]
The first respondent
raises various reasons and justifications for the deviations in the
finished dwelling from that which was originally
provided for in the
agreed plans. These include his assertion that, upon discovering that
the north east corner of the planned
dwelling would be lost due to
the road improvement line and hence that he needed to ‘
recover’
this lost area by amendment of the plans in other respects and,
further, that it never occurred to him to submit these amended
plans
to the CBRRA or affected neighbours. Other grounds relied upon him in
this regard were that he regarded other amendments
to the building
plans as no more than rider plans which are customarily sought in
building projects where unforeseen amendments
to the original plans
are necessary. He also sought refuge in the extended nature of the
consultative process in which, in his
view at least, the applicant
was afforded a full opportunity to comment on the plans which
eventually became the 2012 approved
plans.
[51]
Although some of these
explanations may carry some weight, in my view, neither individually
nor collectively do they amount to anything
approaching cogent
grounds for first respondent’s failure to comply with the
provisions of the agreement and the registered
title conditions which
flowed therefrom. These provided, in clear terms, that he was to
build strictly in accordance with the agreement
and the agreed plans,
that he would not be entitled to deviate in any respect from the
conditions contained in the agreement without
the written consent of
the affected parties and that no alteration, cancellation, variation
or addition to the agreement would
be valid unless reduced to writing
and signed by all parties to the agreement.
[52]
Although first
respondent disavowed any dishonest intent it is impossible to escape
the conclusion that, having obtained the consent
of his neighbours to
the departures on the basis of the agreement, he deliberately avoided
playing open cards with the applicant
and other affected parties when
changing circumstances dictated that his building plans as originally
drawn up could or would not
be approved by the City. His explanation
that it simply did not occur to him to submit the amended building
plans to his neighbours
is, in my view, disingenuous to say the
least.
THE
QUESTION OF SPECIFIC PERFORMANCE
[53]
It
is well established, as was held in
Benson
v SA Mutual Life Assurance Society
[1]
,
that the granting of an order of specific performance is entirely a
matter of the discretion of the Court, which is to be exercised

judicially upon all the relevant facts. In that case it was said of
the discretion:

...It
is
aimed at preventing an injustice - for cases do arise where justice
demands that a plaintiff be denied his right to performance -

and the basic principle thus is that the order which the Court makes
should not produce an unjust result which will be the case,
eg, if,
in the particular circumstances, the order will operate unduly
harshly on the defendant. Another principle is that the
remedy of
specific performance should always be granted or withheld in
accordance with legal and public policy’
[2]
.
[54]
Whilst
there can be no doubt that it lies within the Court’s
discretion to order that the offending or non-complaint sections
of
first respondent’s building works be demolished, as was held in
Trustees,
Brian Lackey Trust v Annandale
[3]
a relevant factor is that ‘
there
is a natural aversion on the part of the Courts to order the
destruction of economically valuable building works.’
That
matter, it should be said, dealt with an encroaching structure in the
sense that the plaintiffs mistakenly built on a neighbouring
erf.
Also relevant to the present matter are Griesel J’s remarks in
that case regarding the principles of neighbour law which
fortified
his conclusion that a demolition order, as opposed to compensation,
would be an inappropriate remedy. The learned judge
stated:

I
am fortified in this conclusion by the rules and principles of
neighbour law, which place certain restrictions on the unencumbered

exercise of powers of ownership. Neighbour law is aimed at achieving
harmony in the relationship between neighbouring landowners
in the
case of conflicting ownership interests.  Considerations of
reasonableness and fairness are prominent factors in the

exercise of the Court's discretion in this field.’
[4]
[55]
In considering whether
to order specific performance regard must firstly be had to the
nature and degree of encroachment, in the
present case, the
non-compliance with the agreement and the agreed plans. It is also
appropriate to consider the extent to which
the applicant had any
prior notice of, or input into, the decision relating to those
particular elements of the building works.
ALL
ELEMENTS OF THE GROUND FLOOR OF THE BUILDING SITUATED NEARER THAN 4.5
METERS FROM THE COMMON BOUNDARY WITH THE APPLICANT’S
ERF,
INCLUDING THE NEW GARAGE
[56]
The agreed plans
indicated that the original garage would remain. According to first
respondent during the course of the construction
work, however, it
was discovered that it had no proper foundation, that its walls were
cracked and damp. and accordingly by December
2011 it was demolished.
In the first of the six consultative meetings first respondent
indicated that he intended to use the space
where the garage had been
as an open carport but applicant indicated that the resulting noise
and fumes adjacent to her property
would cause her inconvenience. At
a later meeting plans were presented on behalf of first respondent
showing a covered garage to
address these concerns. The applicant
was, however, concerned that the roof over the garage would be used
as a trafficable area
with the ensuing privacy problems. It was then
suggested that the roof be turned into a non-trafficable garden area.
A further
concern the applicant had was that a new garage wall on the
side of her property would damage existing trees as a result whereof

it was agreed to leave the existing wall intact and to build a new
wall, set back half a meter from the existing wall. In principle
it
would appear that this compromise was acceptable to the applicant but
an overall agreement could not be reached for lack of
agreement over
damages and/or penalties which the applicant, assisted by CBRRA,
demanded.
[57]
In the event the 2012
approved plans eventually provided for the closing of the area as a
covered garage and the positioning of
its west wall half a meter
inside the common boundary wall, leaving the existing boundary wall
intact and the rendering of the
garage as a non-trafficable garden.
The ultimate result is that although the existing garage was not
retained, a replacement garage
has been built albeit in a slightly
different position which probably affords the applicant less privacy
than was previously the
case.
THE
CANTILEVERED AWNING STRUCTURE OR PERGOLA
[58]
If first respondent’s
dwelling is rebuilt in accordance with the agreed plans, as the
prayer for specific performance envisages,
this will allow him to
build a cantilevered awning structure on the top floor of the
dwelling. This was initially built by first
respondent but because it
was approximately 300mm higher than was shown on the agreed plans, it
was ultimately demolished by him.
The applicant strongly objected to
that structure as originally built.
THE
EAST CORNER
[59]
As previously explained
the City required amendments to the original plans in relation to the
east corner of the proposed dwelling
so as to comply with road
improvement line requirements. This led to first respondent losing
approximately 9m² of dwelling
space on each of the three floors
on the proposed dwelling. Obviously any order for specific
performance cannot override the City’s
lawful requirements in
this respect and first respondent will either have to build the
truncated dwelling or fashion some other
compromise acceptable to the
applicant.
THE
NORTH SECTION OF THE WEST WALL – BASEMENT FLOOR AND GROUND
FLOOR
[60]
The agreed plans showed
that the north section of the basement and ground floors would be set
back by just over one meter more than
is now the case, producing a
kink in the west wall as a whole. As built in accordance with the
2012 approved plans there was no
set back because the pre-existing
garage no longer stood, the effect being that the external west wall
of these floors was closer
to the applicant’s property although
still 4.5 meters from the common boundary.
THE
NORTH PORTION OF THE GROUND FLOOR
[61]
On the agreed plans the
whole of the north area of the ground floor was depicted as a sitting
area linked to the main bedroom. However,
according to the 2012
approved plan, and as built, the area became an outside patio which
could be closed off on the west side
by louvered shutters and flowing
from a TV lounge with a brick wall on the west side.
THE
SWIMMING POOL
[62]
No swimming pool was
shown in the agreed plans but, in accordance with the 2012 approved
plan, a swimming pool, surrounded by a
deck, was built at ground
level between first respondent’s dwelling and Beta Road. In the
agreed plans the area in question
was depicted as lawn at a height of
17.45 meters above mean sea level. The new swimming pool appears to
have been built at 17.42
meters above mean sea level. The extent to
which it creates greater intrusion onto the privacy of the applicant
cannot be determined
since it will depend to a large extent on
whether the pool will generate more human traffic than if the grass
lawn had been retained.
THE
POSITION OF THE WEST WALL ON THE TOP FLOOR
[63]
The agreed plans
depicted the entire length of the west wall on the top floor set back
from the floor below so that it would be
6 meters from the common
boundary with the applicant. However, as built in accordance with the
2012 approved plans, the west wall
was not so set back so that there
was only a 4.5 meter set back from the boundary. The agreed plans
made provision for a large
picture window facing the applicant’s
property whereas the wall as constructed featured a ‘
non-overlooking
high level window sill above 1700mm’
in
order to minimise any overlooking and intrusion onto the applicant’s
property. First respondent also agreed to fit these
windows with
acoustic glass.
THE
CONTESTED ROOF AREA
[64]
The omission of the set
back of the north section of the ground and basement floors left
exposed an area of roof/floor slab to the
west of the top floor deck
which was referred to by the parties as the ‘contested roof
area’. The agreed plans showed
no such area. In the discussions
between the parties in 2011/12 the applicant’s concern was that
the area would be used as
a balcony adversely affecting her privacy.
First respondent’s response was to establish a planter box in
reinforced concrete
on that area wrapping around the north west
corner of the deck. This was duly constructed and renders the area
non-trafficable.
FACTORS
TO BE TAKEN INTO ACCOUNT IN CONSIDERING AN ORDER FOR SPECIFIC
PERFORMANCE
[65]
The following factors
appear to have relevance to the question of the exercise of the
Court’s discretion to order specific
performance:
PREJUDICE
TO THE APPLICANT IF SPECIFIC PERFORMANCE IS REFUSED
[66]
This aspect was treated
to a large extent as self-evident by the applicant who in her
founding papers contented herself with listing
the differences
between the applicant’s dwelling as depicted in the agreed
plans and later plans. It is clear, moreover,
that the poor
relationship between the parties which developed during the lengthy
demolition and building process as well as what
the applicant
considered were first respondent’s egregious and underhand
departures from the agreed plans were motivating
factors in her
seeking specific performance.
[67]
It is, however, also
clear that considerations of privacy with respect to noise, human
traffic and overlooking remained strong concerns
for the applicant in
seeking specific performance. There is, however, a lack of detail in
the applicant’s papers regarding
both the detail thereof and
setting out how the dwelling depicted in the agreed plans would serve
these interests better than the
dwelling as constructed. In this
regard it is relevant that, apart from the garage, the applicant’s
dwelling is at all points
4.5 meters from the common boundary. By
contrast the first respondent’s dwelling is just over 1.3
meters from the common
boundary. Although the applicant alleged that
her property had been devalued by the deviations no evidence in
support of this allegation
was tendered.
PREJUDICE
TO FIRST RESPONDENT
[68]
Mr JP Scannell, a
quantity surveyor commissioned by first respondent, estimated the
costs of carrying out the demolition and rebuilding
work necessary to
reconstruct the dwelling in accordance with the agreed plans at over
R6.2mil. This amount is contested by the
applicant who, at a late
stage herself filed an affidavit from a quantity surveyor, Ms M
Terblanche (‘Terblanche’),
estimating the cost involved
in the demolition of the disputed elements of first respondent’s
property. In Terblanche’s
estimate regard was had to demolition
of all elements of the ground floor nearer than 4.5 meters from the
common boundary (including
the garage), all elements of the first
floor nearer than 6mm from the common boundary, the swimming pool as
well as the reinstatement
of the former garage and former garden
area. In Terblanche’s opinion the total cost would amount to
R1.041mil.
[69]
Terblanche’s much
reduced estimate was attributable, inter alia, to her leaving out of
account any cost that first respondent
would incur in changes to the
internal layout of his dwelling such as the reinstallation of
plumbing, electrical, TV installations,
as well as the reinstalling
of the kitchen and air-conditioning. I fail to see why these costs
should not be taken into account
since it is not a question of

burdening’
the applicant with those costs (as Terblanche put it) but rather
taking into account the costs to first respondent should he have
to
reconstruct the dwelling according to the agreed plans. Part of doing
so would obviously involve him reinstating amenities such
as plumbing
and electrical installation which he enjoys in the dwelling as
presently constructed. It may well be that first respondent’s

estimate is exaggerated but it is not possible to determine solely on
the affidavits precisely what it will cost for the non-conforming

features to be demolished and reconstructed in accordance with the
agreed plans. In my view, however, it is highly unlikely to
be less
than R2-3mil which needless to say, is a very substantial sum.
[70]
A closely related
question is to what extent any prejudice suffered by the applicant
will be removed or alleviated should specific
performance be granted.
I am prepared to accept that the overall effect of reconstructing the
dwelling in accordance with the agreed
plans would be to afford the
applicant greater privacy but there is no evidence that this will be
by any striking margin. By way
of example an important element of the
applicant’s case was the pre-existing garage. A new garage has
been built, however,
albeit in not precisely the same location. The
roof of that garage will, by agreement, remain a non-trafficable
area.
[71]
Even if demolition is
ordered the dwelling will remain one with three levels, the top deck
overlooking the applicant’s property.
One concrete change will
be the areas of set back but these too will be limited to a question
of 1.5 meters  i.e. the difference
between portions of first
respondent’s property being 6 meters from the common boundary
as opposed to 4.5 meters.
[72]
In this regard too
account has to be taken of the fact that reconstruction of the
dwelling will, at least theoretically, entitle
first respondent to
erect the cantilevered concrete awning on the top floor, a feature
which he has foregone in terms of the present
dispensation.
PRIOR
NEGOTIATION BETWEEN THE PARTIES
[73]
As a consequence of the
extended series of meetings between December 2011 and May 2012 the
applicant had considerable input into
the detail of what eventually
became the 2012 approved plans and pursuant to which the dwelling was
eventually constructed. This
unquestionably had the effect of
alleviating the prejudice which the applicant suffered as a result of
first respondent ultimately
building in accordance with those plans
as opposed to the agreed plans.
[74]
The garage represents a
good example of the give and take between the parties. After
demolition of the existing garage first respondent
envisaged building
an open carport in its place but the applicant objected to the noise
and fumes which this would entail. Ultimately
agreement, or perhaps
more accurately a
quasi
a
greement, was
reached whereby the garage in its present form would be built. In
this context I hasten to add that there can be no
question of a
formal agreement ever having been reached regarding the
non-conforming features of first respondent’s dwelling.
The
papers do reveal, however, that ultimately what in all probability
prevented a formal agreement being reached was first respondent’s

refusal to undertake to pay substantial sums of money to affected
neighbours as a form of reparation or compensation for what was

considered by those parties and the CBRRA to be breaches of the
original agreement causing them harm.
[75]
The same series of
meetings produced other compromises which conduced to greater privacy
and non-intruding features for the applicant
such as the
establishment of the large planter boxes on the ground and top
floors. Another important compromise related to the
set back position
of the top floor where, in effect, the applicant ultimately elected
to have the non-set back position but with
higher windows.
[76]
Other compromises
related to the building by first respondent of a new boundary wall,
set back half a meter from the existing wall
in order to protect
certain trees on the applicant’s property.
DELAY
[77]
A further factor
relevant to the issue of specific performance is the late stage at
which the applicant initiated proceedings seeking
specific
performance. These were brought in mid-September 2013 but by mid-July
2012, fourteen months earlier, the applicant had
known that the City
had approved the 2012 plans, that these differed from the agreed
plans and that first respondent intended proceeding
with construction
in accordance with such plans. On 16 July 2012 first respondent’s
attorney had written to the CBRRA, with
copies to the applicant and
her attorney (and partner), advising them that the plans had been
approved and that his client was
intending to build in accordance
therewith. In that letter the CBRRA and interested parties were to
all intents and purposes invited
to litigate the matter since it
ended with the sentence ‘
should
the CBRRA and/or any other ‘affected party’ decide to go
the route of litigation nevertheless, you may serve
papers on us as
that would expedite matters’
.
The litigation referred to would have been to have had the plan
approval set aside or to stop the construction of the building
in
accordance with such plans.
[78]
Throughout the entire
construction process the applicant continued living next door and,
despite the presence of building screens,
can hardly claim to have
been unaware of ongoing construction, including its non-conforming
aspects.
[79]
In response to these
points the applicant emphasised that she looked to the City to
protect her rights vis-à-vis first respondent.
Secondly, she
relies on the difficulty which she had in obtaining copies of
approved building plans from both respondents. In regard
to the first
point, as will be fully discussed when the review relief is
considered, there was ultimately no basis in law for the
applicant to
rely on the City to enforce the provisions of the 2009 agreement. She
was entitled, as she did, to call upon the City
to intervene when
first respondent was building illegally i.e. not in accordance with
approval plans, in response to which the
City served a ‘
cease
works’
order
on him. This is a quite different proposition, however, to the
suggestion that she could in effect sit on her hands and expect
the
City to enforce her contractual rights vis-à-vis first
respondent.
[80]
As regards the second
point, there is in my view substance to the applicant’s
complaint that she was unable to obtain copies
of building plans for
long periods. However, by July 2012 or in the months immediately
thereafter the applicant knew that the City
has approved first
respondent’s plans, that these differed from the agreed plans
and that first respondent was intent upon
building in accordance with
the approved plans. It cannot be disputed furthermore that earlier,
through her commissioning of a
comprehensive report from Jakins, she
had become aware of deviations from the agreed plans by April 2011,
early on in the building
project. Furthermore, the applicant was
deeply involved in the details of the proposed construction by reason
of the extensive
interaction she and her team had with first
respondent and his team of professionals not least during the
consultative process,
together with the fact that she lived next door
to the property and could witness construction on a daily basis.
There is, in my
view, no reasonable excuse or justification for the
applicant’s failure to act for a further fourteen or fifteen
months before
launching in September 2013. The lateness of this date
is underscored by the fact that three weeks after the institution of
the
action first respondent received his certificate of occupancy for
the dwelling.
[81]
Yet a further factor to
be brought into account is the contradiction between the applicant
requiring first respondent to rebuild
in accordance with the agreed
plans and the fact that these plans could not be approved in their
entirety by the City. The agreed
plans were drawn up on the basis of
a road improvement line running parallel to first respondent’s
property in Victoria Road.
It was subsequently ascertained, however,
that the line ran parallel to the property’s boundary wall with
the result that
the eastern corner of his proposed dwelling, as per
the agreed plan, would have encroached over that line.
CONCLUSION
[82]
One cannot help feeling
a measure of sympathy for the applicant who concluded an agreement
with first respondent and on the strength
thereof believed, at least
for a period of time, that he would be building a dwelling in
accordance with the agreed plans only
to face material deviations
from that plan. From the applicant’s point of view at least,
she forfeited her right to object
to his application for the scenic
drive departure and possibly the height departure in return for
illusory benefits. That picture
is, however, by no means complete or
accurate. The title deed conditions remain in place and bind first
respondent and his successors
in title to various conditions which he
would otherwise not have been subject to as are set out in clauses
2.1 – 2.5 of the
agreement. Those include, amongst others,
restrictions on the use of the dwelling, on the erf’s
sub-division, provision for
the non-trafficability of all flat roofs
and a limitation on any future development to the envelope of the
plans, including right
of way servitudes.
[83]
Then also, as has been
set out earlier, the applicant had considerable input into various
decisions concerning aspects of the dwelling
and its surrounds with
the potential to infringe on her privacy albeit that this process
never culminated in a formal agreement.
There are in addition further
undertakings given by first respondent in the course of this
litigation to which I will refer later.
[84]
When all these factors
are taken into account, in my view an order for specific performance
would not be fair or equitable and would
work too hard upon first
respondent without any corresponding or meaningful benefits for the
applicant. For these reasons the applicant’s
prayer for
specific relief in the form of the demolition of the non-conforming
elements of the dwelling and the constructed property
as a whole
cannot succeed.
THE
(NEGATIVE) INTERDICTORY RELIEF
[85]
The applicant sought an
interdict against first respondent in future building other than in
compliance with the agreed plans or
the newly registered title deed
conditions. Her fears in this regard centred around the possibility
of first respondent using the
roof of the new garage as a trafficable
area as an extension of the outdoor entertainment area on the ground
floor. To my mind,
these fears were by no means far-fetched since at
one stage first respondent had clad the roof in wooden decking before
removing
it following objections from the applicant. A further
concern the applicant had related to the planter on the top floor
which provides
a barrier between the two properties vital to her
privacy.
[86]
First respondent’s
counsel ultimately addressed these concerns with undertakings by his
client which could be made an order
of Court. In my view making these
undertakings an order of Court will be salutary.
[87]
Over and above these
issues I consider that the applicant has failed to make out a case
that first respondent will build in breach
of the title deed
conditions or agreement. There is nothing in the papers to suggest
that first respondent’s plans or his
dwelling as a whole are
not completed projects. For these reasons, apart from the agreed
order, the applicant has failed to make
out a case for future
interdictory relief.
THE
REVIEW RELIEF
[88]
In her initial
application the applicant sought an order that the City’s
decision, taken on or about 1 June 2012, to approve
first
respondent’s building plans (‘the 2012 plans’), be
reviewed and set aside. The 2012 plans were in fact
approved on 12
July 2012. The applicant launched her application on 20 September
2013 and was thus looking to review plans which
had been approved
some fourteen months earlier. After the review record was filed by
the City in terms of Uniform Rule 53 the applicant
filed an amended
notice of motion in February 2014 in which she sought a further order
reviewing and setting aside building plans
which had been approved by
the City in relation to first respondent’s property on 21 April
2010, nearly four years previously
(‘the 2010 plans’).
The respondents raised a preliminary point that the applications had
not been brought within a
reasonable time as required by sec 7(1) of
PAJA. In both the original and the amended notice of motion the
applicant sought an
order in terms of sec 9(2) of PAJA extending the
date within which the applications for judicial review could be
instituted. Both
respondents opposed the application for an extension
and this point must be decided first.
[89]
Section
7(1) of PAJA requires that applications for the review of
administrative action be brought within a reasonable time but
no
later than 180 days after the date on which the person concerned was
informed of the administrative action, became aware thereof
or might
reasonably have been expected to become aware of these factors. The
test for an extension is set out in sec 9 which provides
inter alia
that a Court may extend the fixed period ‘
where
the interests of justice so require’
.
The Supreme Court of Appeal has held that whether an extension is in
the interest of justice depends on the facts and circumstances
of
each case
[5]
and that the
relevant factors ‘
generally
include the nature of the relief sought; the extent and cause of the
delay; its effect on the administration of justice
and other
litigants; the reasonableness of the explanation for the delay, which
must cover the whole period of delay; the importance
of the issue to
be raised; and the prospects of success’
.
[90]
Notwithstanding the
voluminous nature of the applicant’s papers the issue of the
extensions sought is not separately or crisply
dealt with therein.
Instead her case for the extensions must be gleaned from various
averments and explanations which she advances.
In the heads of
argument filed on behalf of the applicant it is stated that the 180
day period must be calculated from the date
upon which she could
reasonably be said to have become aware of the ‘
characteristics’
of the administrative action which she seeks to challenge. It is not
clear what this means. Argument then follows on the steps
which the
applicant took to protect her interests and rights through the
offices of the City which and culminate in the submission
that she
should not be prejudiced for having relied on the City she saw as a

guardian’
of her interests. In this regard reliance is placed on the long
consultative process in which the applicant and the respondents

engaged and also her difficulty in obtaining copies of the 2012 plans
which, she states, she only received in July 2013.
[91]
As regards the 2010
plans it is clear that from April 2011 the applicant was aware of
their contents at least as regards the salient
aspects thereof.
During that month she engaged a Mr Mark Jakins (‘Jakins’),
a planner who furnished her with a report
advising that first
respondent’s building works were not in compliance with
approved building plans and pointed out the illegal
works to the
City’s building inspector. By October 2011 Jakins had produced
a full report setting out what he considered
to be the deviations
from the approved plans. Accordingly the applicant was in a position
to review the 2010 plans by April 2011
or, at the latest, by October
2011. Instead she only took this action in February 2014.
[92]
As regards the 2012
plans it is common cause that by mid-July 2012 the applicant knew
that the City had approved those plans and
considered them flawed.
Using the bench mark of 180 days she was required to launch the
review of the approval of these plans by
no later than the end of
January 2013 but instead instituted proceedings in September 2013
approximately eight months after the
outer limit of the period. The
applicant stated that she had been advised at the commencement of the
construction work to seek
an interdict against him but had chosen not
to do so. It must also be borne in mind that at all stages the
applicant was legally
represented, either by her partner, himself an
attorney, or by an independent attorney whose services she engaged.
As mentioned,
as a result of her retaining the services of Jakins in
April 2011 and in due course receiving his comprehensive report, the
applicant
was in a position relatively early on, to identify the
discrepancies between the 2010 plans and the agreed plans. As regards
the
2012 plans, as a result of her participation in the meetings
between her representatives and those of the City and first
respondent
(as well as the CBRRA), over a period of months preceding
the 2012 approval she was aware of their contents and in a position
to
challenge them immediately. Accordingly she delayed for just short
of four years before seeking to review the 2010 approval and
for more
than a year before seeking to review the 2012 approval. Nonetheless,
the applicant did not provide an explanation for
the entire duration
of the delay.
[93]
Bearing in mind that
the reason for the delay rule is to ensure finality in administrative
decision-making, I turn to consider the
applicant’s first
reason for her delay, namely, that she thought the City would protect
her rights and interests in respect
of the allegedly unlawful
building works. This reason does not stand up to closer scrutiny,
however, since it impermissibly conflates
two separate issues: the
City’s duty to approve building plans and to ensure that these
are adhered to and her private law
or contractual rights which
remained her responsibility to protect or enforce. As was pointed out
by the City, once it had approved
the two sets of building plans it
was
functus officio
in that regard although, of course, as and when first respondent
failed to build in compliance with those building plans, it had
the
power and the duty to take action against him in that regard. The
applicant’s initial complaint was in respect of building
works
contrary to the approved building plans and the City duly issued a

notice to
obtain written approval for the unauthorised building work’
pursuant to which
the unauthorised building works were eventually demolished by first
respondent.
[94]
Secondly, the applicant
relied also on what she alleged was the City’s ‘
unwillingness’
to provide access to documentation, presumably a reference to the
building plans, unless compelled by a Court, contending that
this
made it difficult for her to ascertain the true facts and to protect
her position. However, although the applicant may have
had difficulty
in physically securing copies of the various sets of plans, she had
the information that both the 2010 and 2012
plans were not in
accordance with the agreed plans at relatively early stages and in
any event well within the 180 day period.
On the institution of a
review application she would have been entitled to obtain those plans
through her receipt of the record.
Further, as regards the
applicant’s reliance on this point, it must be borne in mind
that the applicant’s averments
that the City would not provide
a copy of the approved 2012 plans except in a response to a PAIA
request, were made in her replying
affidavit in response to first
respondent’s answering affidavit and therefore the City was not
on record with an explanation
as to the reasons for its approach in
this regard. There may well be legitimate reasons for the City’s
stance in not immediately
supplying copies of approved plans to
parties in the position of the applicant who was permitted and did in
fact gain access to
the City’s files by September 2012, as did
her land surveyor.
[95]
Other relevant factors
to consider are the nature of the relief sought and its effect on the
administration of justice and other
litigants. Where the relief is
the setting aside of approved building plans the importance of
timeous review action is particularly
pronounced since obviously the
plans are sought so that the applicant can commence construction work
in accordance therewith. One
of the consequences of a long-delayed
review is that, as in the present case, the construction work has
long since been completed
and the Court is asked to give an order for
specific performance in the form of demolition. Further in this
regard it would seem
that the purpose of the review relief is to meet
any argument that the allegedly offending portions of the
construction works are
lawful inasmuch as they have been built in
accordance with approved plans. In this sense the review relief is
academic if the applicant
is unsuccessful in obtaining an order for
specific performance.
[96]
This leads me onto
further factors which must be considered in exercising my discretion
in terms of sec 9(2), namely, the importance
of the issue to be
raised and the prospects of success. I accept that the issue is one
of considerable importance to the applicant
whose case it is that the
unauthorised building work materially detracted from her property
rights. However, I am doubtful of the
applicant’s prospects of
success for the review relief sought in respect of the 2010 and 2012
plan approvals, the basis of
which appears to be four grounds.
DIFFERENCES
BETWEEN THE APPROVED PLANS AND THE AGREED PLANS
[97]
In the first place the
applicant appears to contend that the 2010 and 2012 plan approvals
fall to be set aside on the ground that
these plans differ from the
agreed plans. It is put in the following way: the City was aware of
the agreement and, being so aware,
must be taken to have been aware
of the fact that the decision of the affected parties not to object
to the departure from the
scenic drive provision was conditional upon
and in exchange for the restrictions on developments stipulated in
the agreement, one
of them being that it would be built in accordance
with the agreed plans.
[98]
However, sec 7 of the
NBRBSA provides that a local authority shall approve building plans
if satisfied that the application complies
with the requirements of
that Act and ‘
any
other applicable law’
.
I do not understand it to be seriously disputed that ‘
applicable
law’
includes
the zoning scheme regulations and any conditions imposed in terms of
sec 42 of LUPO when approving a departure in terms
of sec 15 thereof.
In my view there is no warrant for contending that a private
agreement such as that concluded between the applicant
and first
respondent comprises ‘
applicable
law’
within
the meaning of sec 7 of the NBRBSA. One can readily imagine a private
agreement between neighbours which a local authority
would not be
prepared to countenance. Furthermore, there is also no justification
for the applicant to look to or to rely upon
the local authority, in
this case the City, to enforce any private agreement between her and
a neighbour. The City was not a party
to the agreement and cannot
reasonably be required to enforce it.
[99]
Notwithstanding
the lack of merit in this first ground it was developed further in
relation to the 2012 plans, namely, that to the
extent that those
plans differed from the agreed plans and given that the agreement had
been breached, the City should have required
of first respondent that
he apply fresh for the departures. However, as was pointed out on
behalf of the City, the difficulty with
this approach is that the
granting of departures is administrative action which stands until
set aside by a Court and therefore
the City could not simply
disregard the departures which it had granted to first respondent at
the inception of the building project
[6]
.
THE
APPROVED PLANS CONTRAVENED TITLE DEED CONDITIONS
[100]
It was further
contended on behalf of the applicant that the 2010 and 2012 approved
plans contravened title deed conditions registered
in May 2011
pursuant to the agreement and were therefore susceptible to review.
Once again, however, such title deed conditions
do not constitute

applicable
law’
and even
if the City had been aware of these discrepancies this would not have
entitled it to refuse to approve building plans
on this ground alone.
As was pointed out on behalf of the City, when it approves building
plans it indicates at the same time that
this does not absolve the
owner of the property from compliance with any conditions in the
property’s title deed.
[101]
A distinction must be
drawn here between title deed conditions imposed in terms of LUPO or
the Townships Ordinance, 33 of 1934 since
such conditions then do
constitute ‘
applicable
law’
for the purposes of sec 7 of the NBRBSA.  But that was not the
case in the current matter. In any event when the City
approved first
respondent’s 2010 building plan the title deed condition had
yet to be registered.
THE
APPROVED PLANS DIFFERED FROM THE DEPARTURE PLANS
[102]
A further ground of
review relied upon by the applicant was that the approval of the 2010
and 2012 plans could not stand because
these plans differed from the
plans submitted with the application for departures which preceded
the building plan approvals. Departure
applications are considered in
terms of sec 15 of LUPO and with reference to the particular
departure being sought, however. It
is difficult to see that building
plans submitted for the purposes of obtaining a departure must
invariably be the same as those
in respect of which building plan
approval is sought since the two processes are different. It is
apparently for this reason that
applicants are routinely informed
that an approval of a departure does not guarantee approval of
related building plans sought
in terms of the NBRBSA. As the City’s
representatives pointed out, such an instance occurred in the present
case when first
respondent was required to amend his building plan to
take account of the road line in terms of the Roads Ordinance, 19 of
1976.
As was further pointed out, where such an amendment to the
building plans does not result in a change relevant to the departure

granted, requiring the applicant to seek a new departure would not be
sensible.  If it is intended to link a departure to
a particular
set of building plans that could have been achieved by imposing a
condition to that effect in terms of s 42 of
LUPO.  No such
condition was attached.
THE
CITY BELIEVED, MISTAKENLY, THAT THERE WAS AN AGREEMENT BETWEEN THE
NEIGHBOURS
[103]
Finally, in relation to
the 2012 approved plans, the applicant contends that they fall to be
set aside because a City official,
Mr Gonsalves, had conveyed false
information to his colleague, Mr Theron, who finally approved the
building plans. This false information,
the applicant contends, was
that the building plan application enjoyed ‘
the
approval of all the parties’
.
This was recorded in a note written by Theron on 12 July 2012 in
which he mentioned that Gonsalves had attended numerous meetings
with
all the parties concerned, over a lengthy period of time.
[104]
Both Gonsalves and
Theron denied under oath that any such communication had been made,
but neither official explained how this note
came to be written. The
only basis upon which the City can escape the implications of the
note is Theron’s claim that, in
any event, he did not make the
plan approval decision on the basis of the note’s contents
since they were not relevant to
the issues he was required to
consider in terms of sec 7 of the NBRBSA. He goes further to state
that, rather, he had regard to
the recommendation of the Building
Control Officer, a Mr Louwrens. In that detailed recommendation
Louwrens made it clear that
he was aware of objections from the CBRRA
to the approval of the plans, that he had considered them in his
evaluation of first
respondent’s application for approval of
the plans but had concluded that nonetheless they complied with the
provisions of
the scheme regulations and had accordingly recommended
its approval.
[105]
In the circumstances,
therefore, although I consider that Theron’s explanation for
his note is insufficient and unsatisfactory,
the conclusion cannot be
reached that, even if he had been misled by the note’s content,
that this alone invalidated his
approval of the 2012 plans.
[106]
Having regard to the
applicant’s grounds of review, both singly and cumulatively, I
consider that the prospects of success
in any review application,
should the extension of time be granted, are weak.
PREJUDICE
[107]
Finally, in considering
whether to grant the extensions sought account must be taken of the
prejudice suffered as a result of the
reviewing party’s
unreasonable delay. As previously mentioned the extension sought of
the time period within which to review
the approval of the building
plans is no mere academic question. First respondent has built in
accordance with both sets of plans
and the dwelling is long since
complete. The review proceedings were brought at such a late stage in
relation to the building work
completed in accordance with the plans
that occupancy certificates to the dwelling were issued to first
respondent but a few weeks
thereafter. Needless to say there will be
considerable prejudice to first respondent if the extensions are
granted and the review
applications were to succeed.
CONCLUSION
[108]
In my view when all
these factors are taken into account the only conclusion which can be
reached is that the applicant has failed
to show that it would be in
the interests of justice to extend the 180 day period, in the case of
the 2010 plans for a period of
over three years and, in the case of
the 2012 plans, for a period approaching eight months.
[109]
Having concluded that
the applicant is not entitled to the extensions which she seeks the
Court has no authority to entertain the
application insofar as the
review relief. See in this regard
Opposition
to Urban Tolling Alliance v South African National Roads Agency Ltd
[2013] 4 All SA 639
(SCA) para 26.
THE
STRIKING OUT APPLICATION
[110]
Second
respondent applied to strike out numerous sections of the applicant’s
replying affidavit on the grounds that the contents
were scandalous,
vexatious and irrelevant. In the view that I take of the matter as a
whole, however, I find it unnecessary to
deal with the application.
Nonetheless it is appropriate to record that the applicant’s
replying affidavit which runs to
more than 450 pages, was well over
double the size of the already bulky founding papers. It goes without
saying that an applicant
cannot make his/her case in reply and
prolixity at that stage is generally counter-productive
[7]
.
THE
COUNTER-APPLICATION
[111]
The first respondent
brought a counterclaim for the removal of a timber screen on the
applicant’s first floor balcony on the
grounds that it was an
illegal structure. Despite claiming that she had the City’s
approval for the screen, the applicant
failed to produce the
approval, notwithstanding a Rule 35 notice having been served on her
calling for production thereof. There
is nothing to gainsay first
respondent’s averment that the screen is unauthorised, illegal
and, given its unsightly nature,
it must be removed.
COSTS
[112]
Costs must now be
determined against the background of the applicant having failed to
obtain any substantial relief, either as set
out in her initial
notice of motion or as amended. Both respondents seek the costs of
the application including the costs of two
counsel.
[113]
A distinction must be
drawn between the two respondents. I deal firstly with first
respondent. He has succeeded in defeating the
applicant’s claim
and has succeeded in his (minor) counter-application. However, this
is essentially because, on balance,
I am persuaded that it would be
inappropriate to order specific performance in the form of demolition
of those elements of the
building work which do not conform with the
agreed plans and/or are in breach of the agreement reached between
the parties after
first respondent approached the applicant and
others with a view to them not objecting to his application for
departures.
[114]
As first respondent’s
counsel himself put it, the perception (I would put it more strongly)
that first respondent both had
his cake and ate it, that he ‘
got
it away with it’,
causes discomfort. On first respondent’s own version he failed
to adhere to the agreement in material respects. He effectively

played ducks and drakes with the applicant regarding the building
plans in respect of which he obtained approval from the City.
He
unilaterally decided, after being advised by the City that his
building plans would have to be amended in order to accommodate
the
road line, to regain the space lost through ‘
knocking
off’
the
eastern portion of his dwelling by pushing his house further out
towards the applicant’s in breach of the agreement both
in
respect of the set back and the kink. He demolished the existing
garage without seeking the applicant’s prior approval
and
similarly made major alterations in the design of the garden and
swimming pool. His excuse, in relation to this first infraction
(and
others) that it simply did not ‘
occur’
to him or his architect to advise the applicant or any other affected
party of the impact on his building plans of the road widening
line
and his further explanation that he did not consider these to be
material changes is, as I have said, to put it at its best,

disingenuous.
[115]
The applicant’s
case that the first respondent built in disregard of the agreement
and her rights thereunder without disclosing
his true intentions to
her and, in certain instances, initially without plan approval, has
substantially been made out or admitted
before the Court. In relation
to the 2012 plans, the applicant at least had the benefit of a
lengthy consultative process as a
result of which she was able to
secure certain ameliorative measures or concessions but, to my mind,
this does not absolve first
respondent of his breaches of the
agreement and the numerous infractions. In these circumstances I
consider that it would be unfair
and inappropriate were first
respondent to be awarded an order of costs against the applicant, his
immediate neighbour, who has
borne the brunt of his cavalier approach
to the entire building project.
[116]
An order of costs in
favour of first respondent would send a wrong message that,
notwithstanding the breach of such agreements concluded
with
neighbours, one may not only ward off specific performance in the
form of a demolition order, but also be rewarded with a
costs order
against the very persons whose cooperation was initially secured by
reason of that agreement and who have suffered
by reason of such
breaches and infractions.
[117]
For these reasons I
consider that the most appropriate award vis-à-vis the
applicant and first respondent is that each party
bears their own
costs in the application and counter-application.
THE
SECOND RESPONDENT
[118]
The position as regards
the City is somewhat different. It was drawn into these proceedings
by virtue of the review relief sought
in respect of the 2010 and 2012
approved plans. The applicant has similarly been unsuccessful in this
relief. On behalf of the
applicant it was contended that the City
should bear its own costs inter alia for the reason that its
officials had seen fit to
engage in meetings and various other
communications between the parties and also by virtue of applicant’s
case that she had
relied on the City to protect her rights. However,
as has been pointed out earlier, a distinction must be drawn between
those aspects
of the building works where the City was duty bound to
intervene (and did so) and those aspects where, once it had given
approval
for the various building plans, it was
functus
officio
and could
under those circumstances render no further assistance to the
applicant.
[119]
I do not consider that
because the City went out of its way, through its officials, to
engage in or facilitate the consultative
process, presumably in order
to assist the applicant, it should be mulcted in costs as a result.
[120]
Reliance was also
placed by the applicant’s counsel on the City’s conduct
in obliging the applicant to follow a lengthy
procedure under PAIA in
order to obtain information she sought, in particular in relation to
the 2012 approved plans. As previously
mentioned, this issue was only
really raised vis-à-vis the City in the applicant’s
replying affidavit thus giving
it no opportunity to justify the
procedure which it required the applicant to follow in order to
obtain a copy of the approved
plans. Furthermore, as previously set
out, to all intents and purposes the applicant already had the
necessary information and
was always able to inspect the City’s
files.
[121]
The applicant is
correct in noting that there was no satisfactory explanation by
Theron, the City’s decision-maker, why he
made the note
concerning the approval of all parties to the 2012 building plans.
That, by itself, cannot justify withholding a
costs order from the
City. There is much to be said for the City’s argument that the
matter was in essence a property dispute
between two neighbours in
which the applicant was perhaps not well-advised to have drawn in the
City. At the very least, by the
time that the City set out its case
in its answering papers, the applicant should have reconsidered her
position. Whilst I am sympathetic
to the applicant I find myself
unable to justify withholding a costs order from the City. In the
result the City will be awarded
its costs, including the costs of two
counsel.
[122]
In the result the
following order is made:
1.
The first respondent is
hereby ordered:
1.1
to retain the planter
on the west side of the top deck floor of his dwelling;
1.2
to retain the steel
balustrade which separates the ground floor of his dwelling from the
roof of the garage;
1.3
to retain the roof of
the garage as a non-trafficable area.
2.
The applicant’s
application for further relief against first and second respondents
is dismissed;
3.
The first respondent’s
counter-application is upheld and the applicant is directed to remove
the timber screen erected on
the east edge of the first floor balcony
of the dwelling on her property within one month of date hereof;
failing which the Deputy
Sheriff is authorised to take the necessary
steps to effect its removal;
4.
The applicant and first
respondent shall bear their own costs in both the application and
counter-application;
5.
The applicant is to pay
second respondent’s costs, including the costs of two counsel.
_____________________
BOZALEK
J
APPEARANCES
For
the Applicant:

Mr I Bremridge (SC)
Instructed
by:
Werkmans
Attorneys
For
the 1
st
Respondent:

Mr S Rosenberg (SC)
Ms
K Reynolds
Instructed
by:
Du
Plessis Hofmeyr Malan Inc
For
the 2
nd
Respondent:

Mr LA Rose-Innes (SC)
Ms
E van Huyssteen
Instructed
by:
Hayes
Incorporated
[1]
1986 (1) SA
776 (A).
[2]
Ibid a
At
783 C – E.
[3]
2004 (3) SA
281
(CPD).
[4]
Ibid
para [40].
[5]
Aurecon
South Africa (Pty) Ltd v Cape Town City
2016 (2) SA
199
(SCA) para [17].
[6]
See in this
regard
MEC
for Health, Eastern Cape and Another v Kirland Investments (Pty) Ltd
t/a Eye and Lazer Institute
2014 (3) SA 481
(CC) paras [97 – 105].
[7]
See in this
regard the remarks of Schutz JA in –
Minister
of Environmental Affairs and Tourism and Others v Phambili Fisheries
(Pty) Ltd
;
Minister
of Environmental Affairs and Tourism and Others v Bato Star Fishing
(Pty) Ltd
2003
(6) SA 407
(SCA) para 80.