City of Tshwane Metropolitan Municipality and Another v National Energy Regulator of South Africa and Others (2023-072548) [2026] ZAGPPHC 530 (8 June 2026)

75 Reportability
Administrative Law

Brief Summary

Electricity — Licensing — Review of Nersa decision to amend Eskom's electricity distribution licence — City of Tshwane sought to review and set aside Nersa's decision to include Mooikloof Mega City in Eskom's licensed area, asserting it fell within its own licensed area — Nersa's approval of the amendment challenged on grounds of legality and procedural fairness — Court held that Nersa's decision was unlawful and invalid as it failed to consider Tshwane's constitutional rights and obligations regarding electricity distribution within its jurisdiction.

Comprehensive Summary

Summary of Judgment


1. Introduction


The matter concerned an application in the High Court (Gauteng Division, Pretoria) to judicially review and set aside an administrative decision taken by the National Energy Regulator of South Africa (NERSA). The impugned decision, taken on 10 February 2023, amended Eskom Holdings SOC Limited’s electricity distribution licence to include within Eskom’s licensed area of supply the Mooikloof Mega City Development, to the extent that the development is situated on Farm Rietfontein 375-JR.


The applicants were the City of Tshwane Metropolitan Municipality and the City Manager of the City of Tshwane. The first respondent was NERSA, as the licensing authority under the electricity regulatory framework. The second respondent was Eskom Holdings SOC Limited, the beneficiary of the licence amendment. Additional respondents (the South African Local Government Association, the Minister of Electricity, the Minister of Mineral Resources and Energy, the Minister of Co-operative Governance and Traditional Affairs, and National Treasury) did not participate in the proceedings and did not appear at the hearing.


Procedurally, Eskom lodged its application to NERSA for a licence amendment on 25 March 2021. Tshwane became aware of the application only in March 2022, after NERSA invited public participation, and then participated in the public hearing process. NERSA nevertheless approved Eskom’s amendment on 10 February 2023. Tshwane brought review proceedings under section 10(3) of the National Energy Regulator Act 40 of 2004, read with section 31 of the Electricity Regulation Act 4 of 2006, and also invoked the principle of legality. The matter was heard on 16 April 2026 and judgment was delivered electronically on 8 June 2026.


The general subject-matter of the dispute was whether NERSA could lawfully extend Eskom’s licensed area to cover parts of Farm Rietfontein 375-JR forming part of the Mooikloof Mega City development, given that the Farm was already reflected in Schedule 1 of Tshwane’s distribution licence (subject only to an express exclusion for existing “legacy” Eskom customers at the time Tshwane’s licence commenced).


2. Material Facts


Historically, Farm Rietfontein 375-JR fell under the jurisdiction of the former Kungwini Local Municipality, which was later dis-established. In 2008, the area was transferred to the municipal authority of the City of Tshwane Metropolitan Municipality. These background jurisdictional facts were treated as common cause.


On 22 September 2011, NERSA granted Tshwane an electricity distribution licence. The Farm appeared in Schedule 1 to Tshwane’s licence as “1926 Rietfontein 375-JR”, which the judgment treated as encompassing the Farm, including subdivided portions. At the time of the granting of Tshwane’s licence, certain existing customers in the generally undeveloped area had historically been supplied by Eskom. Tshwane’s licence expressly excluded those existing Eskom-supplied customers by providing that customers supplied by Eskom (or another licensed distributor) at the commencement date were excluded from Tshwane’s licence. The judgment treated it as material that this arrangement resulted in a division: Eskom remained licensed for those legacy customers, while the balance of the Farm—predominantly undeveloped land—fell within Tshwane’s licensed area.


On 25 March 2021, Eskom applied to NERSA to amend Eskom’s distribution licence to include the Mooikloof Mega City development insofar as it related to portions of the Farm for which Eskom held no licence at that time. Tshwane only learned of Eskom’s application in mid-March 2022 through media reports and public consultation notices, and NERSA only officially informed Tshwane on 25 March 2022. Tshwane thereafter objected and participated in the process, including attending and presenting at the public hearing on 11 April 2022.


In its engagement with NERSA, Tshwane asserted that the Farm formed part of its licensed area; that it had existing infrastructure in the area (including the Mooikloof 132 kV/11 kV sub-station); that it intended further infrastructure development; and that an Eskom licence expansion would have significant revenue implications. The court treated these contentions as part of the context presented to NERSA, while the dispositive factual consideration for the outcome was the licensing position: the Farm was listed in Tshwane’s Schedule 1, and Eskom’s licensed position was limited to legacy customers.


Internally within NERSA, the judgment recorded that, at NERSA’s Electricity Subcommittee Meeting on 10 February 2023, members repeatedly raised concerns that the same area remained listed in Tshwane’s licence and indicated a view that Tshwane’s licence should first be amended to remove the area before it could be included in Eskom’s licence. It was common cause that no amendment to Tshwane’s licence was ever made or applied for. Despite the stated procedural concern, NERSA approved Eskom’s licence amendment on 10 February 2023.


A factual dispute arose in relation to a supplementary affidavit filed by Eskom in the review proceedings, which relied on a township establishment condition allegedly directing the developer to plan with Eskom as the licensed supplier. Tshwane opposed the admission of this affidavit on the basis that the information was not before NERSA when it made the decision. The court agreed with Tshwane and did not admit the supplementary affidavit, holding that the review had to be assessed on the record before NERSA at the time of the decision.


3. Legal Issues


The central legal questions were whether NERSA’s decision to amend Eskom’s distribution licence to include the Mooikloof Mega City development on Farm Rietfontein 375-JR was lawful and authorised, given that the Farm was already included in Schedule 1 to Tshwane’s distribution licence, and given the statutory framework governing licence amendments.


A connected legal question was whether the Farm (or undeveloped parts of it) could properly be treated as a “greenfield” area under NERSA’s Internal Electricity Licence Procedure, in a way that would take it outside Tshwane’s existing licensed area of supply for licensing purposes.


The dispute was primarily one of application of law to fact within the administrative-law framework: the material facts concerned the content and effect of the respective licences, the absence of any amendment to Tshwane’s licence, and the regulator’s power under the Electricity Regulation Act to amend licences. It also entailed a legal characterisation issue (whether the Farm could be characterised as greenfield) and a lawfulness inquiry under PAJA into whether the decision was authorised by the empowering provisions, and whether it was otherwise unlawful or unconstitutional.


A further legal issue arose as to the proper framework for review. Tshwane invoked PAJA and also the principle of legality, but the court had to determine whether PAJA provided the applicable basis without the need for an additional legality review. Ancillary issues included whether alleged procedural unfairness and delay in notification rendered the decision reviewable, and whether the developer (Balwin Properties) had to be joined due to a direct and substantial interest in the relief sought.


4. Court’s Reasoning


The court approached the matter as a review of administrative action. It held that, by operation of section 10(3) of the National Energy Regulator Act 40 of 2004 and section 31 of the Electricity Regulation Act 4 of 2006, NERSA’s decision was reviewable in accordance with the Promotion of Administrative Justice Act 3 of 2000 (PAJA). Relying on the Constitutional Court’s confirmation in Bato Star Fishing (Pty) Ltd v Minister of Environmental Affairs and Tourism and Others [2004] ZACC 15; 2004 (4) SA 490 (CC), the court treated PAJA (and specifically PAJA review grounds) as the appropriate framework and held that a separate legality review was not required.


The court identified the “nub” of the dispute as whether Tshwane’s licence conferred, for the non-legacy parts of the Farm, an exclusive right to supply electricity, such that any attempt to license Eskom for additional parts necessarily required a corresponding contraction of Tshwane’s licensed area. The court reasoned that the original licensing arrangement was designed so that the two licences together covered 100% of the Farm: Eskom’s licence covered only the specified legacy customers, and Tshwane’s licence covered the remaining area (with an express exclusion for those existing Eskom customers). On that footing, extending Eskom’s licensed area into the remaining parts of the Farm without simultaneously amending Tshwane’s licence created an impermissible overlap. The court considered this logical consequence decisive: an amendment expanding Eskom’s portion necessarily required an amendment removing that portion from Tshwane’s Schedule 1 area.


The court then measured NERSA’s conduct against the empowering provisions of the Electricity Regulation Act, focusing on section 16, which governs licence amendments. While Eskom applied to amend its own licence under section 16(1)(a), the court regarded it as fundamental that no application was made to amend Tshwane’s licence, nor was Tshwane’s permission obtained in relation to any change affecting its licenced area. The court also referred to section 17, governing revocation on application by a licensee, noting that no such application had been made by Tshwane. The court treated NERSA’s own subcommittee concerns recorded on 10 February 2023 as reinforcing that NERSA appreciated the problem of licensing the same area to two distributors, yet proceeded regardless.


NERSA attempted to justify its approach by characterising the Farm (insofar as it was undeveloped) as a “greenfield” area under its Internal Electricity Licence Procedure rules. The court rejected that contention as inconsistent with the rule definition. The rules defined greenfield as an area outside an existing licensed area of supply and that has never had an electrical connection. The court held that Farm Rietfontein 375-JR had been within Tshwane’s licensed area since 2011, and therefore could not be “outside” an existing licensed area of supply. The greenfield characterisation could not, on the court’s reasoning, be used to take the area outside the ambit of Tshwane’s existing licence.


On Tshwane’s argument that Eskom’s application failed to comply with section 10 of the Electricity Regulation Act (which sets out requirements for a licence application), the court held that section 10 applied to initial licence applications rather than an amendment application brought by an existing licensee. The court reasoned that requiring Eskom, in seeking a licence amendment, to comply as if it were making a first licence application would be impractical and unreasonable, and that it was for NERSA to call for information it needed to decide the amendment. This ground of review was therefore rejected.


The court also relied on the principle that administrative decisions must be made on the basis of material facts properly before the decision-maker, citing Pepcor Retirement Fund and Another v Financial Services Board and Another 2003 (6) SA 38 (SCA) on material mistake of fact as a basis for review. However, the court treated the core defect as not remedied by later information. In this context, Eskom’s supplementary affidavit was excluded because the review had to be assessed through the lens of the record before NERSA when the decision was taken.


The court rejected NERSA’s and Eskom’s argument that electricity supply (and specifically reticulation) does not fall within the exclusive jurisdiction of municipalities and that Tshwane’s reliance on section 156(1)(a) of the Constitution was incorrect. The court stated that the Constitution confers executive authority over electricity reticulation on municipalities, and that the Electricity Regulation Act recognises and gives effect to this constitutional position. The court held that NERSA ought not to have approved Eskom’s licence amendment without addressing whether the amendment was permissible in the absence of an amendment to Tshwane’s licence, and without addressing Tshwane’s constitutional position. This failure was treated as fundamental to the decision’s lawfulness.


Several additional grounds were advanced but not upheld as necessary to determine the review. On procedural unfairness due to delayed notification, the court accepted that Tshwane was not timeously informed in accordance with the distribution licence procedure, but held that Tshwane participated meaningfully once aware and that the process was procedurally compliant thereafter; the court noted Tshwane’s concession which disposed of the ground. On the statutory 120-day timeframe issue, the court held that the delay did not establish prejudice and would not, by itself, justify review in the circumstances.


On joinder, the court rejected the contention that the developer (Balwin Properties) should have been joined. Applying the principle stated in Lebea v Menye and Another 2023 (3) BCLR 257 (CC), the court held that a party must have a direct and substantial interest in the order sought, not merely an interest in the court’s reasoning or findings. The court held that Balwin’s interest was limited to the supply of electricity, not who supplied it, and therefore did not warrant joinder.


5. Outcome and Relief


The court granted the relief sought by Tshwane. It issued a declarator that the Mooikloof Mega City, insofar as it is located on Farm Rietfontein 375-JR, is included in Schedule 1 to Tshwane’s electricity distribution licence NER/D/TSHWANE granted on 13 October 2011.


It further declared that NERSA’s decision of 10 February 2023 to include the Mooikloof Mega City (on Farm Rietfontein 375-JR) in Eskom’s licensed area of supply was unlawful and invalid, and the decision was reviewed and set aside.


On costs, the court ordered that NERSA and Eskom pay Tshwane’s costs jointly and severally, on the party-and-party scale, including the costs of two counsel, with such costs to be taxed on Scale C.


Cases Cited


The judgment referred to Bato Star Fishing (Pty) Ltd v Minister of Environmental Affairs and Tourism and Others [2004] ZACC 15; 2004 (4) SA 490 (CC). It also referred to Glencore Operations South Africa (Pty) Ltd v NERSA 2023 JDR 4386 (GJ), Joseph v City of Johannesburg 2010 (4) SA 55 (CC), and Eskom Holdings SOC Ltd v Vaal River Development Association (Pty) Ltd 2023 (4) SA 325 (CC).


In addition, the judgment cited MEC for Environmental Affairs and Development Planning v Clairison’s CC 2013 (6) SA 235 (SCA), Pepcor Retirement Fund and Another v Financial Services Board and Another 2003 (6) SA 38 (SCA), Johannesburg Metropolitan Municipality v Gauteng Development Tribunal 2010 (6) SA 182 (CC), and Lebea v Menye and Another 2023 (3) BCLR 257 (CC).


Legislation Cited


The judgment referenced the Constitution of the Republic of South Africa, 1996, particularly section 155(2)(a), section 156(1)(a), and Part B of Schedule 4 (electricity and gas reticulation). It cited the National Energy Regulator Act 40 of 2004, including section 10(3) and section 10(1)(a), (b), (d), (e), and (f). It cited the Electricity Regulation Act 4 of 2006, including sections 10, 11, 12, 13(1), 16(1), 17, 27, 31, and 35.


It also referred to the Promotion of Administrative Justice Act 3 of 2000, and to the Local Government: Municipal Structures Act 117 of 1998. The judgment further referenced the Intergovernmental Relations Framework Act 13 of 2005, including the mechanism contemplated by section 42(1)(d).


Rules of Court Cited


The judgment referred to Rule 28(1) in the context of the joinder principle discussed in Lebea v Menye and Another 2023 (3) BCLR 257 (CC).


Held


The court held that Farm Rietfontein 375-JR, including the Mooikloof Mega City insofar as it is situated on that Farm, was included in Schedule 1 of Tshwane’s existing electricity distribution licence, subject only to the express exclusion of existing Eskom-supplied customers at the commencement of Tshwane’s licence. On the court’s reasoning, NERSA could not lawfully approve an amendment expanding Eskom’s licensed area into that Farm without a corresponding lawful change to Tshwane’s licence (or Tshwane’s permission, or a statutory revocation mechanism being invoked), because doing so created an impermissible overlap of licensed areas.


The court held that NERSA’s attempt to treat the undeveloped portions of the Farm as a “greenfield” area under NERSA’s internal licensing procedures was inconsistent with the definition of greenfield, because the area was not outside an existing licensed area of supply and had been included in Tshwane’s licensed area since 2011.


The court held further that the review fell to be determined under PAJA as the applicable review framework by operation of the National Energy Regulator Act and the Electricity Regulation Act. It set aside the decision taken on 10 February 2023 as unlawful and invalid. It also held that additional grounds advanced (including delayed notification and the 120-day period point) did not provide a basis for relief on the facts, and that the developer did not have to be joined because it lacked a direct and substantial interest in the order sought.


LEGAL PRINCIPLES


The judgment applied the principle that, where legislation provides that decisions of a regulator constitute administrative action reviewable under PAJA, the review should proceed within PAJA’s framework rather than through a separate legality enquiry, particularly where the grounds of review are addressed by PAJA.


It applied the principle that an administrative decision must be taken consistently with the empowering statute and must be authorised by law, and that a licensing authority may not approve regulatory outcomes that result in an impermissible overlap of licensed areas where the statutory scheme requires proper amendment or revocation processes to adjust existing rights and obligations.


The judgment applied the principle that a regulator’s decision must be made on the basis of the material information properly before it at the time the decision was taken, and that a review is assessed by reference to the contemporaneous record. On this approach, post-decision information introduced in review proceedings (and not before the decision-maker) does not provide a basis to validate an otherwise defective administrative decision, and may be excluded when it is inconsistent with the record-based nature of review.


It applied the principle (in the joinder context) that joinder depends on a party having a direct and substantial interest in the order sought, and that an interest in the reasoning or in collateral consequences, without an interest in the order itself, is insufficient.


Finally, the judgment reflected the constitutional and statutory principle that municipalities have executive authority over electricity reticulation within their jurisdictions (as recognised by the Constitution and the Electricity Regulation Act), and that regulatory decision-making affecting municipal reticulation competence must properly account for that constitutional position within the licensing framework.

About SAFLII
Databases
Search
Terms of Use
RSS Feeds
South Africa: North Gauteng High Court, Pretoria
You are here:
SAFLII
>>
Databases
>>
South Africa: North Gauteng High Court, Pretoria
>>
2026
>>
[2026] ZAGPPHC 530
|
Noteup
|
LawCite
City of Tshwane Metropolitan Municipality and Another v National Energy Regulator of South Africa and Others (2023-072548) [2026] ZAGPPHC 530 (8 June 2026)
Download original files
PDF format
RTF format
IN THE HIGH COURT
OF SOUTH AFRICA
(GAUTENG DIVISION,
PRETORIA)
Case
No. 2023-072548
(1) 
REPORTABLE:
YES
/
NO
(2) 
OF INTEREST TO OTHER JUDGES:
YES
/
NO
(3)  REVISED
DATE:
8 June
2026
SIGNATURE:
In
the matter between:
CITY
OF TSHWANE METROPOLITAN MUNICIPALITY
FIRST
APPLICANT
THE
CITY OF TSHWANE CITY MANAGER
SECOND
APPLICANT
And
NATIONAL
ENERGY REGULATOR OF SOUTH
AFRICA
FIRST
RESPONDENT
ESKOM
HOLDINGS SOC LIMITED
SECOND
RESPONDENT
SOUTH
AFRICAN LOCAL GOVERNMENT ASSOCIATION
THIRD
RESPONDENT
THE
MINISTER OF ELECTRICITY MR.
RAMOKGOPA
FOURTH
RESPONDENT
THE
MINISTER OF MINERAL RESOURCES AND ENERGY
FIFTH
RESPONDENT
THE
MINISTER OF CO-OPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS
SIXTH
RESPONDENT
NATIONAL
TREASURY
SEVENTH
RESPONDENT
Coram:
Millar
J
Heard
on:
16
April 2026
Delivered:
8
June 2026 - This judgment was handed down electronically by
circulation to the parties' representatives by email,
by being
uploaded to the
CaseLines
system of the GD and
by release to SAFLII. The date and time for hand-down is deemed
to be 15H30 on 8 June 2026.
JUDGMENT
MILLAR J
[1]
This is an application to review and set
aside the decision of the first respondent (Nersa) to amend the
Electricity Distribution
Licence (Edl) granted to the second
respondent (Eskom) to include in it the Mooikloof Mega City
Development. The decision was made
on 10 February 2023.
[2]
The applicants (Tshwane) seek two orders:
[2.1]      
A declaration that the Mooikloof Mega City, Rietfontein 375-JR, is an
area included in
Schedule 1 to Tshwane's electricity licence number
NER/D/TSHWANE granted by Nersa on 13 October 2011; and
[2.2]      
A declarator that Nersa's decision of 10 February 2023 to include the
Mooikloof Mega City,
Rietfontein 375-JR into Eskom's licensed area of
supply be declared unlawful, invalid, and reviewed and set aside.
[3]
Tshwane
brings the review under section 10(3) of the National Energy
Regulator Act
[1]
(NERA), read
together with section 31 of the Electricity Regulation Act
[2]
(ERA), and on the principle of legality. The orders are opposed by
both Nersa and Eskom.
[4]
The Farm Rietfontein 375-JR (the Farm) is
part of the site of the Mooikloof Mega City Development.
Historically, this area fell
under the jurisdiction of the Kungwini
Local Municipality, which was subsequently dis-established. In 2008,
the entire area was
transferred to the municipal authority of
Tshwane.
[5]
On 22 September 2011, Nersa granted Tshwane
an electricity distribution licence listing the Farm as one of the
areas for electricity
supply. The Farm appears in Schedule 1 to the
licence as "
1926 Rietfontein
375-JR,"
which also encompasses
subdivided portions of the Farm.
[6]
At the time the licence was granted to
Tshwane, several existing customers within the generally undeveloped
area of the Farm had
historically been supplied by Eskom. Eskom was
separately licensed to continue supplying those legacy customers.
Tshwane's licence
expressly excluded those customers in that it
provided:
"The
municipal area of City of Tshwane (as per City of Tshwane's map as
submitted with the licence amendment application).
Customers being
supplied by Eskom or any other licensed distributor at the date of
commencement of this licence are excluded from
this licence."
[7]
The balance of the Farm — being
predominantly undeveloped land — was licensed to Tshwane. The
Eskom licence was one
of expedience and practicality, granted because
at the time of transfer, Tshwane did not have the infrastructure
presence to take
over those customers' supply.
[8]
On 25 March 2021, Eskom applied to Nersa to
amend its Edl to include the Mooikloof Mega City development insofar
as it related to
the area of the Farm over which it held no licence.
[9]
Tshwane, the licensed distributor for the
area, only became aware of this application through social media and
newspaper reports
on 17 and 18 March 2022, nearly a year later, when
Nersa invited public consultation and participation in its
consideration of
the application. Nersa did not officially inform
Tshwane until 25 March 2022 of Eskom's application.
[10]
On 28 March 2022, Tshwane wrote to Nersa
asserting that:
[10.1]        
the Farm fell within its licensed area, that it already had
electricity supply
infrastructure in the area which included the
Mooikloof 132 kV/11 kV sub-station;
[10.2]        
it intended to develop a second sub-station (the Zwavelpoort
sub-station)
and it was amenable to granting permission for
alternative distributors, including Eskom, to supply customers where
it was unable
to do so and
[10.3]        
it had concerns about the significant revenue impact on it of any
licence
amendment.
[11]
On 11 April 2022, Tshwane attended the
public hearing and presented its case fully.
[12]
During the public hearing, Tshwane informed
Nersa of the following:
[12.1]        
Tshwane is a Category A City with executive and legislative authority
under
section 155(2)(a) of the Constitution and the Municipal
Structures Act.
[3]
[12.2]        
Under section 156(1)(a) of the Constitution, municipalities have
executive
authority over electricity reticulation, which falls under
Part B of Schedule 4, a concurrent national and provincial
legislative
competence with local government executive and
legislative authority.
[12.3]        
Tshwane holds licence NER/D/TSHWANE, obliging it to operate the
distribution
facility within Schedule 1 and to distribute and supply
electricity to all customers and end users within that area. Its
license
also entitled it to supply electricity in accordance with its
approved electrification plan and that it would not cede or transfer

any licence power without Nersa's prior consent.
[12.4]        
No permission had been sought from Tshwane under section 16(1)(b) of
ERA
for any amendment to its licence in connection with the Mooikloof
Mega City inclusion.
[12.5]        
The Mooikloof Mega City falls within Tshwane's Region 6. While the
area's
agricultural holdings had historically been supplied by Eskom,
any new township developments were to be supplied by Tshwane
consistent
with its executive and legislative authority.
[12.6]        
Bulk electricity supply in the Eastern Suburbs, although severely
limited,
was being addressed by Tshwane through the construction of
the Wildebees Infeed Station, scheduled for commissioning in 2025.
Once
commissioned, it would alleviate the burden on the Nyala Infeed
Station and create sufficient capacity to supply all 50 000 units
of
the Mooikloof Mega City Development.
[12.7]        
Full implementation of the 50 000-unit development was estimated to
yield
approximately R125 million per month in electricity revenue (at
an average household consumption of R2 500 per month). The loss
of
revenue, if the license was granted to Eskom, would be significant
for Tshwane.
[13]
At Nersa’s Electricity Subcommittee
Meeting of 1 December 2022, it was observed that Eskom's application
lacked any legal
argument addressing Tshwane's constitutional rights
and obligations regarding the executive control over electricity
distribution
within its jurisdiction. This observation was not taken
any further after a legal opinion was obtained that reticulation had
"not been defined to a point where
it is deemed as constitutionally acceptable."
[14]
At the Electricity Subcommittee Meeting of
10 February 2023, members
repeatedly
raised concerns that the same area was still listed in Tshwane's
licence:
"Procedurally,
Members queried whether the inclusion of one area in another
licensee's (Eskom's) licence could be considered
when the same area
was still in another licensee's (City of Tshwane) licence. Members
were of the view that the City of Tshwane's
licence should be first
amended to remove the area before including it in Eskom's
distribution licence."
No such amendment to
Tshwane's licence was ever made or applied for.
[15]
Despite these concerns, Nersa approved
Eskom's licence amendment on 10 February 2023.
[16]
Section 156(1)(a) of the Constitution
confers on municipalities executive authority over local government
matters listed in Part
B of Schedule 4, which includes electricity
reticulation. The ERA defines a municipality accordingly as one that:
"has executive
authority over and the right to reticulate electricity within its
area of jurisdiction in terms of the Municipal
Structures Act."
[17]
Section 27 of ERA, specific to
municipalities such as Tshwane, provides as follows:

(1)      
Each City must exercise its executive authority and perform its duty
by–
(a)
Complying with all the technical and
operational requirements for electricity networks determined by the
Regulator;
(b)
Integrating its reticulation
services with its integrated development plans;
(c)
Preparing, implementing and
requiring relevant plans and budgets;
(d)
Progressively ensuring access to at
least basic reticulation services through appropriate investments in
its electricity infrastructure;
(e)
Providing basis reticulation
services free of charge or at a minimum cost to certain classes of
end users within its available resources;
(f)
Ensuring sustainable reticulation
services through effective and efficient management and adherence to
the national norms and standards
contemplated in section 35;
(g)
Regularly reporting and providing
information to the Department of Provincial and Local Government, the
National Treasury, the Regulator
and customers;
(h)
Executing its reticulation function
in accordance with relevant national energy policies; and
(i)
Keeping separate financial
statements, including a balance sheet of the reticulation business.”
[18]
Section
10 of ERA sets out the requirements for a licence application.
Section 11 requires advertising of an application and obliges
Nersa
to consider objections.
[4]
Section 12 requires that an applicant be furnished with all
substantiated objections to allow response. Section 13(1) requires
a
decision within 120 days from advertisement (or from any request for
additional information following objections).
[19]
Section 16 of ERA governs licence
amendments. Section 16(1) of ERA provides:
"(1)
The Regulator may vary, suspend or remove any licence condition, or
may include additional conditions— (a) on application
by the
licensee; (b) with the permission of the licensee; (c) upon
non-compliance by a licensee with a licence condition; (d) if
it is
necessary for the purposes of this Act; or (e) on application by any
affected party."
[20]
Section 17 of ERA governs the revocation of
a licence on application by a licensee in prescribed circumstances.
No such application
was ever made by Tshwane.
[21]
Nersa approved and published its Internal
Electricity Licence Procedure (the Rules) on 13 April 2012 pursuant
to section 35 of ERA.
Rule 2.1 states that the purpose of the Rules
is to

outline the administrative
procedure that will apply in the processing of electricity
distribution licence applications made in
terms of sections 4, 7, 16
and 17 of the Act.”
[22]
The Rules define
"greenfield"
as:
"an area
that is outside of an existing licensed area of supply (AoS) that has
never had any electrical connection, has potential
for development
and/or potential to be rezoned and/or proclaimed to require
electricity connection(s)."
[23]
The Rules further distinguish between a
"licensed area of supply"
(a
NERSA-approved area referred to in Schedule 1 of an issued licence)
and a
"licensable area of supply"
(a specific area, whether greenfield or
brownfield, that is eligible for licensing).
[24]
These are mutually exclusive designations.
Once an area is licensed, it is no longer licensable unless the
licence is amended under
section 16 or revoked under section 17. A
licensable area is one that has never been licensed, or one in
respect of which a licence
has been revoked but no new licence has
yet been granted.
[25]
Section
10(3) of NERA provides that any person may institute proceedings in
the High Court for judicial review of an administrative
action by the
Energy Regulator in accordance with the Promotion of Administrative
Justice Act
[5]
(PAJA). Section
31 of ERA applies section 10(3) of NERA to every decision of the
Regulator under ERA (except where ERA provides
otherwise, or the
Regulator sits as a tribunal).
[26]
Section
10 of NERA further requires that every Nersa decision must be:
“consistent with the Constitution and all applicable
laws”
[6]
;
“in the public interest”
[7]
;
“procedurally fair”
[8]
;
and “based on reasons, facts and evidence that must be
summarized and recorded”
[9]
and “explained clearly as to its factual and legal basis and
the reasons therefore”
[10]
.
[27]
In
Bato
Star Fishing (Pty) Ltd v Minister of Environmental Affairs and
Tourism and Others
,
[11]
the Constitutional Court confirmed that section 6 of PAJA codifies
the grounds of judicial review of administrative action and
that
causes of action for the review of administrative action ordinarily
arise from PAJA, grounded in the Constitution.
[28]
Since
the decision of Nersa is an administrative action reviewable under
PAJA by operation of sections 10(3) of NERA and 31 of ERA,
PAJA,
specifically sections 6(2)(c)
[12]
,(f)
[13]
and (i)
[14]
provides the
appropriate framework for this application. A separate legality
review is accordingly not required.
[29]
In
Glencore
Operations South Africa (Pty) Ltd v NERSA
,
[15]
Senyatsi J affirmed that local government has executive authority and
the right to administer electricity reticulation and may
make and
administer by-laws for its effective administration. ERA permits
local government to exercise power in respect of electricity
supply,
including providing basic reticulation services free of charge or at
minimum cost to certain end users, ensuring sustainable
reticulation
services, reporting to National Treasury and Nersa, and keeping
separate financial statements.
[30]
In
Joseph
v City of Johannesburg
,
[16]
the Constitutional Court held that:
"The provision of
basic municipal services is a cardinal function, if not the most
important function, of every municipal government.
The central
mandate of local government is to develop a service delivery capacity
in order to meet the basic needs of all inhabitants
of South Africa,
irrespective of whether or not they have a contractual relationship
with the relevant public service provider."
[31]
In
Eskom
Holdings SOC Ltd v Vaal River Development Association (Pty) Ltd
,
[17]
the Constitutional Court set out the complementary roles of Eskom and
municipalities. Municipalities have constitutional and statutory

duties to procure bulk electricity (as Eskom's customers under ERA)
and to supply electricity to residents as end users. Furthermore,
ERA
gives effect to those constitutional duties through the obligations
imposed by section 27 and Nersa enjoys the power to regulate
the
licensees which would otherwise enjoy a monopoly on power.
[32]
The nub of the dispute is whether Tshwane
holds, by virtue of its licence, an exclusive right to supply
electricity to all areas
of the Farm not previously supplied by
Eskom's legacy customers.
[33]
Tshwane's licence covered all portions of
the Farm where there were no historical Eskom customers, while
Eskom's licence was limited
exclusively to those specific legacy
customers. It follows, as a matter of logic, that any extension of
Eskom's licence to additional
areas of the Farm necessarily required
a corresponding amendment to Tshwane's licence to remove those areas
from its scope. It
is for this reason that the licence granted by
Nersa in this case was exclusive.
[34]
In the present case, Eskom applied to amend
its own licence under section 16(1)(a) of ERA. However, what did not
occur was any application
to amend Tshwane's licence. The combination
of both licences on their original terms was intended to cover 100%
of the Farm. Expanding
Eskom's portion without contracting Tshwane's
portion creates an impermissible overlap.
[35]
Nersa was aware of the terms of both
licences when Eskom applied. The Subcommittee itself queried
procedurally whether an area could
be included in Eskom's licence
while it remained in Tshwane's licence and noted that Tshwane's
licence should first be amended.
No such amendment was ever sought or
made.
[36]
Nersa asserted that the Farm constitutes a
greenfield area under the Rules. This assertion was made to try and
take the area of
the Farm (which falls under Tshwane’s licence)
which was undeveloped, outside of the ambit of the license. This
contention
is not supported by the Rules. A greenfield, as defined,
is an area outside of an existing licensed area of supply that has
never
had any electrical connection. The Farm has been within
Tshwane's licensed area since 2011. It is not outside any existing
licensed
area, and therefore cannot be characterized as a greenfield.
[37]
Moreover, Nersa's argument that farms
should not be regarded as part of Tshwane's Schedule 1 is also
irreconcilable with its prior
approval of tariffs for those Farms.
[38]
Tshwane
also argued that Eskom failed to comply with the requirements of
section 10 of ERA when it submitted its application, which
in
addition to the failure to apply to amend or revoke Tshwane’s
licence, also rendered Nersa's decision
ultra
vires
.
Section 10 applies to initial applications, which this was not. Eskom
was already in possession of a license and sought to amend
it. The
application to amend can hardly be said to be on the same footing as
a first application. To require Eskom in seeking to
amend its
application, to start from the beginning seems to me to be entirely
impractical and unreasonable. It was for Nersa, given
the exigencies
of the application, to call for the information that it needed to
properly consider it.
[18]
For
this reason, I am not persuaded that this ground of review has any
merit.
[39]
In
Pepcor
Retirement Fund and Another v Financial Services Board and
Another,
[19]
it was held:

In
my view, a material mistake of fact should be a basis upon which a
Court can review an administrative decision. If legislation
has
empowered a functionary to make a decision, in the public interest,
the decision should be made on the material facts which
should have
been available for the decision properly to be made. And if a
decision has been made in ignorance of facts material
to the decision
and which therefore should have been before the functionary, the
decision should . . . be reviewable . . .The doctrine
of legality . .
. requires that the power conferred on a functionary to make
decisions in the public interest, should be exercised
properly, i.e.
on the basis of the true facts:  it should not be confined to
cases where the common law would categorize the
decision as ultra
vires.”
[40]
This
principle applies here. Nersa's decision was made without full
material information before it and in particular, the information

contained in Eskom's supplementary affidavit (regarding Tshwane's
township establishment condition directing Balwin Properties
to
Eskom). While that information might have been relevant, it does not
cure the fundamental defect. Nersa approved Eskom's licence
amendment
without simultaneously amending Tshwane's licence, or obtaining
Tshwane's consent, or requiring Tshwane to apply for
the revocation
of its licence in terms of section 17 of ERA.
[20]
[41]
In its supplementary affidavit, Eskom
relied on a condition that Tshwane had imposed for the establishment
of the Mooikloof Mega
City, which directed the township owner to plan
with Eskom as
"the licensed
supplier of electricity in the township."
Tshwane
opposed admission of this affidavit, primarily on the basis that this
information was not before Nersa when the impugned
license was
granted. I agree and the supplementary affidavit is not admitted.
[42]
The decision under review must be assessed
solely through the lens of the record before Nersa at the time. This
information was
not before Nersa when it made its decision.
[43]
Nersa
and Eskom argued that electricity supply does not fall within the
exclusive jurisdiction of municipalities and that Tshwane's

interpretation of section 156(1)(a)
[21]
of the Constitution is incorrect. This contention is rejected. The
Constitution unequivocally confers executive authority and
jurisdiction over electricity reticulation on Tshwane. ERA expressly
recognises and gives effect to this constitutional position.
Nersa
ought not to have approved Eskom's licence amendment without either
addressing whether or not this was permissible in the
absence of an
amendment to Tshwane’s licence and also the constitutional
position of Tshwane. This was fundamental to the
consideration of
whether to approve Eskom’s application. This is the nub of the
review and why it must succeed.
[44]
Several further grounds were advanced by
Tshwane for the review. Both Nersa and Eskom refuted these. I am not
persuaded that these
are necessary or meritorious for the following
reasons:
[44.1]        
It was asserted that there had been procedural unfairness due to
delayed
notification. Tshwane only became aware of Eskom's
application through media reports nearly a year after it was filed.
The distribution
licence procedure required that a copy of any
application be forwarded to other licensees operating in the
vicinity, which was
not done timeously. However, once Tshwane became
aware of the process, it made its views known and participated
meaningfully at
every stage. Nersa conducted the process in a
procedurally compliant manner, and Tshwane's own concession on this
point disposes
of this ground.
[44.2]        
It was asserted that the decision to grant Eskom’s license, was
made
outside the 120 days provided for. This ground ignores that
between Eskom's application (25 March 2021) and Tshwane's
notification
(March 2022), nothing of consequence occurred. From the
time Tshwane was notified, it participated fully and so no prejudice
arises
from the delay and this ground alone would, to my mind, be
insufficient to find that the decision to grant Eskom its license is

reviewable.
[45]
Eskom
and Nersa also both initially argued that the present application was
doomed to failure in that as Organs of State, Tshwane
and Nersa ought
to have attempted to resolve the dispute in terms of the
Intergovernmental Relations Framework Act.
[22]
This argument was not pursued at the hearing as the parties had
subsequent, to the issue of the application, endeavored to resolve

the matter through this mechanism.
[23]
[46]
Eskom and Nersa also argued that the
declaratory order sought was limited in geographic scope. It was
argued that because the Mooikloof
Mega City extends beyond the Farm
Rietfontein 375-JR onto other Farms not in Tshwane's licensed area,
the declaratory orders sought
have no basis. This ground is not
persuasive. The orders sought relate only to the licensed area and
could never be in respect
of areas not specifically included within
Tshwane's licensed area. The orders are accordingly appropriately
framed.
[47]
It
was also argued that the developer (Balwin Properties) of the
Mooikloof Mega City, ought to have been joined. This ground is

summarily rejected. Balwin Properties does not have a direct and
substantial interest in the order sought. The law in this regard
is
clear as set out in
Lebea
v Menye and Another
.
[24]
An interest in the court's reasoning or findings, as opposed to the
order itself, is insufficient for joinder. The only interest
that
Balwin Properties has is in the supply of electricity to the
development. It has no interest in who supplies that electricity.
[48]
For the reasons set out above, the decision
taken by Nersa on 10 February 2023 is declared unlawful and invalid
and is reviewed
and set aside.
[49]
Regarding costs, given the nature and
importance of this matter to all parties, engagement of more than one
counsel was a wise and
reasonable precaution. Costs are ordered on
Scale C, including costs of two counsel.
[50]
In the circumstances, I make the following
order:
[50.1]        
It is declared that the Mooikloof Mega City, insofar as it is located
upon
Farm Rietfontein 375-JR, is an area included in Schedule 1 of
the City of Tshwane's electricity licence number NER/D/TSHWANE
granted
by the first respondent on 13 October 2011 for the operation
of a distribution facility.
[50.2]        
It is declared that the first respondent's decision taken on 10
February
2023 to include the Mooikloof Mega City, insofar as it is
located upon Farm Rietfontein 375-JR, into the second respondent's
licensed
area of supply, is declared unlawful, invalid and is
reviewed and set aside.
[50.3]        
The first and second respondents are jointly and severally, the one
paying
the other to be absolved, ordered to pay the costs of the
applicant on the scale as between party and party, which costs are to

include the costs consequent upon the engagement of two counsel upon
Scale C.
A MILLAR
JUDGE
OF THE HIGH COURT
GAUTENG DIVISION,
PRETORIA
HEARD
ON:                                                 

            16
APRIL 2026
JUDGMENT DELIVERED
ON:                             

08 JUNE 2026
FOR THE APPLICANTS
COUNSEL:              
                                               

ADV. M RIP SC
ADV. T
MAKOLA
INSTRUCTED
BY:                                                  

MAHUMANI INCORPORATED
REFERENCE:                                                         

MS. K MTHETHWA
FOR THE FIRST
RESPONDENT
COUNSEL:                                      

           
           

ADV. N MAENETJE SC
ADV. T
CHARLIE
INSTRUCTED
BY:                                                  

PRINCE MUDAU & ASSOCIATES
REFERENCE:                                                         

MS. D MOKWENA
FOR THE SECOND
RESPONDENT
COUNSEL:                                                              

ADV. M MAKOTI
ADV. L
RAKGWALE
INSTRUCTED
BY:                                                  

MAPONYA INCORPORATED
REFERENCE:                                                         

MS. P LEDWABA
NO APPEARANCE FOR
THE THIRD TO SEVENTH RESPONDENTS
[1]
Act
40 of 2004. The section provides “
Any
person may institute proceedings in the High Court for the judicial
review of an administrative action by the Energy Regulator
in
accordance with the Promotion of Administrative Justice Act, 2000
(Act 3 of 2000.)”
[2]
Act
4 of 2006. The section provides “
Section
10(3) of the National Energy Regulator Act applies to every decision
taken by the Regulator in terms of this Act, except
where this Act
provides otherwise or whether the Regulator sits as a tribunal, in
which case section 10(4) of that Act applies.”
[3]
Act
117 of 1998.
[4]
Section
11(4) of ERA.
[5]
Act
3 of 2000.
[6]
Section
10(1)(a) of NERA.
[7]
Section
10(1)(b) of NERA.
[8]
Section
10(1)(d) of NERA.
[9]
Section
10(1)(e) of NERA.
[10]
Section
10(1)(f) of NERA.
[11]
[2004] ZACC 15
;
2004
(4) SA 490
(CC) at para
[25]
.
[12]

The
action was procedurally unfair.”
[13]

The
action itself – (i) contravenes a law or is not authorised by
the empowering provision.”
[14]

The
action is otherwise unconstitutional or unlawful
.”
[15]
2023
JDR 4386 (GJ) at paras [31] - [32].
[16]
2010
(4) SA 55
(CC) at para [34].
[17]
2023
(4) SA 325
(CC). See the minority judgment of Unterhalter AJ at
paras [83]-[87].
[18]
MEC
for Environmental Affairs and Development Planning v Clairison’s
CC
2013 (6) SA 235
(SCA) at para [22].
[19]
2003
(6) SA 38
(SCA) at para [47].
[20]
Johannesburg
Metropolitan Municipality v Gauteng Development Tribunal
2010 (6) SA 182
(CC) at para [91].
[21]
The
section provides that a City “
has
executive authority in respect of and has the right to administer –
(a) the local government matters listed in part
B of schedule 4 and
part B of schedule 5.”
Part
B of schedule 4 specifically lists “
Electricity
and gas reticulation.”
[22]
Act
13 of 2005.
[23]
In
terms of a court order granted on 22 August 2025, a facilitator was
appointed by the parties as envisaged by the provisions
of Section
42(1)(d) of the Intergovernmental Relations Framework Act.  By
the time the application was heard however, the
efforts to settle
the dispute had been unsuccessful and a certificate to this effect
was filed in court on 13 January 2026.
[24]
2023
(3) BCLR 257
(CC) (CC) at para [30] in which it was stated: ““
The
word “interest” in rule 28(1) has been interpreted to
mean a direct and substantial interest which a person is
required to
have in the subject matter before he or she can be said to have
locus standi in such a matter or before such a person
may be jointed
or be allowed to be joined in proceedings.  Direct and
substantial interest is a direct and substantial interest
in the
order that a court is asked to make in a matter.  It is not
enough if a person has an interest in a finding or in
certain
reasons for an order.   The interest must be in the order
or the outcome of the litigation.